| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹37.9 LAccepted-AOC | L1 | Accepted-AOC DUE TO L1 | |
| 2 | L2₹46.0 L+₹6.6 L (16.8%)Rejected-Finance FLAT NO 602 THE ELEPHANT HEAD CGHS LTD PLOT NO 41 OPP AYUSHMAN HOSPITAL DWARKA SECTOR 10 SOUTH WEST DELHI 110075 | SOUTH WEST | DELHI | 110075 | L2 | Rejected-Finance HIGHER RATE | |
| 3 | L3₹48.9 L+₹9.5 L (24.1%)Rejected-Finance 205 PARSHAV VIHAR PLOT NO 50 1 P EXTN PATPARGANJ DELHI 110092 | DELHI | EAST DELHI | DELHI | 110092 | L3 | Rejected-Finance HIGHER RATE |
Tender Value
Refer Docs
EMD Value
₹99,920
Closing Date
26 Sept 2024, 6:00 pmClosed
GE NEW DELHI
GE NEW DELHI, SP MARG NAR ABHM GATE NO 5
REPAIR/ MAINT OF EXTERNAL WATER SUPPLY, SWIMMING POOL AND MECHANICAL LAUNDRY PLANT AND REPAIR/ MAINT OF EXTERNAL ELECTRIC SUPPLY IN NAVY AREA UNDER GE NEW DELHI
2024_MES_668749_1
NIT No GE/ND-57/2024-25
Open Tender
Miscellaneous Works
Item Rate
270 days
GE NEW DELHI
Please refer Tender documents.
7 documents required · 7 mandatory
₹500
Yes
GE NEW DELHI
₹99,920
Yes
14 Nov 2024
31 Aug 2024
28 Sept 2024
31 Aug 2024
26 Sept 2024
13 Sept 2024
Amount
Material and labour for Cleaning of NSB-I Swimming Pool of size 25 m x 13.5 m using Eco friendly / harmless to human being cleaning material and suitable methods to make the pool water crystle clear bottom of the pool and transparent water all the time before filling as required at site complete all as specified and directed. M&L for cleaning of swimming pool by taking out of muddy water and removing the mud/settled particles and all other foreign material from the swimming pool and depositing where directed but not less than 50 mtr from the starting point including scraping / removing all dirt/scales from the internal wall of the swimming pool and washing the bottom surface and wall surface of the swimming pool with clean water, draining out the dirty water so that the whole swimming pool be thoroughly cleaned after pumping out all existing water by portable centrifugal/mono block pumping set, applying sulfuric acid on surface and wall of swimming pool and outer drain out path for removing the settled chemicals on surface/wall. after cleaning with sulfuric acid fillingup of swimming pool with fresh water and make the pool water crystal clear when pool is start and make the bottom clear when pool is closed. Note:- Quoted rates shall inclusive of manpower and cleaning material, safety gears and ladders etc required at site for filling up the swimming pools with water and de-watering on completion of Operation and Maintenance of swimming pools
Supply and charging (filling in) in replacement of old worn out/uncleaned/choked filter media in filteration cum recycle plant of capacity 100000 ltrs/hr to maintain the desired filter flow rate as recommended by manufactuere and swimming pool norms complete all as specified and directed. Filter media details are as under:- (i) Media Depth – 915 MM (ii) Quartz Pebbles of 1" – 3/4" size Not less then 100 mm thick layer (iii) Quartz Pebbles of 3/4" to 1/2" size Not less then 100 mm thick layer (iv) Quartz Pebbles of 1/2" to 1/4" size Not less then 100 mm thick layer (v) Quart zPebbles of 1/4" to 1/10" size Not less then 100 mm thick layer (vi) Quart zsand of assorted sizes Not less than 900mm thick layer (vii) Making Back wash arrangement functional/repair – Back wash arrangement shall be made through the running water hence arrangement shall be made to facilitate the back washing system. (viii) Replacement of Pressure gauges and flow meters from Filtration plant. (ix) Repair and replacement of Air release pipe and valve from all filteration plant
M&L for rewinding of motor 3 HP with super enameled winding copper wire of existing size/gauge after cutting of burried winding including all insulation material such as insulation varnish , PVC copper cable lead glass fiber sleeves cotton tape insulation paper and heating in heat chamber at appropriate temp complete all as specified and directed.
M&L for complete overhauling/repair of defective submersible pump/mono submersible pump/monoblock pump of 3.0 HP ,dismantling of UNSV motor from pump set and opening the pump including cleaning of all parts, oiling/greasing, replacing of unserviceable parts such as CI connection piece,CI stage bowl,GM neck ring, remelting of GM impeller turning,GM DOL bush,SS stud with nut,water seal, revolving disc,EPV impeller,impeller key,repairing of stamping of stator,CI DOL piece,SS coupling with key,CI suction Piece.GMsand guard and any other parts of pump of capacity 3.0 HP, 3 phase motor driven (excluding motor winding) cast iron/cast steel body complete and connecting with motor portion complete all as specified and directed.
Repair/maintenance/ servicing to 3 phase electric driven air compressor with motor of capacity 5 HP Make: EVEREST BLOWER for filteration plant after diconnecting the electriclal connection , dismantling, the compressor and motor from foundation taking to the civil workshop and carry out the repair by replacing compressure bearing gland packing , nut bolt and washer including necessary greasing , oiling , machining work for its smooth bringing back/fixing at its original position and testing complete including painting the complete set with 2 coat of synthatic enamel paint of approved colour complete all as specified and directed by Engr -in charge Note: Rewinding of motor shall be measured and paid seperately
Supplying, injecting and mixing of alum sulphate in swimming pool through dozing system installed complete all as specified and directed by Engr-in-charge.
Supplying, injecting and mixing of soda ash in swimming pool through dozing system installed complete all as specified and directed by Engr-in-charge.
Supplying, injecting and mixing of TCC A90 in swimming pool through dozing system installed complete all as specified and directed by Engr-in-charge.
Supplying, injecting and mixing of copper suphate in swimming pool through dozing system installed complete all as specified and directed by Engr-in-charge.
Supplying, injecting and mixing of HCL in swimming pool through dozing system installed complete all as specified and directed at site.
Supply and filling AQUAFIT brand calcium hypochlorite 65% to 70 % chlorine content (in drum) the form of granular and tablet complete all as specified and directed.
M&L for isolation of power supply from the existing electric panel , Lifting of submersible pumping set of any capacity from deep bore well of any depth with chain and pulley arrangement ,transportation of submersible pump set to civil workshop,returning back of pump set on site after repair work completed and lowering down the submersible pump set and reconnecting it with power supply complete all as specified and directed.
S&F in replacement nuts, bolts, rubber gasket complete set complete all as specified and directed by Engineer-in-charge.. Note : One job shall be inclusive of all nuts, bolts, washers and rubber gasket required for lifting/lowering of pipe line for one pumping set complete all as specified and directed by Engineer-in-charge.
M&L for complete overhauling/repair of defective monosubmersible pump/jockey pump/ submersible pump/sewage pump of 5 HP to 7.5 HP ,dismantling of UNSV motor from pump set and opening the pump including cleaning of all parts, oiling/greasing, replacing of unserviceable parts such as CI connection piece,CI stage bowl,GM neck ring, remelting of GM impeller turning,GM DOL bush,SS stud with nut,water seal, revolving disc,EPV impeller,impeller key,repairing of stamping of stator,CI DOL piece,SS coupling with key,CI suction Piece.GMsand guard and any other parts of pump of capacity 5HP to 7.5 HP, 3 phase motor driven (excluding motor winding) cast iron/cast steel body complete and connecting with motor portion complete all as specified and directed.
M&L for complete overhauling/repair of defective monosubmersible pump/jockey pump/submersible pump/sewage pump of 10HP to 12.5 HP ,dismantling of UNSV motor from pump set and opening the pump including cleaning of all parts, oiling/greasing, replacing of unserviceable parts such as CI connection piece,CI stage bowl,GM neck ring, remelting of GM impeller turning,GM DOL bush,SS stud with nut,water seal, revolving disc,EPV impeller,impeller key,repairing of stamping of stator,CI DOL piece,SS coupling with key,CI suction Piece.GMsand guard and any other parts of pump of capacity 10HP to 12.5 HP, 3 phase motor driven (excluding motor winding) cast iron/cast steel body complete and connecting with motor portion complete all as specified and directed.
M&L in replacement of re-winding of motor of monosubmersible pump/jockey pump/submersible pump /sewage pump set of capacity 5.0 HP to 7.5 HP (for Navy area and panchwati) with suitable size copper conductor wire after cutting of existing burnt winding including replacement of unserviceable parts such as GM bearing,Rotor sleeve,water seal,thrust bearing segment,thrust bearing counter,thrust plate,T-bolt,submersible cable jointing kit,revolving disc,Rotor sleeve,impeller,distance sleeve,guide bush,DOL sleeve,O ring,motor seal,CI lower housing and upper housing, diffuser,all insulating materials such as insulation varnish, PVC copper cable lead, glass fiber sleeves, cotton tape, insulation paper and heating in heat chamber at appropriate temperature complete all as specified and directed.
M&L in replacement of re-winding of motor of monosubmersible pump/jockey pump/submersible pump set of capacity 10 HP to 12.5 HP with suitable size copper conductor wire after cutting of existing burnt winding including replacement of unserviceable parts such as GM bearing,Rotor sleeve,water seal,thrust bearing segment,thrust bearing counter,thrust plate,T-bolt,submersible cable jointing kit,revolving disc,Rotor sleeve,impeller,distance sleeve,guide bush,DOL sleeve,O ring,motor seal,CI lower housing and upper housing, diffuser,all insulating materials such as insulation varnish, PVC copper cable lead, glass fiber sleeves, cotton tape, insulation paper and heating in heat chamber at appropriate temperature complete all as specified & directed.
M&L for isolation of power supply from the existing electric panel , Lifting of sewage pumping set of any capacity (at DAD Panchwati and NSB-II) from deep sewage well of any depth with chain and pulley arrangement ,transportation of sewage pump set to civil workshop,returning back of pump set on site after repair work completed and lowering down the pump set Complete all as specified and directed.
M&L for isolation of power supply from the existing electric panel, taking out unserviceable induction pump set of cap 10 HP to 15.0 HP by unscrewing of bolts of pumpset casing from MS base frame and keeping aside , transportation of booster pump to civil workshop, dismantling of UNSV pumpset in including cleaning of all parts, oiling/greasing including reassemblimg the same after repair , and back to site, fixing of repaired booster pump set on its original foundation making proper alignment , including restoration of power supply and testing, commissioning to the entire satisfation of Engr-in-Charge complete all as specified and directed.
M&L for rewinding of 10 HP to 15.0 HP induction motor with new super enameled winding copper wire of existing size/gauge after cutting of burned winding including all insulating materials such as insulation varnish,bush, PVC copper cable lead, glass fiber sleeves, cotton tape, insulation paper,bearing sleeve,pump shaft welding,turning,grinding,making key way,TC coupling,CI impeller,CI interstage ring,gland packing,wear ring,bearing housing,fastener,air release valve,eye bolt,ball bearing,water liquid deflector,motor & pump coupling and heating in heat chamber at appropriate temperature complete all as specified and directed.
Supply ,installation,commissioning and testing of mono submeresible pump set of capacity 3.0 HP suitable for delivering water at 30 meter head with commensuring capacity ,water cooled operating on 3 Phase ,415 Volts ,50 HZ supply including taking down old/ unsv pump complete all as specified and directed. Note: Old unsv pump will be deposited in MES store yard in safe custody
M&L for isolation of power supply from the existing electric panel, taking out unserviceable booster pump set of cap 10.0 HP to 12.5 HP by unscrewing of bolts of pumpset casing from MS base frame and keeping aside , transportation of fountain pump to civil workshop, dismantling of UNSV pumpset in including cleaning of all parts, oiling/greasing replacing of unserviceable parts such as CI connection piece,CI stage bowl,GM neck ring, remelting of GM impeller turning,GM DOL bush,SS stud with nut,water seal, revolving disc,EPV impeller,impeller key,repairing of stamping of stator,CI DOL piece,SS coupling with key,CI suction Piece.GMsand guard and any other parts of pump of capacity 10HP to 12.5 HP, 3 phase motor driven (excluding motor winding) cast iron/cast steel body complete and connecting with motor portion including reassemblimg the same after repair , and back to site, fixing of repaired booster pump set on its original foundation making proper alignment, including restoration of power supply and testing, commissioning to the entire satisfation of Engr-in-Charge complete all as specified and directed.
M&L for isolation of power supply from the existing electric panel, taking out unserviceable booster pump set of cap 20 HP to 25 HP by unscrewing of bolts of pumpset casing from MS base frame and keeping aside , transportation of booster pump to civil workshop, dismantling of UNSV pumpset in including cleaning of all parts, oiling/greasing replacing of unserviceable parts such as CI connection piece,CI stage bowl,GM neck ring, remelting of GM impeller turning,GM DOL bush,SS stud with nut,water seal, revolving disc,EPV impeller,impeller key,repairing of stamping of stator,CI DOL piece,SS coupling with key,CI suction Piece.GMsand guard and any other parts of pump of capacity 20 HP to 25 HP , 3 phase motor driven (excluding motor winding) cast iron/cast steel body complete and connecting with motor portion including reassemblimg the same after repair , and back to site, fixing of repaired booster pump set on its original foundation making proper alignment , including restoration of power supply and testing, commissioning to the entire satisfation of Engr-in-Charge complete all as specified and directed.
M&L for isolation of power supply from the existing electric panel, taking out unserviceable booster pump set of cap 75 HP to 100 HP by unscrewing of bolts of pumpset casing from MS base frame and keeping aside , transportation of booster pump to civil workshop, dismantling of UNSV pumpset in including cleaning of all parts, oiling/greasing replacing of unserviceable parts such as CI connection piece,CI stage bowl,GM neck ring, remelting of GM impeller turning,GM DOL bush,SS stud with nut,water seal, revolving disc,EPV impeller,impeller key,repairing of stamping of stator,CI DOL piece,SS coupling with key,CI suction Piece.GMsand guard and any other parts of pump of capacity 75 HP to 100 HP, 3 phase motor driven (excluding motor winding) cast iron/cast steel body complete and connecting with motor portion including reassemblimg the same after repair , and back to site, fixing of repaired booster pump set on its original foundation making proper alignment , including restoration of power supply and testing, commissioning to the entire satisfation of Engr-in-Charge complete all as specified and directed.
M&L for rewinding of 10.0 HP to 12.5 HP booster motor with new super enameled winding copper wire of existing size/gauge after cutting of burned winding including all insulating materials such as insulation varnish,bush, PVC copper cable lead, glass fiber sleeves, cotton tape, insulation paper,bearing sleeve,pump shaft welding,turning,grinding,making key way,TC coupling,CI impeller,CI interstage ring,gland packing,wear ring,bearing housing,fastener,air release valve,eye bolt,ball bearing,water liquid deflector,motor & pump coupling and heating in heat chamber at appropriate temperature complete all as specified and directed.
M&L for rewinding of 20 HP to 25 HP booster motor with new super enameled winding copper wire of existing size/gauge after cutting of burned winding including all insulating materials such as insulation varnish, bush,PVC copper cable lead, glass fiber sleeves, cotton tape, insulation paper,bearing sleeve,pump shaft welding,turning,grinding,making key way,TC coupling,CI impeller,CI interstage ring,gland packing,wear ring,bearing housing,fastener,air release valve,eye bolt,ball bearing,water liquid deflector,motor & pump coupling and heating in heat chamber at appropriate temperature complete all as specified and directed.
M&L for rewinding of 75 HP to 100 HP booster motor with new super enameled winding copper wire of existing size/gauge after cutting of burned winding including all insulating materials such as insulation varnish, bush,PVC copper cable lead, glass fiber sleeves, cotton tape, insulation paper,bearing sleeve,pump shaft welding,turning,grinding,making key way,TC coupling,CI impeller,CI interstage ring,gland packing,wear ring,bearing housing,fastener,air release valve,eye bolt,ball bearing,water liquid deflector,motor & pump coupling and heating in heat chamber at appropriate temperature complete all as specified and directed.
M&L for development of tube well for improvement of water yield by 210 CFM compressor including taking out existing submersible pump set complete with pipe and cable and lowering the same after water yield improvement including necessary traspotation and minor spare parts complete all as specified and directed.
S&F in replacement of Cosmic Star Standard Automatic Star Delta Starter/ controleer for submersible /mono block pump set of capacity 12.5 HP to 15 HP comprising of item Single phasing preventor, overload relay,contactor,Auto/Manual Switch, Amp meter, voltmeter, ON/Off Push Button, Light indicator abd other connected accessories in housing in Sheet steel enclosurer including connection in existing system with cable and all arrangement complete all as specified and directed. Make:- Havells/ L&T/ Standard.
S&F in replacement of Cosmic Star Standard Automatic Star Delta Starter/ controleer for submersible /mono block pump set of capacity 10 HP comprising of item Single phasing preventor, overload relay,contactor,Auto/Manual Switch, Amp meter, voltmeter, ON/Off Push Button, Light indicator abd other connected accessories in housing in Sheet steel enclosurer including connection in existing system with cable and all arrangement complete all as specified and directed. Make:- Havells/ L&T/ Standard.
S&F in replacement of DOL Direct Online Starter suitable for submersible pump set/ mono block/sewage pump set of capacity 7.5 HP comprising of item Single phasing preventor, overload relay,contactor,Auto/Manual Switch, Amp meter, voltmeter, ON/Off Push Button, Light indicator and other connected accessories in housing in Sheet steel enclosurer including connection in existing system with cable and all arrangement complete all as specified and directed. Make:- Havells/ L&T/ Standard.
S&F in replacement of DOL Direct Online Starter suitable for submersible pump set/ mono block pump set of capacity 5 HP comprising of item Single phasing preventor, overload relay,contactor,Auto/Manual Switch, Amp meter, voltmeter, ON/Off Push Button, Light indicator abd other connected accessories in housing in Sheet steel enclosurer including connection in existing system with cable and all arrangement complete all as specified and directed. Make:- Havells/ L&T/ Standard.
S & F in replacement waterproof submersible copper cable flat 6 Sqmm 3 core for bore well of any depth with fitting and connections complete all as specified and as directed.
S & F in replacement of GI water tubing, 100mm bore, medium grade, galvanised (ISI marked as IS-1239), with all fittings including short lengths, fixed to walls, fixed in sewage well, U/G sump,concealed in wall and ceiling or laid in floor trench complete with all fittings (such as bends, elbows,flanges Tee, short pieces, reducer, nipple, connectors, back nuts, diminishing pieces, caps and plugs, unions etc), including excavation ,returning filling and removing wherever reuired complete, all as specified and directed.
All as per item No 34.00 above but size 80mm bore complete all as specified and directed.
All as per item No 34.00 above but size 50mm bore complete all as specified and directed.
All as per item No 34.00 above but size 40mm bore complete all as specified and directed.
All as per item No 34.00 above but size 25mm bore complete all as specified and directed.
All as per item No 34.00 above but size 20mm bore complete all as specified and directed.
All as per item No 34.00 above but size 15mm bore complete all as specified and directed.
M & L for excavation by trenchless boring technology for holes under road pavement, hard standing using ultra sound technique and engaging necessary machine including HDPE pipe ISI marked of dia 200 mm suitable for 0.4 Mpa working pressure complete all as specified and directed Note: HDPE pipe and marking good the disturbed surface shall deemed to be included in quoted rate.
Preventive and comprehensive maintenance of complete fire alarm system(s) installed at Chiman Block (G+8) in reliable, safe and efficient manner using latest techniques & expertise by regularly examining the sensor/detector, Main fire alarm control panels, Repeater panels, Hooters, MCP, Sirens etc of various type / capacity / make, including making the non-functional parts of fire alarm system into fully functional condition, attending day to day complaint / fault(s) every day incl sunday & holiday, including quarterly cleaning of the detectors and monthly joint testing/inspection of the complete fire alarm system, including replacement of items such as wire, lugs, nut, bolts, screws, electronic circuit, chip etc complete all as specified and directed by Engr- in- charge. Note : (i) The complete fire alarm system(s) will be handed over to contractor in existing condition and no claim on this effect will be accepted at any stage. Hence, the bidder is advised to visit the site to access the quantum of work to be carried out in this contract and quote thier rates accordingly. (ii) The cost of all kind of repair /servicing/ replacement of defective equipment/devices and other parts/spares or cell/ batteries as and when required for making the entire fire alarm system(s) fully functional, is deemed to be included in quoted rates and no extra cost shall be paid to the contractor on this effect. (iii) All the complaint / fault (s) will be addressed within 02 hrs from the time of receipt of complaint. If, contractor or his tradesmen fails to attend the complained within 02 hrs from the time of receipt of complaint verbally or telephonically, the compensation/penalty of Rs. 500.00 (Rupees Five Hundred only) per complaint per hr for first 04 hr and after that Rs. 1000 (Rupees one thousand only ) per complaint each day (i.e 24 hrs ) shall be recovered from the contractor’s dues.
Preventive and comprehensive maintenance of complete fire alarm system(s) installed at varunika in reliable, safe and efficient manner using latest techniques & expertise by regularly examining the sensor/detector, Main fire alarm control panels, Repeater panels, Hooters, MCP, Sirens etc of various type / capacity / make, including making the non-functional parts of fire alarm system into fully functional condition, attending day to day complaint / fault(s) every day including sunday and holiday, including quarterly cleaning of the detectors and monthly joint testing/inspection of the complete fire alarm system, including replacement of items such as wire, lugs, nut, bolts, screws, electronic circuit, chip etc complete all as specified and directed by Engr- in- charge. Note : (i) The complete fire alarm system(s) will be handed over to contractor in existing condition and no claim on this effect will be accepted at any stage. Hence, the bidder is advised to visit the site to access the quantum of work to be carried out in this contract and quote thier rates accordingly. (ii) The cost of all kind of repair /servicing/ replacement of defective equipment/devices and other parts/spares or cell/ batteries as and when required for making the entire fire alarm system(s) fully functional, is deemed to be included in quoted rates and no extra cost shall be paid to the contractor on this effect. (iii) All the complaint / fault (s) will be addressed within 02 hrs from the time of receipt of complaint. If, contractor or his tradesmen fails to attend the complained within 02 hrs from the time of receipt of complaint verbally or telephonically, the compensation/penalty of Rs. 500.00 (Rupees Five Hundred only) per complaint per hr for first 04 hr and after that Rs. 1000 (Rupees one thousand only ) per complaint each day (i.e 24 hrs ) shall be recovered from the contractor’s dues.
S&F in replacement of cast iron sluice valve, 150mm bore, hand wheel operated , non rising type with steel spindle complete with flanged ends and gun metal parts including necessary nut, bolts, washers and rubbers gasets, 3mm thick, heavy duty and iron whell all as per site requirement complete with jointing material complete all as specified and directed.
S&F in replacement of cast iron sluice valve, 100mm bore, hand wheel operated , non rising type with steel spindle complete with flanged ends and gun metal parts including necessary nut, bolts, washers and rubbers gasets, 3mm thick, heavy duty and iron whell all as per site requirement complete with jointing material complete all as specified and directed.
S&F in replacement of cast iron sluice valve, 80mm bore, hand wheel operated ,non rising type with steel spindle complete with flanged ends and gun metal parts including necessary nut, bolts, washers and rubbers gasets, 3mm thick, heavy duty and iron whell all as per site requirement complete with jointing material complete all as specified and directed.
S&F in replacement of non return valve, 150mm with flanged ends ,doors and discs cast integral cast hinge lugs to allow free door and disc operation without by pass arrangement, including necessary nut, bolt, washer and rubber gaskets, 3mm thick, heavy duty all as per site requirement complete all as specified and directed.
S&F in replacement of non return valve, 100mm with flanged ends ,doors and discs cast integral cast hinge lugs to allow free door and disc operation without by pass arrangement, including necessary nut, bolt, washer and rubber gaskets, 3mm thick, heavy duty all as per site requirement complete all as specified and directed.
S&F in replacement of non return valve, 80mm with flanged ends ,doors and discs cast integral cast hinge lugs to allow free door and disc operation and without by pass arrangement, ISI marked including necessary nut, bolt, washer and rubber gaskets, 3mm thick, heavy duty all as per site requirement complete all as specified and directed.
S&F in replacement of cast iron body butterly valve, wafer type, gear operated with stainless steel disc of size 150mm, with integrally moulded rubber linning of silicon, double flange all as per site requirement complete all as specified and directed.
S&F in replacement of cast iron body butterly valve, wafer type, gear operated with stainless steel disc of size 100mm, with integrally moulded rubber linning of silicon, double flange all as per site requirement complete all as specified and directed.
S&F in replacement of cast iron body butterly valve, wafer type, gear operated with stainless steel disc of size 80mm, with integrally moulded rubber linning of silicon, double flange all as per site requirement complete all as specified and directed.
S&F in replacement of cast iron body foot valve with strainer, single door, swing check type of size 150mm with all the material and components, flanged ends all as per site requirement complete all as specified and directed.
S&F in replacement of cast iron body foot valve with strainer, single door, swing check type of size 100mm with all the material and components, flanged ends all as per site requirement complete all as specified and directed.
S&F in replacement of cast iron body Y strainer of size 150mm with all the material and components, flanged ends all as per site requirement complete all as specified and directed.
S&F in repair 40 mm dia gate valve, gun metal, heavy duty screwed down both ends with iron wheel head complete all as specified and directed.
S&F in repair 20/25 mm dia gate valve, gun metal, heavy duty screwed down both ends with iron wheel head complete all as specified and directed.
S&F in repair 15 mm dia gate valve, gun metal, heavy duty screwed down both ends with iron wheel head complete all as specified and directed.
Comprehensive maintenance and repair of 62.5 KVA DG Set with AMF including servicing,oiling,greasing and replacement of defective parts/ fitting inclunding all required electrical and mechanical Spares required for comprehensive maintenance during the entire contract period complete all as specified and directed. Make- Jakson Note:-The qouted rate shall be inclusive of spare parts required for smooth functioning of DG set.
M&L for cleaning of RCC underground water sump of approx capacity upto 455000 Ltrs by removing the mud/settled bleaching powder and all other foreign material from the sump and depositing where directed but not less than 50 mtr from the starting point including scraping / removing all dirt/scales from the internal wall of the sump and washing the bottom surface and wall surface of the sump with clean water, draining out the dirty water so that the whole sump be thoroughly cleaned after pumping out all existing water by portable centrifugal/mono block submersible pumping set, applying one coat of bleaching powder on the all inner wall surface of sump including bottom surface and writing the date of cleaning on the sump complete all as specified and directed.
Comprehensive, preventive and periodical maintenance of washer extractor (03 Nos) of capacity 60 Kg per charge Make: STEFAB/FEBCARE installed at NOM-Varuna in reliable, safe and efficient manner by regular examining, lubricating and adjusting the mechanical and electrical driving equipment including repacement of defective / spares parts as "Supply only" and testing on completion to the entire satisfaction of Engr-in-charge complete all as specified and directed. Note:- (i) The contractor shall have MOU for providing service and material with Laundry plant manufacturer, M/s STEFAB, FEBCARE, (ii) Spare parts to be replaced as listed in sch 'A' to be measured and paid seperately as supply only. Fixing charge is deemed to be included in this item. (iii) All the complaints will be rectify within 24 hrs from the time of receipt of complaint. If contractor fails to rectify the complaint within 24 hrs from the time of receipt of complaint, the compensation / penalty of Rs 500.00 per complaint per day shall be recovered from the contractor's dues.) (iv) Any items not covered under as supply only shall be deemed to be included in this section for the smooth functioning of laundry plant and the contractor may quote the rate accordingly. Contractor is expected to inspect the laundry plant at NOM Varuna before quoting the rate.
Supply only in replacement Programmable Logical Card (PLC) ST-6 type complete all as specified and directed.
Supply only in replacement of V-Belt of suitable size for 60 Kg per charge washer extractor complete all as specified and directed.
Supply only in replacement of filter regulator suitable for 10 bars maximum pressure & 0.5-10 bars pressure range suitable for 60 Kg per charge washer extractor complete all as specified and directed.
Supply only in replacement of lubricator suitable for 10 bars maximum pressure suitable for 60 Kg per charge washer extractor complete all as specified and directed.
Supply only, in replacement of main shocker suitable for Washer Extractor of 60 Kg capacity including nut,bolt and washer complete all as specified and directed.
Supply only in replacement of water outlet valve of existing size with diaframe inside suitable for 60 Kg washer extractor complete all as specified and directed.
Supply only in replacement of water inlet inlet valve of existing size suitable for 60 Kg washer extractor complete all as specified and directed.
Supply only in replacement of dosing valve of existing size suitable for 60 Kg washer extractor complete all as specified and directed.
Supply only, in replacement of main spring heavy duty suitable for Washer Extractor of 60 Kg capacity complete all as specified and directed by Engr-in-Charge.
Supply only, in replacement of door lock latch handle suitable for Washer Extractor of 60 Kg capacity complete all as specified and directed by Engr-in-Charge. As per existing sample.
Supply only in replacement of filter suitable for 60 Kg per charge washer extractor complete all as specified and directed.
Supply only in replacement of heating element 6 KW, 240 volts, 50 Hz suitable for solar water heating unit complete all as specified and directed.
Supply only in replacement of Main bearing set of size (6315,2RS and 6316,2RS) (set of 02) of suitable dia and thickness for Washer Extractor of 60 Kg complete all as specified and directed by Engr-in-Charge.
Supply only in replacement of Main bearing seal set of vieton suitable for Washer Extractor of 60 Kg capacity complete all as specified and directed by Engr-in-Charge.
Supply only in replacement of Digital Display Controller Unit (AWX-60) suitable for 60 Kg extractor complete all as specified and directed.
Supply only in replacement variable frequency drive suitable for 60 Kg per charge washer extractor complete all as specified and directed.
Comprehensive, preventive and periodical maintenance of drying tumbler (02 Nos) of capacity 60 Kg per charge Make: STEFAB/FEBCARE installed at NOM-Varuna in reliable, safe and efficient manner by regular examining, lubricating and adjusting the mechanical and electrical driving equipment including repacement of defective / spares parts as "Supply only" and testing on completion to the entire satisfaction of Engr-in-charge complete all as specified and directed. Note:- (i) The contractor shall have MOU for providing service and material with Laundry plant manufacturer, M/s STEFAB, FEBCARE, (ii) Spare parts to be replaced as listed in sch 'A' to be measured and paid seperately as supply only. Fixing charge is deemed to be included in this item. (iii) All the complaints will be rectify within 24 hrs from the time of receipt of complaint. If contractor fails to rectify the complaint within 24 hrs from the time of receipt of complaint, the compensation / penalty of Rs 500.00 per complaint per day shall be recovered from the contractor's dues. (iv) Any items not covered under as supply only shall be deemed to be included in this section for the smooth functioning of laundry plant and the contractor may quote the rate accordingly. Contractor is expected to inspect the laundry plant at NOM Varuna before quoting the rate.
Supply only in replacement Programmable Logical Card (PLC) as per existing typetype complete Make Stefab complete all as specified and directed.
Supply only in replacement of Digital Display Controller Unit suitable for 60 Kg per charge drying tumbler complete all as specified and directed.
Supply only in replacement of V-Belt of suitable size for 60 Kg per charge drying tumbler complete all as specified and directed.
Supply only, in replacement of main shocker suitable for drying tumbler of 60 Kg capacity including nut,bolt and washer complete all as specified and directed by Engr-in-Charge.
Supply only in replacement of heating element 2 KW, 240 volts, 50 Hz suitable for solar water heating unit complete all as specified and directed.
Supply only in replacement of thermostat suitable for drying tumbler of 60 Kg capacity complete all as specified and directed.
Supply only in replacement of Main bearing set of size (2208 and 2210) (set of 02) of suitable dia and thickness for drying tumbler of 60 Kg complete all as specified and directed.
Supply only, in replacement of door lock latch handle suitable for drying tumbler of 60 Kg capacity complete all as specified and directed by Engr-in-Charge. As per existing sample.
Supply only, in replacement of padding set suitable for Flat bed Press complete all as specified and directed by Engr-in-Charge.
Supply only, in replacement of main bearing suitable for Flat bed Press complete all as specified and directed by Engr-in-Charge.
Supply only in replacement of Table switch suitable for 60 Kg per charge STEFAB/ FEBCARE Make washer extractor complete all as specified and directed.
Comprehensive, preventive and periodical maintenance of washer extractor (01 Nos) of capacity 60 Kg per charge Make: Lucky Engnrs works installed at NSB-I Chankyapuri in reliable, safe and efficient manner by regular examining, lubricating and adjusting the mechanical and electrical driving equipment including repacement of defective / spares parts as "Supply only" and testing on completion to the entire satisfaction of Engr-in-charge complete all as specified and directed. Note:- (i) The contractor shall have MOU for providing service and material with Laundry plant manufacturer, M/s STEFAB/FEBCAR/Lucky Engnr works, (ii) Spare parts to be replaced as listed in sch 'A' to be measured and paid seperately as supply only. Fixing charge is deemed to be included in this item. (iii) All the complaints will be rectify within 24 hrs from the time of receipt of complaint. If contractor fails to rectify the complaint within 24 hrs from the time of receipt of complaint, the compensation / penalty of Rs 500.00 per complaint per day shall be recovered from the contractor's dues (iv) Any items not covered under as supply only shall be deemed to be included in this section for the smooth functioning of laundry plant and the contractor may quote the rate accordingly. Contractor is expected to inspect the laundry plant at NSB-I Chankyapuri before quoting the rate.
Supply only in replacement of filter regulator suitable for 10 bars maximum pressure & 0.5-10 bars pressure range suitable for 60 Kg per charge washer extractor complete all as specified and directed.
Supply only in replacement of lubricator suitable for 10 bars maximum pressure suitable for 60 Kg per charge washer extractor complete all as specified and directed.
Supply only, in replacement of main shocker suitable for Washer Extractor of 60 Kg capacity including nut,bolt and washer complete all as specified and directed by Engr-in-Charge.
Supply only in replacement of water outlet valve of existing size with diaframe inside suitable for 60 Kg washer extractor complete all as specified and directed.
Supply only in replacement of water inlet inlet valve of existing size suitable for 60 Kg washer extractor complete all as specified and directed.
Supply only in replacement of dosing valve of existing size suitable for 60 Kg washer extractor complete all as specified and directed.
Supply only, in replacement of main spring heavy duty suitable for Washer Extractor of 60 Kg capacity complete all as specified and directed by Engr-in-Charge.
Supply only in replacement of filter suitable for 60 Kg per charge washer extractor complete all as specified and directed.
Supply only in replacement of heating element 6 KW, 240 volts, 50 Hz suitable for solar water heating unit complete all as specified and directed.
Supply only in replacement of Main bearing seal set of vieton suitable for Washer Extractor of 60 Kg capacity complete all as specified and directed by Engr-in-Charge.
Comprehensive, preventive and periodical maintenance of drying tumbler (01 No) of capacity 60 Kg per charge Make: Lucky Engnr works installed at NOM-Varuna in reliable, safe and efficient manner by regular examining, lubricating and adjusting the mechanical and electrical driving equipment including repacement of defective / spares parts as "Supply only" and testing on completion to the entire satisfaction of Engr-in-charge complete all as specified and directed. Note:- (i) The contractor shall have MOU for providing service and material with Laundry plant manufacturer, M/s STEFAB, FEBCARE/Lucky Engnr Works, (ii) Spare parts to be replaced as listed in sch 'A' to be measured and paid seperately as supply only. Fixing charge is deemed to be included in this item. (iii) All the complaints will be rectify within 24 hrs from the time of receipt of complaint. If contractor fails to rectify the complaint within 24 hrs from the time of receipt of complaint, the compensation / penalty of Rs 500.00 per complaint per day shall be recovered from the contractor's dues. (iv) Any items not covered under as supply only shall be deemed to be included in this section for the smooth functioning of laundry plant and the contractor may quote the rate accordingly. Contractor is expected to inspect the laundry plant at NSB-I Chanakyapuri before quoting the rate.
Supply only in replacement Programmable Logical Card (PLC) as per existing typetype complete Make Stefab complete all as specified and directed.
Supply only in replacement of V-Belt of suitable size for 60 Kg per charge drying tumbler complete all as specified and directed.
Supply only, in replacement of main shocker suitable for drying tumbler of 60 Kg capacity including nut,bolt and washer complete all as specified and directed by Engr-in-Charge.
Supply only in replacement of heating element 2 KW, 240 volts, 50 Hz suitable for solar water heating unit complete all as specified and directed.
Supply only in replacement of thermostat suitable for drying tumbler of 60 Kg capacity complete all as specified and directed.
Supply only in replacement of Main bearing set of size (2208 and 2210) (set of 02) of suitable dia and thickness for drying tumbler of 60 Kg complete all as specified and directed by Engr-in-Charge.
Comprehensive, preventive and periodical maintenance including replacement of defective spare parts of Steam Boiler of 04 Kg -01 No and 06 Kg -01 No capacity (Make : stefeb/Febcare) by engaging sufficient man power and suitable T&P to ensure safety of boiler as well as working persons including disconnecting of water / steam / electric connections, dismantling of boiler plant by unscrewing/cutting of screws, nuts & bolts etc, taking out complete coil assembly and other major parts from the boiler etc, replacing all defective spares parts (Spare parts shall be measured and paid in this section ) cleaning / servicing of coil assembly incl electrical control panel board, all machine works i.e. welding, cutting, drilling etc as and when required and reassembling all dismantled part/items after carrying out necessary repair as required, other material, cleaning, servicing, oiling, greasing etc, making all steam / water connection and electrical connection, leak testing at desired pressure, with and including testing, commissioning of complete boiler plant in original location for smooth and trouble free operation, to entire satisfaction of Engineer-in-charge, complete all as specified and directed by Engr-in-Charge.
S&F in replacement of heating element 4 KW, 240 volts, 50 Hz suitable for solar water heating unit complete all as specified and directed.
S&F in replacement of heating element 6 KW, 240 volts, 50 Hz suitable for solar water heating unit complete all as specified and directed.
S&F in replacement of high pressure pump for boiler of existing size complete all as specified and directed by Engr-in-Charge.
S&F in replacement of ball valve 15 mm of ss complete all as specified and directed.
M&L for Earthing complete with galvanized steel earth plate electrode 60 cm x 60 cm x 6 mm thick buried directly in ground (earth pit not less than 2.25 metres deep below normal ground level) with top edge of plate not less than 1.5 metres below normal ground level, connecting to the Galvanised iron strip 25x4 mm by means of bolts, nuts , check nuts and washers of galvanized iron and steel earth wire protected by provision of GI light grade pipe 40 mm bore including provision of concrete pit made from PCC ( 1:2:4) type B-1 (using 20 mm graded stone aggregate) with 40mm thick cover of RCC 1:2:4 reinforced with XPM (Weight not less than 4 Kg/Sqm) and frame of angle iron 40 x 40 x 6 mm and handle of 6 mm dia MS bar made to shape, GI light grade 20 mm bore pipe for watering perforated at bottom, 1.50 metre long placed on top edge of earth plate, common salt & charcoal filling, with fixing arrangement , funnel, wire mesh and earth work in hard/dense soil , returning filling in and removal of surplus soil to a distance not exceeding 50 metres, all as per electrical plate No 5 of SSR 2009 Part-I and connecting to starter panel including taking down old unsv earthing complete all as specified and directed.
S & F in replacement of old unserviceable overload relay suitable for 20 HP to 25 HP motor and connected internal wiring complete all as specified and directed by Engineer -In- Charge. Note:- The rate is inclusive of connection out the starter and make the connection after replacement of realy.
S & F in replacement of old unserviceable contactor suitable for 20 HP to 25 HP motor and connected internal wiring complete all as specified and directed by Engineer -In- Charge. Note:- The rate is inclusive of connection out the starter and make the connection after replacement of realy.
S & F in replacement of old unserviceable single phase preventor and connected internal wiring suitable for 20 HP to 25 HP motor starter complete all as specified and directed by Engineer -In- Charge. Note:- The rate is inclusive of connection out the starter and make the connection after replacement of realy.
S & F in replacement of old unserviceable phase sequence corrector relay 440V , 50 HZ Supply suitable for 20 HP to 25 HP motor starter and connected internal wiring complete all as specified and directed by Engineer -In- Charge. Note:- The rate is inclusive of connection out the starter and make the connection after replacement of realy.
S & F in replacement of old unserviceable overload relay suitable for 75 HP to 100 HP motor and connected internal wiring complete all as specified and directed by Engineer -In- Charge. Note:- The rate is inclusive of connection out the starter and make the connection after replacement of realy.
S & F in replacement of old unserviceable contactor suitable for 75 HP to 100 HP motor and connected internal wiring complete all as specified and directed by Engineer -In- Charge. Note:- The rate is inclusive of connection out the starter and make the connection after replacement of realy.
S & F in replacement of old unserviceable single phase preventor and connected internal wiring suitable for 75 HP to 100 HP motor starter complete all as specified and directed by Engineer -In- Charge. Note:- The rate is inclusive of connection out the starter and make the connection after replacement of realy.
S & F in replacement of old unserviceable phase sequence corrector relay 440V , 50 HZ Supply suitable for 75 HP to 100 HP motor starter and connected internal wiring complete all as specified and directed by Engineer -In- Charge. Note:- The rate is inclusive of connection out the starter and make the connection after replacement of realy.
S & F in replacement of old unserviceable overload relay suitable for 10 HP to 12.5 HP motor and connected internal wiring complete all as specified and directed by Engineer -In- Charge. Note:- The rate is inclusive of connection out the starter and make the connection after replacement of realy.
S & F in replacement of old unserviceable contactor suitable for 10 HP to 12.5 HP motor and connected internal wiring complete all as specified and directed by Engineer -In- Charge. Note:- The rate is inclusive of connection out the starter and make the connection after replacement of realy.
S & F in replacement of old unserviceable single phase preventor and connected internal wiring suitable for 10 HP to 12.5 HP motor starter complete all as specified and directed by Engineer -In- Charge. Note:- The rate is inclusive of connection out the starter and make the connection after replacement of realy.
S & F in replacement of old unserviceable phase sequence corrector relay 440V , 50 HZ Supply suitable for 10 HP to 12.5 HP motor starter and connected internal wiring complete all as specified and directed by Engineer -In- Charge. Note:- The rate is inclusive of connection out the starter and make the connection after replacement of realy.
S & F in replacement of old unserviceable overload relay suitable for 7.5 HP motor and connected internal wiring complete all as specified and directed by Engineer -In- Charge. Note:- The rate is inclusive of connection out the starter and make the connection after replacement of realy.
S & F in replacement of old unserviceable contactor suitable for 7.5 HP motor and connected internal wiring complete all as specified and directed by Engineer -In- Charge. Note:- The rate is inclusive of connection out the starter and make the connection after replacement of realy.
S & F in replacement of old unserviceable single phase preventor and connected internal wiring suitable for 7.5 HP motor starter complete all as specified and directed by Engineer -In- Charge. Note:- The rate is inclusive of connection out the starter and make the connection after replacement of realy.
S & F in replacement of old unserviceable phase sequence corrector relay 440V , 50 HZ Supply suitable for 7.5 HP motor starter and connected internal wiring complete all as specified and directed by Engineer -In- Charge. Note:- The rate is inclusive of connection out the starter and make the connection after replacement of realy.
S & F in replacement of old unserviceable indication lamp in R,Y,B colour and connected internal wiringin for motor starter complete all as specified and directed by Engineer-In-Charge.
S & F in replacement of old unserviceable Rotary switch and connected internal wiringin for motor starter complete all as specified and directed by Engineer-In-Charge.
S & F in replacement of old unserviceable push button and connected internal wiringin for motor starter complete all as specified and directed by Engineer-In-Charge.
S&F in repair 3 Phase Digital Ammeter including wiring from CT to meter complete all as specified and as directed.
S&F in replacement of Digital voltmeter as per existing including wiring complete all as specified and as directed.
Comprehensive, preventive and periodical maintenance of exhaust system (03 Nos) Make: zeeco installed at NOM-Varuna in reliable, safe and efficient manner by regular examining, lubricating,cleaning and adjusting the mechanical and electrical driving equipment including repacement of defective spares parts and testing on completion to the entire satisfaction of Engr-in-charge complete all as specified and directed. Note:- (i) Cleaning of wet type scrubber,air washer,fan section with DIDW type centrifugal pump,wet section with double bank spray header,double skin type evaporative air cooling machines,double screen package type machine with backward curve blsde and forward curved blade and duct should be carried out each month by suitable means (ii)Repair/replacement of any unserviceable/defective parts/machines for smooth functioning of exhaust system. (iii) All the complaints will be rectify within 24 hrs from the time of receipt of complaint. If contractor fails to rectify the complaint within 24 hrs from the time of receipt of complaint, the compensation / penalty of Rs 500.00 per complaint per day shall be recovered from the contractor's dues.) (iv) The rates for centrifugal pump set repairs should be paid separately under respective item. (v) System should maintain proper cooling inside the galley. Contractor is expected to inspect the exhaust system at NOM Varuna before quoting the rate.
S & F in repair CP push cock 15mm dia for water cooler complete all as specified and directed.
S & F in repair ball cock PTMT 15mm dia for water cooler with aluminium rod and PVC ball complete all as specified and directed.
M & L for excavation by trenchless boring technology for holes under road pavement, hard standing using ultra sound technique and engaging necessary machine suitable for 0.4 Mpa working pressure complete all as specified and directed Note:- marking good the disturbed surface shall deemed to be included in quoted rate.
Supply & Laying in replacement of XLPE LT cable size 25 sqmm 3.5 core 1100 volts grade heavy duty with XLPE insulated stranded aluminium conductor served with an inner sheathing of PVC Tape armoured with galvanized steel strip or wire and over all PVC Sheathed stranded conductor conforming to IS-7098 (Part-I) with latest amendments laid in tranches/fixed to wall/pole/laid in floor including necessary connections and suitable size of thimbling complete all as specified and as directed by Engineer-in-Charge. Note : If Required Excavation , returning filling and removing, sand cushioning , brick protection of cable shall be measured and paid under this item of schedule
All as per Item No 139.00 above but size 35 sqmm 3.5 core complete all as specified and directed.
All as per Item No 139.00 above but size 50 sqmm 3.5 core complete all as specified and directed.
All as per Item No 139.00 above but size 70 sqmm 3.5 core complete all as specified and directed.
All as per item No 139.00 above but size 95 sqmm 3.5 core complete all as specified and directed.
All as per Item No 139.00 above but size 120 sqmm 3.5 core complete all as specified and directed.
All as per item No 139.00 above but size 240 sqmm 3.5 Core complete all as specified and directed.
All as per item No 139.00 above but size 400 sqmm 3.5 Core complete all as specified and directed.
All as per item No 139.00 above but size 16 sqmm 4.0 core complete all as specified and directed.
M&L for locating the fault in underground electrical power cable of any length & any type of 1100 grade LT cables, by arranging fault locating Machine & pin point the fault, cutting the cable at fault to fixing the joint including testing of the cable after locating fault and jointing cable including excavation and earth work in any type of soil complete all as specified and as directed. Note: (i) Jointing of cable shall be measured and paid separately under respective item of this Schedule. (ii) If fault is not rectified within 24 hours after receiving Message, the contractor shall be charged penalty for Rs 500/- per hour per complaint and shall be deducted from next payment due to contractor.
Supply, fixing, testing and commissioning in replacement of cable joint kit for 1.1 KV grade cable size 25 to 35 sqmm cable of 3.5/4 core size for straingt through joint heat shrinkable type joint complete with jointing material and accessories suitable complete all as specified and directed.
All as per item No 149.00 but size 50 to 95 Sq mm cable of 3.5core size complete all as specified and directed.
All as per item No 149.00 above but size 185 to 400 Sq mm cable of 3.5 core size complete all as specified and directed.
Material & Labour for road cutting, including excavation, returning filling in, spreading, leveling well ramming in layers, soling with broken boulders/stones, WBM 7.5 cm thick coarse aggregate received from dismentling the existing road, premix, carpeting 25 mm thick using ready mix patch mate material, rolled and compacted for road patch repair work, complete all as specified and directed by Engr-in-Charge.
M&L for supply, erection, testing & commissioning of 8 metre high made out of 3 mm thick galvanized iron sheet hot dip octagonal street light pole in one segment with one longitudinal welding joint including galvanized MS sheet with window/door opening with one MCB SP 6 to 16 Amps & TPN connector block 40 Amps having flash cover including necessary earth work (excavation, returning filling & removal) in soft/loose soil, RCC (grade M20) in foundation as per recommended design of manufacturer considering safe soil bearing capacity at site including suitable size & minimum 04 Nos foundation bolts of minimum dia 22 mm & 750 mm long "J"-type alongwith nuts, washers, anchor plates and templates, 50 mm dia PVC pipe in foundation for entering cable complete including dismantling of existing old unsv PCC pole complete all as specified and directed. The foundation details shall be as under:- (a) RCC foundation size below GL will be 600 mm x 600 mm x 1300 mm (depth) (minimum) and above GL shall be 300 mm high of same section. (b) Main reinforcement in RCC shall be 20 mm dia 8 Nos TMT steel bars in vertical and stirrups of 8 mm dia @ 190 mm c/c. ( c) Base plate and anchoring plate shall be of minimum size 225 x 225 x 16 mm thick. (d) RCC (grade M20) in foundation. (e) Anchoring bolts shall be of "J"-type 750 mm long and 22 mm dia MS rod. Make: Cat Pt No. HM-1109P of Crompton Greaves or equivalent in L&T/ schneider
S&F in repair single arm bracket of minimum length 1.00 mtr,GI pipe duly fixed with necessary fixing arrangement complete all as specified and directed.
Disconnecting HT supply and taking out ACB of any make and rating 630 Amps to 1250Amp and servicing by cleaning the fix and moving parts, removing dust particles by using high speed blower applying grease / jelly to moving mechanism and moving parts, tightening nut bolts of all the components of ACB and replacement of all unserviceable spares as required, testing commissioning and putting on the supply on load and testing with VI injecting instrument for full load test/calibration for work efficiently in the tripping circuit complete all as specified and directed by Engr-in-Charge. Note:- (i) Spares as required for replacement shall be of the same company as of existing make. Spares parts shall be measured and paid seperately as supply only under respective item on Sch 'A'. Fixing charges deemed to be included in this item. (ii) All Measuring equipments and T&P required shall be arranged by the contractor. (iii) A sum of Rs. 1000/- will be recovered from the contractor for non rectification of breakdown/fault or replacement of any unserviceable spares after 12 hours from lodging of complaint telephonically or verbaly. (vii) Thereafter Rs. 600/- will be added every day till rectification of fault or replacement of unserviceable spares complete all as specified and directed by Engr-in-Charge.
Supply only in repair Earth Fault protection relay for ACB of capacity 1000 Amps complete all as specified and directed.
Supply only in repair 3 Phase Digital programmable Ammeter including wiring from CT to meter and Bus bar complete all as specified and directed.
Supply only in replacement of Digital programmable voltmeter as per existing including wiring complete all as specified and directed.
Supply only in replacement of LED Phase Indication Light (set of three) and its connection complete all as specified and directed.
Supply only in repair Breaker Control Switch (TNC) to operate ACB's including fixing charges and required wiring for ACB's complete all as specified and directed.
Supply only in replacement manual charging handle suitable for LT ACB of any make and rating 630 Amps to 1250 Amps as per existing make and model complete all as specified and directed by Engr-in-Charge.
Supply only in replacement UVR under voltage release coil assembly suitable for LT ACB of any make and rating 630 Amps to 1250 Amps as per existing make and model complete all as specified and directed by Engr-in-Charge.
Supply only in replacement of Male/Female contact set suitable for LT ACB of 630 Amps to 1250 Amps as per existing make and model complete all as specified and directed by Engr-in-Charge.
Supply only in replacement of metering CT of suitable ratio for LT ACB of rating 630 Amps to 1250 Amps as per existing make and model complete all as specified and directed.
Supply only in replacement of Racking inter lock complete suitable for LT ACB of rating 630 Amps to 1250 Amps as per existing make and model complete all as specified and directed.
S&F in replacement of MCCB, 4 pole, 415 volt of capacity 100 amp, Ics=100% Icu, adjustable thermal setting 80-100% with breaking capacity 16 KA including suitable thimbles complete all as specified and directed.
All as per item No. 167.00 here-in-before but 125 Amps breaking capacity not less than 36 KA complete all as specified and directed.
All as per item No. 167.00 here-in-before but 200 Amps breaking capacity not less than 36 KA complete all as specified and directed.
All as per item No. 167.00 here-in-before but 250 Amps breaking capacity not less than 36 KA complete all as specified and directed.
All as per item No. 167.00 here-in-before but 400 Amps breaking capacity not less than 36 KA complete all as specified and directed.
All as per item No. 167.00 here-in-before but 630 Amps breaking capacity not less than 50 KA complete all as specified and directed.
All as per item No. 167.00 here-in-before but 3 Pole 63 Amps breaking capacity not less than 16 KA complete all as specified and directed.
All as per item No. 167.00 here-in-before but 3 Pole 100 Amps breaking capacity not less than 16 KA complete all as specified and directed.
All as per item No. 167.00 here-in-before but 3 Pole 125 Amps breaking capacity not less than 16 KA complete all as specified and directed.
All as per item No. 167.00 here-in-before but 3 Pole 160 Amps breaking capacity not less than 36 KA complete all as specified and directed.
All as per item No. 167.00 here-in-before but 3 pole 200 Amps breaking capacity not less than 36 KA complete all as specified and directed.
All as per item No. 167.00 here-in-before but 3 pole 250 Amps breaking capacity not less than 36 KA complete all as specified and directed.
All as per item No. 167.00 here-in-before but 3 Pole 400 Amps breaking capacity not less than 36 KA complete all as specified and directed.
S&F in replacement MCB TPN/ Isolator 4P from 63 Amps 415 volts, 'C' Series 10 KA as per site requirement complete all as specified and directed.
S&F in replacement MCB TPN/ Isolator 4P from 100 Amps 415 volts, 'C' Series 10 KA as per site requirement complete all as specified and directed.
S&F in replacement MCB TP 3P from 63 Amps 415 volts, 'C' Series 10 KA as per site requirement complete all as specified and directed.
S&F in replacement of digital type Ampere meter range 0-(100/200/400) Amps, square type, flush mounted of size 96 mm x 96 mm and making connection with copper conductor cable of suitable size complete all as specified and directed.
Supply and fix in replacement of digital type Voltmeter range 0-500 volt, square type flush mounted size 96 mm x 96 mm and making connection with copper conductor cable of suitable size complete all as specified and directed.
S&F in replacement of decorative LED type post top lanterns luminaire 40 watts, out door type for 360 degree indirect light with resistant to corrosion, glare free having better uniformity complete with suitable driver complete all as specified and directed. Make: Crompton Greaves Cat pt No. LPTO-40/CDL or equivalent of make as specified in PS.
S&F in replacement of ARCHNER LED type post top light 45 watts, PDC aluminium housing with opal diffuser,IP- 65 protection ,input voltage 140-270 Volt, 50 HZ ,Total hormonic distortaion less than 10%,CCT- warm white and power factor greater than 0.95 out door type complete with GI decorative light pole of suitable length and size with necessary foundation for fixing the light pole complete all as specified and directed. Make: Bajaj Cat pt No BGCPNP 45 W LED WW or equivalent of make as specified in PS.
S&F in repair LED bollard luminaire 10 watts, inverted pyramid tripod type with soft 360 degree light out door type having resistant to corrosion with better optics for uniform distribution complete with suitable driver & fixing nuts, bolts & washers complete all as specified and directed. Make: Crompton Greaves Cat pt No LBLSN-10CDL or equivalent of make as specified in PS.
S & F in repair LED flood light luminaires 40 watts, 230 volts AC, out door type with pressure die cast aluminium housing resistant to impact and corrosion, glare free complete with lamp, driver complete all as specified and directed.
S & F in repair LED flood light luminaires 90 watts, 230 volts AC, out door type with pressure die cast aluminium housing resistant to impact and corrosion, glare free complete with lamp, driver complete all as specified and directed.
S&F in repair LED flood light luminaires 120 watt , 230 volt AC, out door type with pressure die cast aluminium housing resistant to impact and corrosion, glare free complete with lamp, driver complete all as specified and directed.
S & F in replacement of Integral aviation obstruction light luminaires comprising of aluminium housing with polycarbonate encloser including 230 volts, 50 Hz red coloured complete with all fixing accessories including minimum 01 RM medium grade GI tube of 25 mm bore with suitable reducer & suitable PCC foundation and all standard accessories complete all as specified and directed.
S&F in replacement of LED Street light fitting 45 Watt Highly efficient made of pressure die cast aluminium housing with lens & toughened glass in replacement of old unservicable conventional security light fitting including fixing material ie MS clamp, Nut and bolt,anchor fastner washer etc complete all as specified and directed.
S&F in replacement of LED Street light fitting 120 Watt Highly efficient made of pressure die cast aluminium housing with lens & toughened glass in replacement of old unservicable conventional security light fitting including fixing material ie MS clamp, Nut and bolt,anchor fastner washer etc complete all as specified and directed.
S&F in replacement of LED Street light fitting 135 Watt Highly efficient made of pressure die cast aluminium housing with lens & toughened glass in replacement of old unservicable conventional security light fitting including fixing material ie MS clamp, Nut and bolt,anchor fastner washer etc complete all as specified and directed.
S & F in replacement of ornamental street light 120 Watt, 230 Volt AC ,outdoor type with spun aluminiumdesigner housing with clearacrylic for city beautification with IP 65 protection all as specified and directed by Engineer-In-Charge. Make: Halonix Cat No HLOSL-04-120-CWL or equivalent of make as specified in PS.
Supply and fix in repair sports light fitting 480 watt LED complete with suitable bracket , and fixing arrengment like bracket clamp complete all as specified and directed. Make: Philips cat part Part No BVP621 LED504/CW 480W 220-240V NB GM or equivalent of make as specified in PS.
S&F in replacement of LED driver having input voltage as 200-260 Volts AC 50 HZ & output voltage as 12 Volt DC Suitable for 40 to 120 watt LED Fitting driver complete including making proper electic connection complete all as specified and directed.
S&F in replacement of LED Fountain light 27 Watt water proof ,adjustable type IP 67 complete with stainless steel housing toughened glass LED lens of multicolour including necessary nut,bolt,anchor,fastner,washer etc complete all as specified and directed.
Supply & fix in replacement of SS fountain nozzle of suitable size (as per sample) for fountain outer ring complete all as specified and directed.
M&L for painting of steel tubuler pole after Cleaning and scraping with wire brush complete with two coat of aluminium paint over a coat of red oxide primer and applying one coat of cement base paint on PCC coping complete all as specified and directed.
M& L for Painting of LT Panel of any sizes after cleaning and scraping old paint with wire brush with two coat existing paint over a one coat of red oxide primer by using spary gun and applying one coat of cement base paint on PCC foundation complete all as specified and directed.
Supply and fix in replacement of decorative post top 40 Watt LED light pole with suitable length and size alongwith suitable foundation and nut bolts for fixing the pole and refix the light on newly mounted pole including taking down old rusted/broken pole of any type complete all as specified and directed by Engr-In-Charge.
Taking out complete 8 Mtr street light pole alongwith street light fitting from existing site and refixing the same pole with new foundation concret , including grouting with new nut bolts, and refixing/reconnecting the street light after completion of fixing of pole work complete all as specified and directed by Engr-in -Charge
Material and labour for design, development, commissioning & testing EHCC certified ground tubular effective earthing system to give earth resistance less than 2 ohm ,hollow tube solid bar (CPRI tested for 15 kA current capacity for LT line) highly anticorrosive long life electrode with and including adequate protective coating to withstand severe wear conditions in the earth pit and of size std medium grade GI tube outside secondary conductor of 80mm dia and main primary conductor inside of 25x4mm copper strip 3000mm length ready to install with suitable connecting terminal confirming to IS: 3043:1987 specification highly conductive packing material to be filled in earth pits for providing uniform low resistivity anticorrosive hygroscopic medium around the earth system for improving the efficiency of current dissipation 25 Kg per bag (3 bag per kit) min or sufficient quantities required as per site complete including main copper earthing lead of size 25x6 mm up to 7.50 metre to connect with equipment and including PCC 1:2:4 type B0 using 12 mm graded crushed stone aggregate pit chamber with FRP pit cover of size 0.30x0.30x0.30m and cutting of rocks if available at site in a rocky area including necessary earth work in any type of soil including taking down old unsv earthing any type complete all as specified and directed.
Supply, Installation, testing and commissioning in replacement of 4 Pole Automatic Transfer Switch (ATS) 400 Amps, 415 Volts, 50 Hz, automatic/manual type with inbuilt time delay complete with enclosure complete all as specified and directed.
Supply, Installation, testing and commissioning in replacement of 4 Pole Automatic Transfer Switch (ATS) 125 Amps, 415 Volts, 50 Hz, automatic/manual type with inbuilt time delay complete with enclosure complete all as specified and directed.
Supply, installation, testing and commissioning in replacement of 4 pole phase corrector unit 100 Amps, 415 Volts, 50 Hz, automatic/manual type with inbuilt time delay complete with enclosure complete all as specified and directed.
S&F in repair thermoplastic cable junction box with metric knock out for cable entry of size 200x160x98mm with 4 Nos of 200A aluminium busbar mounted on insulators, terminal and MCB 10A capacity including fixing with clamp 30x5mm iron flate, nuts, bolts and washer complete including providing of steel conduit of dia 32mm bore of length 1.60 mtr including earth work for taking out of cable and fixing complete all as specified and directed.
S&F in repair copper thimble ring/pin type of size 6 Sq mm to 10 Sqmm complete all as specified and directed.
S&F in repair aluminiumn thimble ring/pin type of size 16 Sq mm to 35 Sqmm complete all as specified and directed.
S&F in repair aluminium thimble ring/pin type of size 50 Sq mm to 120 sq mm complete all as specified and directed.
S&F in repair aluminium thimble ring/pin type of size 150 Sq mm to 300 sq mm complete all as specified and directed.
S & F in replacement of Auto/ Manual switch for security light panel as per sample complete all as specified and directed.
S & F in replacement of digital timer for security light panel complete all as specified and directed by Engr-In-Charge.
S & F in replacement of HRC Fuse 20 Amps for security light panel complete all as specified and directed by Engr-In-Charge.
S & F in replacement of fuse 800 Amps for fuse box complete all as specified and directed by Engineer-In-Charge.
S&F in replacement Off load Changeover Switch - 200 Amps 415 Volts 50 HZ 4 pole handle operated type inclduing taking down old change over complete all as specified and directed.
S&F in replacement Off load Changeover Switch - 400 Amps 415 Volts 50 HZ 4 pole on load side handle operated type inclduing taking down old change over complete all as specified and directed.
Supply and fixing in replacement of flexible tricolour/triglow LED rope light of 18 Meter length and wattage capacity of 6 Watt per meter & high brightness for outdoor application (light must be change its colour at equal interval) including driver and its connection complete all as specified and directed by Engr-In-Charge. Make: Philips Cat No/Model No 582183 or equivalent of make as specified in PS.
S & F in replacement of Heavy Duty Power Factor Improvement Capacitors BANK Stud Mounting Cylindrical type, 440 volts, 50 Hz, 3 phase, delta connected of capacity 5 KVAR complete all as specified and directed.
All as per item No 222.00 above but of capacity 10 KVAR complete all as specified and directed.
All as per item No 222.00 above but of capacity 15 KVAR complete all as specified and directed.
All as per item No 222.00 above but of capacity 25 KVAR complete all as specified and directed.
S & F in replacement Power Contactor of rating 70 Amps AC3, 3 pole 415 V suitable for operating of time switch complete all as specified and directed.
S & F in replacement Power Contactor of rating 40 Amps AC3, 3 pole 415 V suitable for operating of time switch complete all as specified and directed.
S & F in replacement Power Contactor of rating 25 Amps 220 volts 3 pole suitable for operating of time switch complete all as specified and directed.
M & L for constructing PCC foundation (1x1x1 ft) for bollard light, fixing of bollard light on new PCC foundation by grouting nut bolt and making arrangement of conduit pipe 25 mm in PCC for passing of electric cable,connecting cable with lights complete all as specified and directed by Engr-In-Charge. Note:- 1.The quoted Rates also include necessary excavation and earth work . 2. The quoted rates also include taking down of bollard light from existing structure and fixing it on new PCC.
NEERU ELECTRICALS (BID ID -3099905)
SANJEEV ENTERPRISES (BID ID -3100458)
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .