| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹4.2 CrAccepted-AOC JHANSI | JHANSI | UTTAR PRADESH | 284001 | ₹4.2 Cr | L1 | Accepted-AOC Financial bid accepted |
| 2 | L2₹5.4 Cr+₹1.3 Cr (30.0%)Rejected-Finance KARNATAKA | RAICHUR | KARNATAKA | 584123 | ₹5.4 Cr+₹1.3 Cr (30.0%) | L2 | Rejected-Finance L2 |
| 3 | L3₹5.8 Cr+₹1.6 Cr (38.4%)Rejected-Finance VILLAGE DOLIPUR PASANA KARCHANA PRAYAGRAJ | PRAYAGRAJ | PRAYAGRAJ | UTTAR PRADESH | ₹5.8 Cr+₹1.6 Cr (38.4%) | L3 | Rejected-Finance L3 |
Tender Value
Refer Docs
EMD Value
₹12 L
Closing Date
7 Feb 2025, 12:00 pmClosed
S.E, Jhansi Circle, P.W.D., Jhansi
Office of the S.E, Jhansi Circle, P.W.D., Jhansi
Widening and strengthening work of Dimrauni Road (ODR).
2025_CEJNS_1000021_1
9056/44 C-jhs-cir/24, Date 10.12.2024
Open Tender
Civil Works - Roads
Item Rate
365 days
Jhansi
Please refer Tender documents.
3 documents required · 3 mandatory
₹6,250
₹12 L
Yes
Office of the S.E, Jhansi Circle, P.W.D., Jhansi
7 Mar 2025
30 Jan 2025
7 Feb 2025
30 Jan 2025
7 Feb 2025
30 Jan 2025
30 Jan 2025
Amount
Excavation for roadwork in soil with hydraulic excavator including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross sections, and transporting to the embankment location within all lifts and lead upto 1000m
Construction of embankment with approved materials deposited at site from roadway cutting and excavation from drain and foundation of other structures graded and compacted to meet requirment of table 300-2. As per Ref. to MoRTH Spec no-301+305.
Construction of embankment with approved materials deposited at site from roadway cutting and excavation from drain and foundation of other structures graded and compacted to meet requirement of table 300-2.
Construction of sub-grade and earthen shoulders with approved material obtained from borrow pits with all lifts & leads, transporting to site, spreading, grading to required slope and compacted to meet requirement of table No. 300-2 Earth carted up to 2 Km from site of work
Construction of granular sub-base by providing close graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with front end loader at OMC, and compacting with vibratory roller to achieve the desired density, complete as per clause 401
Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the Material with water at OMC in mechanical mix plant carriage of mixed Material by tipper to site, laying in uniform layers with paver in sub- base / base course on well prepared surface and compacting with vibratory roller to achieve the desired density.
Construction of dry lean concrete Sub-base over a prepared sub-grade with coarse and fine aggregate confirming to IS: 383 the size of coarse aggregate not exceeding 25 mm, aggregate cement ratio not to exceed 15:1 aggregate gradation after blending to be as as per table 600-1, optimum moisture content to be determined during trial length construction, concrete strength not to be less than 10 Mpa at 7 days, mixed in a batching plant, transported to site, laid over a paver with electronic sensor, compacting with 8-10 tonnes vibratory roller, finishing and curing.
Cement Concrete Pavement (Construction of M40 grade un-reinforced, dowel jointed at construction joint, plain cement concrete pavement over a prepared sub base with 43 grade cement, coarse and fine aggregate conforming to IS 383, maximum size of coarse aggregate not exceeding 25 mm, mixed in a batching and mixing plant as per approved mix design, transported to site, laid with a fixed form or slip form paver, spread, compacted and finished in a continuous operation including providing of construction joints, separation membrane (where DLC is done), admixtures, fibre mesh, curing compound, finishing to lines and grades as per drawing.The White topping without fibre mesh shall not be accepted.
Excavation in Foundation in ordinary soil (Loam clay, or sand) including lift upto 1.5 metre (5 fts.) and lead upto 30 m (100 fts) & including filling, watering and ramming of excavated earth into the trenches or into the space between the building and the sides of foundation trenches or into the plinth and removal and disposal of surplus earth as directed by the Engineer-in-charge upto a distance of 30 m. (100 fts) from the foundation trenches (S.I. No.251).
Sand filling in plinth including supply of necessary quantity of sand from a distance not exceeding 8 km.(5 miles) from the site of work and including watering, dressing etc. Rate to include cost of all materials, labour and T&P etc. required for proper completion of the work. (Rate is Including Royality) (S.I. No.255).
Cement concrete with 4 cm (1.5") gauge approved stone ballast, approved coarse sand and cement in the proportion of 6 : 3 : 1 including supply of all materials, labour and T & P etc. required for proper completion of the work. (S.I. No.280).
Random course rubble masonary in 1:4 cement and coarse sand mortar in foundation and plinth, including supply of material as order by the Engineer-in-charge, labour, T&P etc, required for proper completion of work (Ch.-8, Additional Item-2).
Providing and Laying Reinforced cement concrete pipe NP3/prestressed concrete pipe for culverts on first class bedding of granular material in single row including fixing collar with cement mortar 1:2 but excluding excavation, protection works, backfilling, concrete and masonry works in head walls and parapets. (350 mm dia).
Providing and Laying Reinforced cement concrete pipe NP4/prestressed concrete pipe for culverts on first class bedding of granular material in single row including fixing collar with cement mortar 1:2 but excluding excavation, protection works, backfilling, concrete and masonry works in head walls and parapets. (1000 mm dia).
Raised pointing with cement and Fine sand 1.25 F.M. mortar on brick work in proportion of 1 :2, including supply of all material, labour and T & P etc. required for proper completion of the work (S.I. No.577).
Cement concrete with 2 cm gauge approved stone ballast, approved coarse sand and cement in the proportion of 4 : 2 : 1 including supply of all materials, labour and T & P etc. required for proper completion of the work. (S.I. No.279 (New Item-a)).
R.C.C work with cement approved coarse sand and 2 cm. (3/4") gauge approved stone ballast in the proportion of 1:1.5:3 in lintels of doors and windows excluding supply of reinforcement and its binding but including its fixing and binding the same with 24 B.W.G.G.I binding wire and including necessary centering and shuttering etc. and also including supply of all materials, labour& T&P etc. required for proper completion of the work. Binding wire cost being included in the item. (S.I. No-283(i).
Mild steel or iron in plain work such as reinforced concrete or reinforced brick work (when not included in an over all rates) wrought to required shape as necessary including bending for proper completion of the work and including supply of all steel and wastage & overlapping & hooks. (S.I. No. 504)
Kilometer stone.
Hectometer.
The routine maintenance of above road work including embankment,patri,pavement, road sides and cross drains, hume pipe culvert etc to the required standards and in the manner as defined in CB Condition and keep the entire road surface and structure in Defect free condition during the entire maintenance period which begins from the actual Completion Date and ends after five years. (including cost of material T&P labour but excluding GST) for 1st year maintenance cost (0%)
The routine maintenance of above road work including embankment,patri,pavement, road sides and cross drains, hume pipe culvert etc to the required standards and in the manner as defined in CB Condition and keep the entire road surface and structure in Defect free condition during the entire maintenance period which begins from the actual Completion Date and ends after five years. (including cost of material T&P labour but excluding GST) for 2nd year maintenance cost (0.25% Construction Cost)
The routine maintenance of above road work including embankment,patri,pavement, road sides and cross drains, hume pipe culvert etc to the required standards and in the manner as defined in CB Condition and keep the entire road surface and structure in Defect free condition during the entire maintenance period which begins from the actual Completion Date and ends after five years. (including cost of material T&P labour but excluding GST) for 3rd year maintenance cost (0.50% Construction Cost)
The routine maintenance of above road work including embankment,patri,pavement, road sides and cross drains, hume pipe culvert etc to the required standards and in the manner as defined in CB Condition and keep the entire road surface and structure in Defect free condition during the entire maintenance period which begins from the actual Completion Date and ends after five years. (including cost of material T&P labour but excluding GST) for 4th year maintenance cost (0.75% Construction Cost)
The routine maintenance of above road work including embankment,patri,pavement, road sides and cross drains, hume pipe culvert etc to the required standards and in the manner as defined in CB Condition and keep the entire road surface and structure in Defect free condition during the entire maintenance period which begins from the actual Completion Date and ends after five years. (including cost of material T&P labour but excluding GST) for 5th year maintenance cost (1% Construction Cost)
SATYAM CONSTRUCTIONS (BID ID -4920569)
Ashish Enterprises (BID ID -4923303)
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .