| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹12.6 LAdmitted-Finance | -0.10% | ₹12.6 L | L1 | Admitted-Finance |
Tender Value
₹14.9 L
EMD Value
₹1.3 L
Closing Date
3 Jul 2026, 3:00 pmClosed
Municipal Commissioner
Nagar Nigam Firozabad
Construction of an RCC drain from the temple to Ramnath, passing through Anokhe and Jagdish, and into the link lanes in Ward No. 25, Thar Bajidpur.
2026_DOLBU_1103806_240
12/PWD/2025-26
Open Tender
Civil Works
Percentage
Firozabad
Please refer Tender documents.
2 documents required · 2 mandatory
₹1,488
Municipal Commissioner
₹1.3 L
10 Aug 2026
24 Jun 2026
3 Jul 2026
24 Jun 2026
3 Jul 2026
24 Jun 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Excavation in foundation in ordinary soil or silt (loam, clay or sand) including lift upto 1.50m and lead up to 30m and including filling watering and ramming of excavated earth in to the trenches or in to the space between the building and the side of foundation trenches or into plinth and removal and disposal of surplus earth as directed by thr Engineer in charge up to a distance of 30m from the foundation trenches.(PWD SOR 2025-26, chepter-4, Item No.01 Spec-251) | 170.8 | cum | 150 | ₹25,620 |
| 2 | Construction of granular sub-base by providing well graded material, spreading in uniform layers wth motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with smooth wheelo roller to achieve the desired density. complete as per technical spercification clause-401 (As per Analysis of Rate) | 7.82 | cum | 3,234 | ₹25,289.88 |
| 3 | Proving and laying cement concrete in 1:4:8 Providing and laying cement concrete in 1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 40 mm nominal size) and curing complete, including cost of form work in Foundation and floors. (PWD SOR 2025-26 Chapter No-05 Item No. 3 spec. No. 4.1) | 36.6 | cum | 5,650 | ₹2,06,790 |
| 4 | R.C.C work Providing and laying in position specified grade of reinforced cement concrete in Raft foundation, including the cost of centering, shuttering, finishing and excluding reinforcement All work up to plinth level in 1:1.5:3 (1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size) . (PWD SOR 2025-26, Chepter-5, Item No.9 Spec no. 5.2) | 33.55 | cum | 8,100 | ₹2,71,755 |
| 5 | R.C.C work in Wall (any thickness) including attached plasters, buttresses, plinth and string courses, fillers, columns, pillars, abutments, post and struts etc. including the cost of centering, shuttering, finishing and excluding reinforcement All work up to plinth level in 1:1.5:3 (1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 mm nominal size) upto plinth level (PWDSOR 2022-23 Chapter No-05 Item No. 5.2spec. No. 5.2.2) | 36.6 | cum | 8,300 | ₹3,03,780 |
| 6 | R.C.C work Providing and laying in position specified grade of reinforced cement concrete, including the cost of centering, shuttering, finishing and excluding reinforcement All work up to plinth level in 1:1.5:3 (1 cement : 1.5 coarse sand : 3 graded stone aggregate 20 | 1.13 | cum | 7,650 | ₹8,644.5 |
| 7 | Proving and laying cement concrete in 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) and curing complete, including cost of form work. (PWD SOR 2022-23 Chapter No-05 Item No. 4.1 spec. No. 4.1.3) | 8.28 | cum | 6,600 | ₹54,648 |
| 8 | M.S or Iron work in plain work such as reinforced concrete or reinforced brick work (When not included in and an over all rates) brought to required shape as necessary of the work and including the supply of steel and its wastage bend, hooks and authorized over lapping shall be measured upto floor to level. .(As per Analysis) | 44.76 | Qtl | 7,800 | ₹3,49,128 |
| 9 | Supply and fixing Manak board …………………….. All Complete. | 1 | Nos | 4,635 | ₹4,635 |
| 10 | Construction of Inauguration /Silla patta board using brick work and granite stone …………. All complete. | 1 | Job | 10,980 | ₹10,980 |
stage.html
html • 0.02 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 6.13 MB
BOQ_2179802.xls
BOQ • 0.24 MB
TD.pdf
Tender Documents • 1.55 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .