Tender Value
₹9.9 Cr
EMD Value
₹9.9 L
Closing Date
7 Sept 2026, 3:30 pmClosed
CE R and B State Roads
Mahabubnagar
Improvements to Existing single lane to PWD road to YIIR school via Dhamgnapur from Km 0/0 to 4/0 (Actual length 3.8 Kms) in Mahabubnagar District.
729239
1606/CTN/DCE(R)/EE(R)/DEE-III/AEE-III/2026-27, Dt:14-08-2026
OPEN
Road Work
MAHABUBNAGAR, TELANGANA
14 documents required · 13 mandatory · 1 optional
₹11,800
₹9.9 L
31 Aug 2026
31 Aug 2026
31 Aug 2026
Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, up to a lead of 1000 metres including removal and disposal of top organic soil not exceeding 150 mm in thickness by Mechanical means as per the Techinical Specification Clause 201 MoRTH 5th Revision for Road Works
Scarifying the existing B.T surface to a depth of 50 mm by Mechanical means and disposal of scarified material with all leads and lifts upto 1000 Mtrs as per MoRT&H (5th Revision) Specn. No.305.4.3 for Road Works
Earthwork excavation for road way in soils upto SDR by mechanical means including trimming bottom and side slopes in accordance with requirements of lines, grades and cross sections etc., complete including for finished item of work for trench cutting as per MoRT&H specification 301(5th Revision) and as directed by the Engineer-in-Charge. for Road Works
Forming embankment with excavated earth obtained from roadway excavation for Embankment by mechanical means upto SDR including pre-watering of soil, removal of top soil, excavation of soils, depositing the soils on the embankment, spreading soil, breaking clods, sectioning, grading and consolidation with 8 to 10 Tonnes Vibratory Road Roller @ OMC to meet requirement of table 300-2 of MoRT&H, including all hire and operational charges of T&P and complete for finished item of work as per MoRT&H specification 305 (5th revision). for Road Works
Construction of embankment with material obtained from borrowed useful earth from outside road boundary MDD of 18 KN/Cum , CBR ≥= 10%, PI <= 18%, by mechanical means upto SDR with all leads and lifts including pre-watering of soil at borrow area, removal of top soil, excavation of soils at borrowed area, conveyance of soil, depositing the soil on the embankment, spreading soil, breaking clods, sectioning, grading and consolidation with 8 to 10 Tonnes Vibratory Road Roller @ OMC to meet requirement of table 300-2 of MoRT&H, including all hire and operational charges of T&P, complete for finished item of work as per MoRT&H specification 305 (5th revision). for Road Works
Construction of subgrade with approved material of gravelly soils with CBR ≥10%, obtained from borrow pits with all lifts and leads transporting to site, spreading, grading to required slope and compacted , removal of top soil, excavation of soils at borrowed area, conveyance of soil, depositing the soil , spreading soil, breaking clods, sectioning, grading and consolidation with 8 to 10 Tonnes Vibratory Road Roller @ OMC to meet requirement of table 300-2 of MoRT&H, including all hire and operational charges of T&P and seigniorage charges, complete for finished item of work as per MoRT&H specification 305 (5th Revision) for Road Works
Construction of Granular sub-base by providing HBG material confirming to Grading - VI of MoRT&H Table 400-1 including cost, (excluding seigniorage charges) and conveyance of all materials to work site and spreading in uniform layers with motor grader or by approved means, on prepared surface mixing by mix in place method with Rotavator / approved means at OMC and compacting with vibratory roller to achieve the desired density etc., complete for finished item of work as per MoRT&H Specification 401 (5th revision) and as directed by the Engineer-in-charge. for Road Works
Providing, Laying, Spreading and compacting graded HBG crushed stone aggregate to Wet Mix Macadem specification including cost of all materials and including premixing the material with water at OMC in Mechanical mix plant carriage of mixed material by tipper to site, laying in uniform layers with paver in base courses on well prepared surface and compacting with Vibratory roller to acheive the desired density etc., as directed by the Engineer-in-Charge and as per MoRT&H specification 406 (5th revision) for finished item of work. for Road Works
Providing and aplying Prime coat with bitumen emulsion (Slow setting SS1) bulk using emulsion pressure distributor on prepared surface of Granular base including cleaning of road surface and spraying emulsion at the rate of 0.70 Kg/sqm using emulsion pressure distributor for finished item of work as per MoRT&H specification 502 (5th Revision) and as directed by the Engineer - in charge. for Road Works
Providing and applying tack coat with bitumen emulsion (Rapid settting-I) (Bulk) using Emulsion pressure distributor at the rate of 0.20 kgs per sqm on the prepared bituminous/granular surface cleaned with mechanical broom for finished item of work as per MoRT&H Specification 503 (5th revision) and as directed by the Engineer-in-Charge for Road Works
Providing 40 mm thick compacted Bituminous Concrete with 100-120 TPH Batch mix plant using HBG crushed aggregates of Grading – 2 as per table 500-17 of specification 509 of MoRT&H (5th revision), premixed with bitumen VG-30 grade @ 5.4% of mix and Hydrated lime, transporting the hot mix to work site, laying with full width paver to the required grade, level and alignment, rolling with smooth wheeled, vibratory and tandem rollers to achieve the desired compaction as per MoRT&H Specification 507 (5th revision) complete for finished item of work in all respects as directed by Engineer-in-Charge for Road Works
Plain Cement Concrete (1:3:6) nominal mix in foundation using 40mm size HBG crushed stone aggregate and fine aggregate conforming to table 1000-2 of MoRT&H including cost, (excluding seigniorage) conveyance of all materials to site and labour charges, centering, machine mixing, laying, Vibrating, curing etc., including all other incidental and operational charges of all T&P etc., complete for finished item of work as per MoRT&H specification 1500,1700, 2100 (5th Revision) and as directed by the Engineer-in-Charge for Road Works
Construction of Cement Concrete road by providing VCC M 35 Grade pannel of size (1.0mx1.0m) using 20mm & 10mm HBG crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to table 1000-2) including cost, conveyance of all materials to site and labour charges, centering, machine mixing, laying, vibrating, curing etc., including all other incidental and operational charges of all T&P etc., complete for finished item of work as per MoRT&H specification 1500, 1700, 2100 & 2702 (5th Revision) and as directed by the Engineer-in-Charge for C.C Pavement. for Road Works
Groove Cutting of 2-4 mm for 1/3rd depth of concrete slab 100mm to 200mm thick using concrete groove cutting machine with diamond studded saw within 24 hours of casting of CC pavementPavement. for Road Works
Construction of earthen shoulders with approved material of gravelly soils with CBR ≥10%, obtained from borrow pits with all lifts and leads transporting to site, spreading, grading to required slope and compacted , removal of top soil, excavation of soils at borrowed area, conveyance of soil, depositing the soil , spreading soil, breaking clods, sectioning, grading and consolidation with 8 to 10 Tonnes Vibratory Road Roller @ OMC to meet requirement of table 300-2 of MoRT&H, including all hire and operational charges of T&P and seigniorage charges, complete for finished item of work as per MoRT&H specification 305 (5th Revision) for Road Works
Providing, laying Reinforced cement concrete Hume pipes of 450 mm Dia., NP-3 class for pipe culverts including cost and conveyance of Pipes etc., complete and Labour charges for laying, jointing of R.C.C Hume pipes in position including lifting, aligning, lowering and hoisting etc., as per drawing and as per MoRT&H Specification 2900, 2905 and 2906 (5th Revision) and IRC Special Publication No: 13 and as directed by the Engineer-in-Charge for finished item of work. for Road Works
Earthwork excavation in soils upto SDR by mechanical means for foundations of structures as per drawing and technical specification including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing sides of bottom, back filling the excavation earth to the extent required etc., complete excluding seignioarge charges for finished item of work as per MoRT&H specification 304(5th Revision) and as directed by the Engineer-in-Charge for Pipe Culverts
Plain Cement Concrete (1:3:6) nominal mix in foundation using 40mm size HBG crushed stone aggregate and fine aggregate conforming to table 1000-2 of MoRT&H including cost, (excluding seigniorage) conveyance of all materials to site and labour charges, centering, machine mixing, laying, Vibrating, curing etc., including all other incidental and operational charges of all T&P etc., complete for finished item of work as per MoRT&H specification 1500,1700, 2100 (5th Revision) and as directed by the Engineer-in-Charge for Pipe Culverts
Vibrated cement concrete M 20 Grade Concrete using 40mm , 20mm and 10mm size HBG crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to table 1000-2) including cost, (excluding seigniorage) and conveyance of all materials to site and all labour charges ,centering, machine mixing, laying in position, Compacting , Vibrating and curing including all other incidental and all other operational charges of T&P required etc., complete as per MoRT&H Specification 1500,1700, 2200 (5th Revision).. for Pipe Culverts
Providing, laying Reinforced cement concrete Hume pipes of 1000 mm Dia., NP-3 class for pipe culverts including cost and conveyance of Pipes etc., complete and Labour charges for laying, jointing of R.C.C Hume pipes in position including lifting, aligning, lowering and hoisting etc., as per drawing and as per MoRT&H Specification 2900, 2905 and 2906 (5th Revision) and IRC Special Publication No: 13 and as directed by the Engineer-in-Charge for finished item of work for Pipe Culverts
Earthwork excavation in soils upto SDR by mechanical means for foundations of structures as per drawing and technical specification including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing sides of bottom, back filling the excavation earth to the extent required etc., complete excluding seignioarge charges for finished item of work as per MoRT&H specification 304(5th Revision) and as directed by the Engineer-in-Charge. (upto 3m depth) for Slab Culvert
Vibrated cement concrete M 15 Grade Concrete using 40mm , 20mm and 10mm size HBG crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to table 1000-2) including cost, (excluding seigniorage) and conveyance of all materials to site and all labour charges ,centering, machine mixing, laying in position, Compacting , Vibrating and curing including all other incidental and all other operational charges of T&P required etc., complete as per MoRT&H Specification 1500, 1700, 2100 (5th Revision). Under Abutments, Piers and wing walls for Slab Culvert
Vibrated reinforced cement concrete M 25 grade using 20mm & 10mm HBG crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to table 1000-2) including cost, (excluding seigniorage) conveyance of all materials to site and labour charges, centering, machine mixing, laying, vibrating, curing etc., including other incidental hire and operational charges of all T&P as per approved drawings and as directed during execution but excluding cost of steel and its fabrication charges for finished item as per MoRT&H specification 1500,1600,1700 & 2200 (5th revision ) and as directed by the Engineer-in-Charge for Raft Foundation for Slab Culvert
Vibrated cement concrete M20 Grade Concrete using 40mm, 20mm and 10mm size HBG crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to table 1000-2) including cost, (excluding seigniorage) and conveyance of all materials to site and all labour charges , centering, mixing using concrete batching plant, transporting using transit mixer, laying in position, Compacting, Vibrating and curing including all other incidental and all other operational charges of T&P required etc., complete as per MoRT&H Specification1500, 1700, 2100 (5th Revision) for footings of Abutments, Piers & Wing Walls for Slab Culvert
Vibrated cement concrete M 20 Grade Concrete using 40mm , 20mm and 10mm size HBG crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to table 1000-2) including cost, (excluding seigniorage) and conveyance of all materials to site and all labour charges ,centering, machine mixing, laying in position, Compacting , Vibrating and curing including all other incidental and all other operational charges of T&P required etc., complete as per MoRT&H Specification 1500,1700, 2200 (5th Revision). for substructure Abutments, Piers and Wing walls for Slab Culvert
Vibrated reinforced cement concrete M 25 grade using 20mm & 10mm HBG crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to table 1000-2) including cost, (excluding seigniorage) conveyance of all materials to site and labour charges, centering, machine mixing, laying, vibrating, curing etc., including other incidental hire and operational charges of all T&P as per approved drawings and as directed during execution but excluding cost of steel and its fabrication charges for finished item as per MoRT&H specification 1500,1600,1700 & 2200 (5th revision ) and as directed by the Engineer-in-Charge for Abutment Bed Blocks & Backing Walls (substructure) for Slab Culvert
Vibrated reinforced cement concrete M 30 grade using 20mm & 10mm HBG crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to table 1000-2) including cost, (excluding seigniorage) conveyance of all materials to site and labour charges, centering, machine mixing, laying, vibrating, curing etc., including other incidental hire and operational charges of all T&P as per approved drawings and as directed during execution but excluding cost of steel and its fabrication charges for finished item as per MoRT&H specification 1500,1600,1700 (5th revision ) and as directed by the Engineer-in-Charge as per MOST Drg No. SD/178-deck slab for Slab Culvert
Vibrated cement concrete M 15 Grade Concrete using 40mm , 20mm and 10mm size HBG crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to table 1000-2) including cost, (excluding seigniorage) and conveyance of all materials to site and all labour charges ,centering, machine mixing, laying in position, Compacting , Vibrating and curing including all other incidental and all other operational charges of T&P required etc., complete as per MoRT&H Specification 1500, 1700, 2100 (5th Revision). for levelling course below approach slab for Slab Culvert
Vibrated reinforced cement concrete M 30 grade for approach slab using 20mm & 10mm HBG crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to table 1000-2) including cost, (excluding seigniorage) conveyance of all materials to site and labour charges, centering, machine mixing, laying, vibrating, curing etc., including other incidental hire and operational charges of all T&P as per approved drawings and as directed during execution but excluding cost of steel and its fabrication charges for finished item as per MoRT&H specification 1500, 1600, 1700 & 2704 (5th revision ) and as directed by the Engineer-in-Charge for Slab Culvert
Provision of an Reinforced cement concrete crash barrier at the edges of the road, approaches to bridge structures and medians, constructed with M-40 grade concrete with HYSD reinforcement conforming to IRC:21 and dowel bars 25 mm dia, 450 mm long at expansion joints filled with pre-moulded asphalt filler board, keyed to the structure on which it is built and installed as per design given in the enclosure to MOST circular No. RW/NH - 33022/1/94-DO III dated 24 June 1994 as per dimensions in the approved drawing and at locations directed by the Engineer-in-Charge. for Slab Culvert
Providing HYSD bars (Fe-500 From Primary Producers like TATA, SAIL, VSP,JSW and Shyam as approved by Ministry of Steel) of different diameters, wrought and put up bars of all diameters including cost and conveyance of steel to site and all labour charges for fabrication of reinforcement including cutting, bending, binding rods, tying grills, placing them in position etc., complete including cost and conveyance of binding wire and all handling charges and operational charges etc., and including over lapping welding if required etc., complete for all R.C.C items for finished item of work as per standard drawings, as per the directions of the Engineer-in-Charge and as per MoRT&H specification 1600 &2200 (5th revision) and as per I.S.1786 of 1985 for substructure RCC items. for Slab Culvert
Providing HYSD bars (Fe-500 From Primary Producers like TATA, SAIL, VSP,JSW and Shyam as approved by Ministry of Steel) of different diameters, wrought and put up bars of all diameters including cost and conveyance of steel to site and all labour charges for fabrication of reinforcement including cutting, bending, binding rods, tying grills, placing them in position etc., complete including cost and conveyance of binding wire and all handling charges and operational charges etc., and including over lapping welding if required etc., complete for all R.C.C items for finished item of work as per standard drawings, as per the directions of the Engineer-in-Charge and as per MoRT&H specification 1600 &2200 (5th revision) and as per I.S.1786 of 1985 for foundation RCC items. for Slab Culvert
Providing Grouted Revetment with rough stone (HBG) of not less than 300 mm size grouted with 0.20 cum of CC (1:4:8) including cost, _ charges and conveyance of materials to site and including labour charges for packing the stones for revetment etc., complete for finished item of work as per MoRT&H specification 2504 (5th revision ) and as directed by the Engineer-in-Charge for quadrential revetment. for Slab Culvert
Providing dry rough stone revetment 300 mm thick with HBG stone of not less than 300 mm size including cost, (excluding seigniorage) charges and conveyance of materials to site and including labour charges for packing the stones for revetment etc., complete for finished item of work as per MoRT&H specification 2504 ( 5th revision ) and as directed by the Engineer-in-Charge for Slab Culvert
Providing and laying filter material with selected earth underneath pitching in slopes including cost, (excluding seigniorage) charges and conveyance of materials to site including labour charges etc., complete for finished item of work as per MoRT&H Specification 2504 (5th Revision) and as directed by the Engineer-in-Charge for Slab Culvert
Back filling behind abutments with serviceable material including cost ,conveyance and of all materials to site etc., complete as per Clause 710.1.4 of IRC : 78and as per MoRT&H Specification No. 2200 (5th Revision) and as per Drawing and technical specifications for finished item of work for Slab Culvert
Providing and laying of filter media using 50% of 150 mm IRC soling stone and 50 % of 40 mm HBG metal satisfying the requirements laid down in clause 2504.2.2 of MoRT&H specifications to a thickness of not less than 600mm with smaller size towards the soil and bigger size towards the wall and provided over the entire surface behind the abutment, wing wall and return wall to the full height compacted to a firm condition including cost and conveyance of all metal (excluding seigniorage) charges ,and all labour charges as directed by the departmental officers as per drawing and Technical specifications as per clause 710.1.1 of IRC:78 and Clause 2200 of MoRT&H (5th Revision) for finished item of work. for Slab Culvert
Providing Weep holes in RCC Abutment/ Wing wall/return wall with 100mm Diameter AC pipe extending through the full width of the structure at 1.00m C/C in both horizontal and vertical direction so that the weep holes in each horizontal direction is staggered from the weep holes laying above and below lines as shown in drawing including cost and conveyance of the A.C pipes and labour charges for cutting to required length, placing the pipe with a slope of about 1V : 20H towards stream side face etc., complete for finished item of work for weep holes as per MoRT&H specification 2706 & 2200 (5th Revision) for Slab Culvert
Providing and laying boulders apron for bed protection against scour with stone boulders weighing not less than 40kg with 300mm thick each complete as per drawing and specification. complete for finished item of work as per MoRT&H specification 2504 ( 5th revision ) and as directed by the Engineer-in-Charge for Slab Culvert
Drainage spouts complete as per drawing and technical specifications Clause 1209 MORD & 2705 MORTH for Slab Culvert
Supplying of hot applied thermoplastic road marking compound, 2.5mm thick including reflectorising glass beads @ 250 gms with Reflectorising Glass Beads on Bituminous Surface at 250 gms per sqm area, thickness of 2.5mm is exclusive of surface applied glass bead as per IRC :35, the material should be of BERGER Company/BERGER Equivalent and must comply with the follwing; a) White index for the product should be in the range of 60-70 when measured against standard reference. The applied panel 7/8 number must be submitted for checking up the white index in the department lab. in case the department approves the white index of any vendor, the department Engineer any carrout random checking of applied products at site against the approved panel. In case of any major deviation, beyond acceptance limit, department reserve the right to cancel or reject the total supplied consignment of the said material and will compell the vendor who has to replace the full consignment by the desired material as per approved panel at his own cost and additional demurrages may be claimed due to loss of man days (as per the rules of the department). b) Luminance factor of the material should be in the range of 80-85% at 45 degree centigrade as per AASTHOM 249. c) Crack resistance: The applied panel cured for 7 days under ambient condition and then should be tested as per BS3262, Part-1, 1989 and should pass at the range of '0' degree centigrade to '10' degree centigrade. D) Adhesion: Strong. E) Softening point: 102 degree centigrade. F) Dried film finish: Smooth and uniform. G) Night Vision: High as directed by the Engineer-in- Charge and confrming to IS:164-1961 (1st revision reaffirmed in 1986) and clause conforming to IRC35-1997 for lane marking for RSI
Supplying & Fixing of Molded Shanks Raised Pavement Markers and reflective panels with micro prismatic lens capable of providing total internal reflection of the light entering the lens face and shall support a load of 16000 kg tested in accordance to ASTM D 4280 Type H and complying to Specifications of Category A of MORTH Circular No RW/NH/33023/10-97 – DO III Dt 11.06. 1997. The height, width and length shall not exceed 50 mm, 100 mm and 100 mm and with minimum reflective area of 13 Sqcm on each side and the slope to the base shall be 35 +/- 5 degree. The strength of detachment of the integrated cylindrical shanks, (of diameter not less than 19 +/- 2 mm and height not less than 30+/- 2 mm) from the body is to be a minimum value of 700 Kgs. Fixing will be by drilling holes on the road for the twin shanks to go inside, without nails and using epoxy resin based adhesive as per manufacturer’s recommendation and complete as directed by the engineer.
Providing and fixing Cautionary / Warning sign boards size 900 mm equilateral triangle made out of Type – XI of ASTMD 4956-09 wide angle cube cornered micro Prismatic Retro reflective sheeting and confirming to IRC 67:2012 for full background of White colour and letters/logos done by screen printing in Black colour, boarders by screen printing in Red colour and fixed over 3MM Aluminium Composite Material sheet having minimum 0.3 mm thick Aluminium skin on both sides with back side painted grey colour and fixed over back support frame of M.S angle 25x25x3mm all round and fixing with 35x35x4mm and mounted on a MS angle post of size 75x75x6mm with clear height of not less than 2.1 m from the ground level to the bottom of the board. The signpost should be painted with one coat of red oxide paint and 2 coats of synthetic enamel paint Black and White colour with bands of 30cm of height. The signpost shall be firmly fixed with MS base angle 35x35x4 mm in to the ground by M-15 Concrete foundation of size 450x450x600mm including cost and conveyance of all materials ,equipment, machinery and labour with all leads and lift, loading chages necessary for satisfactory completion of the work as directed by Engineer -in-Charge. for RSI
Providing and fixing Mandatory / Regulatory sign boards size 900 mm circle made out of Type – XI of ASTMD 4956-09 wide angle cube cornered micro Prismatic Retro reflective sheeting and confirming to IRC 67:2012 for full background of White colour and letters/logos done by screen printing in Black colour, boarders by screen printing in Red colour and fixed over 3MM Aluminium Composite Material sheet having minimum 0.3 mm thick Aluminium skin on both sides with back side painted grey colour and fixed over back support frame of M.S angle 25x25x3mm all roundand fixing with 35x35x4mm and mounted on a MS angle post of size 75x75x6mm with clear height of not less than 2.1 m from the ground levelto the bottom of the board. The signpost should be painted with one coat of red oxide paint and 2 coats of synthetic enamel paint Black and White colour with bands of 30cm of height. The signpost shall be firmly fixed with MS base angle 35x35x4 mm in to the ground by M-15 Concrete foundation of size 450x450x600mm including cost and conveyance of all materials ,equipment, machinery and labour with all leads and lift, loading charges necessary for satisfactory completion of the work as directed by Engineer -in-Charge. for RSI
Providing and fixing facility informatory sign board size 600x800 mm made out of Type – XI of ASTMD 4956-09 wide angle cube cornered micro Prismatic Retro reflective sheeting and confirming to IRC 67:2012 for full background of Green Colour & White Letters and fixed over 3MM Alluminium Composite Material sheet having minimum 0.30mm thick Aluminium skin on both sides with back side painted grey colour and fixed over back support frame of M.S angle 25x25x3mm all round and fixing with 35x35x4mm and mounted on a MS angle post of size 75x75x6mm with clear height of not less than 2.1 m from the ground level to the bottom of the board. The signpost should be painted with one coat of red oxide paint and 2 coats of synthetic enamel paint Black and White colour with bands of 30cm of height. The signpost shall be firmly fixed with MS base angle 35x35x4 mm in to the ground by M-15 Concrete foundation of size 450x450x600mm including cost and conveyance of all materials ,equipment, machinery and labour with all leads and lift, loading charges necessary for satisfactory completion of the work as directed by Engineer –in-Charge. for RSI
Manufacturing and supplying and fixing of Precast RCC precasted Ordinaray KM stone using 20 mm IRC GBG metal including cost & conveyance of all materials and steels with its fabrication, cutting, bending, wastage placing grills in position including cost of binding wire and labour charges, centering, laying concrete, tamping, vibrating and palstewring with 20 mm thick in CM(1:3) prop, including cost & conveyance of all materials labour charges and all leads and curing for work and fixing of CC (1:4:8) and excavating the pit and fixing the stone in position including painting and figuring as directed by the Engineer-in-Charge. for RSI
Manufacturing and supplying and fixing of Precast RCC precasted Hectometer stone using 20 mm IRC GBG metal including cost & conveyance of all materials and steels with its fabrication, cutting, bending, wastage placing grills in position including cost of binding wire and labour charges, centering, laying concrete, tamping, vibrating and palstewring with 20 mm thick in CM(1:3) prop, including cost & conveyance of all materials labour charges and all leads and curing for work and fixing of CC (1:4:8) and excavating the pit and fixing the stone in position including painting and figuring as directed by the Engineer-in-Charge. for RSI
Providing & fixing junction boards of size 1500x1200 mm made out of Type-XI of ASTMD 4956-09 High Intensity Prismatic Retro reflective sheeting and confirming to IRS 67:2012 for full background of Green Colour & White Letters and fixed over 4MM Alluminium Composite Material sheet having minimum 0.5mm thick Aluminium skin on both sides with back side painted grey colour and fixed over back support frame of M.S. angle post of size 75x75x6mm with clear height of not less than 2.1 m from the ground level to the bottom of the board. The signpost should be painted with one coat of red oxide paint and 2 coats of synthetic enamel paint Black and White colour with bands of 30cm of height. The signpost shall be firmly fixed with MS base angle 35x35x4mm into the ground by M-15 Concrete foundation of size 450x600mm including cost and conveyance of all materials, equipment, machinery and labour with all leads and lift, loading charges necessary for satisfactory completion of the work as directed by Engineer-in-Charge for RSI
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
RAW_HTML
YIIA Dhamagnapur road BOQ.xls
TENDER_DOCUMENT • 0.13 MB
Bid Doc YIIR Dhamagnapur road.docx
TENDER_DOCUMENT • 0.32 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .