| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.6 LAccepted-AOC 5 ESWARAN KOVIL STREET PSG NAGAR IN AVALPOONDURAI TOWN PANCHAYAT ERODE DISTRICT | ERODE | TAMIL NADU | 638001 | ₹1.6 L | L1 | Accepted-AOC Lowest Tender |
| 2 | L2₹2.4 L+₹76,462.90 (47.2%)Rejected-AOC | ₹2.4 L+₹76,462.90 (47.2%) | L2 | Rejected-AOC Highest Tender |
| 3 | L3₹2.0 L+₹41,316.03 (25.5%)Rejected-AOC | ₹2.0 L+₹41,316.03 (25.5%) | L3 | Rejected-AOC Highest Tender |
| 4 | L4₹2.4 L+₹76,189 (47.0%)Rejected-AOC | ₹2.4 L+₹76,189 (47.0%) | L4 | Rejected-AOC Highest Tender |
| 5 | L5₹2.1 L+₹43,750 (27.0%)Rejected-AOC | ₹2.1 L+₹43,750 (27.0%) | L5 | Rejected-AOC Highest Tender |
| Sl No | Description | Qty | Unit | KMR AND CO L5 | GS CONSTRUCTION L2 | GS TRADERS AND CIVIL CONSULTING L4 | A.NAGULAN CONTRACTOR L1 | AMMAN AND CO L3 |
|---|---|---|---|---|---|---|---|---|
| 1.00 | Dismantling Plain Cement Concrete For Damaged Cement Concrete Pavement and Damaged Strom Water Drain including all Charges. | 26 | M3 | 520 ₹13,520 | 443.49 ₹11,530.74 | 520 ₹13,520 | 354 ₹9,204 Lowest | 450 ₹11,700 |
| 2.00 | Earth Work Excavation for foundation in all types of soils and sub soils to full depth (such as Soils in Rock / Silt / Light Black Cotton Soil / Ordinary Soil ) except in rock requiring blasting but inclusive of shoring, shuttering and bailing out water wherever necessary and refilling the sides of foundation with excavated earth other than sand in layers of 150 mm thick well rammed and consolidated, depositing the surplus earth in places shown by the Departmental Officers with initial lead of 10 m and initial lift of 2 m. Complete as per TNSS 23 & 24, V, VI (S2), VII, 9,10 | 89 | M3 | 197.5 ₹17,577.5 | 168.65 ₹15,009.85 | 197 ₹17,533 | 134 ₹11,926 Lowest | 170 ₹15,130 |
| 3.00 | Supply and Dellivary of PVC pipe and GI pipe and Specials including cost of material and cost of conveyance etc. 90 mm PVC 6 kg/cm2 Pipe | 280 | Mt | 142.3 ₹39,844 | 121.31 ₹33,966.8 | 142 ₹39,760 | 96 ₹26,880 Lowest | 122 ₹34,160 |
| 4.00 | Loweing PVC rigid pipes and specials to trench and laying to proper gradient and alignment jointing with PVC couplers with cement paste and testing to the required pressure including conveyance of water for filling during testing etc., Complete complying with standard specification. 90 mm PVC 6 kg/cm2 Pipe | 280 | Mt | 22.2 ₹6,216 | 18.94 ₹5,303.2 | 22 ₹6,160 | 15 ₹4,200 Lowest | 19 ₹5,320 |
| 5.00 | Refilling with excavated excess earth work including all labour charges etc., complete complying with standard specification. | 89 | M3 | 45.8 ₹4,076.2 | 39.08 ₹3,478.12 | 45 ₹4,005 | 31 ₹2,759 Lowest | 39 ₹3,471 |
| 6.00 | Plain Cement Concrete of mix 1 : 4 : 8 (One part of Cement four part of sand eight part of aggregates) using 40mm gauge hard broken including cost conveyance of all materials to site including formwork and centering labour charges, transporting and placing in position including shoring, strutting, forming protective bunds, cofferdams bailing out of water labour for mixing compacting, finishing and curing, working at depths, tools and plants and incidental charges such as sheeting, shoring and bracing and their subsequent removal etc., complete as per standard specification. TNDSS NO: 28 V, VI (S2) V,VI (S5A) VII | 13 | M3 | 5,404.7 ₹70,261.1 | 4,607.51 ₹59,897.63 | 5,404 ₹70,252 | 3,680 ₹47,840 Lowest | 4,674 ₹60,762 |
| 7.00 | Plain Cement Concrete 1:2:4 (one cement, two sand and four hard broken stone jelly) using 20mm jelly for wearing coat including laying, compacting, finishing and curing, etc., complete as per standard specificatins and as directed by the departmental officers. | 13 | M3 | 6,695.7 ₹87,044.1 | 5,708.13 ₹74,205.69 | 6,695 ₹87,035 | 4,559 ₹59,267 Lowest | 5,791 ₹75,283 |
Tender Value
₹3 L
EMD Value
₹6,000
Closing Date
26 Feb 2026, 3:00 pmClosed
Executive Officer
Sivagiri Town Panchayat
General Fund 2025-2026 Erode District Sivagiritp Extension of Pipeline at Ward No.7 Ammankovil Cross Streets in Sivagiri Town Panchayat, Erode District
2026_DTP_665228_1
46/2026
Open Tender
Civil Works
Works
30 days
Sivagiri Town Panchayat
As per norms
2 documents required · 2 mandatory
₹0
₹6,000
10 Jul 2026
24 Feb 2026
27 Feb 2026
24 Feb 2026
26 Feb 2026
24 Feb 2026
24 Feb 2026 - 26 Feb 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Dismantling Plain Cement Concrete For Damaged Cement Concrete Pavement and Damaged Strom Water Drain including all Charges. | 26 | M3 | - | - |
| 2 | Earth Work Excavation for foundation in all types of soils and sub soils to full depth (such as Soils in Rock / Silt / Light Black Cotton Soil / Ordinary Soil ) except in rock requiring blasting but inclusive of shoring, shuttering and bailing out water wherever necessary and refilling the sides of foundation with excavated earth other than sand in layers of 150 mm thick well rammed and consolidated, depositing the surplus earth in places shown by the Departmental Officers with initial lead of 10 m and initial lift of 2 m. Complete as per TNSS 23 & 24, V, VI (S2), VII, 9,10 | 89 | M3 | - | - |
| 3 | Supply and Dellivary of PVC pipe and GI pipe and Specials including cost of material and cost of conveyance etc. 90 mm PVC 6 kg/cm2 Pipe | 280 | Mt | - | - |
| 4 | Loweing PVC rigid pipes and specials to trench and laying to proper gradient and alignment jointing with PVC couplers with cement paste and testing to the required pressure including conveyance of water for filling during testing etc., Complete complying with standard specification. 90 mm PVC 6 kg/cm2 Pipe | 280 | Mt | - | - |
| 5 | Refilling with excavated excess earth work including all labour charges etc., complete complying with standard specification. | 89 | M3 | - | - |
| 6 | Plain Cement Concrete of mix 1 : 4 : 8 (One part of Cement four part of sand eight part of aggregates) using 40mm gauge hard broken including cost conveyance of all materials to site including formwork and centering labour charges, transporting and placing in position including shoring, strutting, forming protective bunds, cofferdams bailing out of water labour for mixing compacting, finishing and curing, working at depths, tools and plants and incidental charges such as sheeting, shoring and bracing and their subsequent removal etc., complete as per standard specification. TNDSS NO: 28 V, VI (S2) V,VI (S5A) VII | 13 | M3 | - | - |
| 7 | Plain Cement Concrete 1:2:4 (one cement, two sand and four hard broken stone jelly) using 20mm jelly for wearing coat including laying, compacting, finishing and curing, etc., complete as per standard specificatins and as directed by the departmental officers. | 13 | M3 | - | - |
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.31 MB
BOQ_798950.xls
BOQ • 0.36 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .