Tender Value
₹3.0 L
EMD Value
₹6,000
Closing Date
27 Aug 2026, 12:00 pmDue tomorrow
EX-ENG-IX
THE KOLKATA MUNICIPAL CORPORATION 11,BELVEDERE ROAD KOLKATA-700027
REPAIRING OF ROAD SURFACE AT 19 SCHOOL ROW , 33 GOBINDA BOSE LANE AND OTHER SURROUNIDNG AREAS IN WARD NO 071.
2026_KMC_1038559_1
KMC/IX/071/008/2026-2027/R (2ND CALL)
Open Tender
CIVIL WORKS
Percentage
60 days
BR-IX
Please refer Tender documents.
5 documents required · 5 mandatory
₹0
₹6,000
18 Aug 2026
18 Aug 2026
29 Aug 2026
18 Aug 2026
27 Aug 2026
18 Aug 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | BUILDING WORKS (A) EARTH WORK,ANTITERMITE TREATMENT 2. Earth work in excavation of foundation trenches or drains, in all sorts of soil (including mixed soil but excluding laterite or sandstone) including removing, spreading or stacking the spoils within a lead of 75 m. as directed. The item includes necessary trimming the sides of trenches levelling, dressing and ramming the bottom, bailing out water as required complete. (a) Depth of excavation not exceeding 1,500 mm. | - | %M3 | 11,927 | - |
| 2 | Supplying, spreading and compacting Sand to required thickness, in layers not exceeding 150 mm to proper gradient and camber, inundating each layer by water and packing and ramming layer by layer to achieve desired compaction, including lighting, guarding, barricading and making adequate earthen bundh where necessary, curing with water as per direction, mending cracks and depressions by ramming wherever necessary. Note:- Add cost at site of the materials to arrive at the complete rate. The compaction factor for dry, clean sand may be taken as 0.835. (The payment is to be made on the basis of finished compacted volume). (a) For Fine Sand | - | M3 | 1,104.11 | - |
| 3 | Taking out stone slab of kerb & channel of road side drain and stacking as directed. b) flat channel stone. ( Ref :Rate based on PWD Current SOR. [PWD(B)2017,p-303]) | - | MTR | 8.17 | - |
| 4 | Taking out stone slab of kerb & channel of road side drain and stacking as directed. a) vertical kerb stone. ( Ref :Rate based on PWD Current SOR. [PWD(B)2017,p-303]) | - | MTR | 8.17 | - |
| 5 | BUILDING WORKS ( C ) Brickworks,Concrete Works etc B. CONCRETE WORKS 1. Cement concrete with graded jhama khoa (30 mm size) excluding shuttering In ground floor and foundation (a) 1:3:6 proportion | 1 | M3 | 4,572 | ₹4,567.43 |
| 6 | Resetting of Stone Slabs of kerb & channel of road side drain to correct line and level including cement pointing (1:2).b) flat channel stone. ( Ref :Rate based on PWD Current SOR. [PWD(B) 2017, p-303 & 3rd corri. Addea dtd-04.06.2018. P-52 ]) | - | MTR | 18.3 | - |
| 7 | Resetting of Stone Slabs of kerb & channel of road side drain to correct line and level including cement pointing (1:2). a) Vertical Kerb | - | MTR | 21.34 | - |
| 8 | Single Brick Flat Soling of picked jhama bricks including ramming and dressing bed to proper level and filling joints with local sand. ( Ref :PWD (Bldg.)-2017, It. No. 1, Page No.14 & 3rd Corrigenda Addenda dtd-04.06.18,P-1) | 0.6 | SQM | 361 | ₹216.6 |
| 9 | Water Bound Macadam Sub Base by consolidating Jhama metal / Laterite chelly or stone metal / shingles of specific size in hard crust to requisite thickness (measured after compaction) in layers including screening of metals etc. as necessary, hand packing, sweeping, watering and rolling in stages with power roller to proper line, grade and camber, lighting, guarding & barricading and making necessary earthen bundh of one metre width on each side where necessary to protect edges and preparing the bed by necessary cutting or filling and rolling all complete including the cost of all materials and hire and labour charges of all men and machineries and compacting to the required density, as per Clause 404 of Specifications for Road & Bridge Works of MoRT&H (5th Revision). (ii) For Construction of Sub Base by consolidating Brick Bats / Laterite (90 mm to 45 mm) (For compacted thickness 100mm) | - | SQM | 194.49 | - |
| 10 | Water Bound Macadam Sub Base by consolidating Jhama metal / Laterite chelly or stone metal / shingles of specific size in hard crust to requisite thickness (measured after compaction) in layers including screening of metals etc. as necessary, hand packing, sweeping, watering and rolling in stages with power roller to proper line, grade and camber, lighting, guarding & barricading and making necessary earthen bundh of one metre width on each side where necessary to protect edges and preparing the bed by necessary cutting or filling and rolling all complete including the cost of all materials and hire and labour charges of all men and machineries and compacting to the required density, as per Clause 404 of Specifications for Road & Bridge Works of MoRT&H (5th Revision). (i) For Construction of Sub Base by consolidating Jhama metal / Laterite (63 mm to 45 mm) (Moorum replaced with course sand) (For compacted thickness 75mm) | - | SQM | 188.23 | - |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.43 MB
ROAD.pdf
Additional Documents • 2.42 MB
TF_71_08.pdf
Tender Documents • 0.75 MB
BOQ_2551265.xls
BOQ • 0.25 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].