| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.6 LAccepted-AOC | ₹1.6 L | L1 | Accepted-AOC LOW PRICE |
| 2 | L2₹1.6 L+₹150.19 (0.10%)Rejected-Finance | ₹1.6 L+₹150.19 (0.10%) | L2 | Rejected-Finance HIGH PRICE |
| Sl No | Description | Qty | Unit | Vengatesh L1 | Nisathkhan L2 |
|---|---|---|---|---|---|
| 1.00Strengthening to the road From ECR to Chellanendal Lakshmi Veedu in Keelamajakkudi Pancahayat | |||||
| 2.00 | Earth work excavation in all classes of soils except hard rock requiring blsating depositing on bank with initial lead of 10M and lift of 2M including all labour charges and incidental charges such as shorting,strutting,providing coffer dams,bailing out of water as per SS 20A | 18 | Cum | 140 ₹2,520 Lowest | 140.45 ₹2,528.1 |
| 3.00 | Picking old Wornout WBM Surface upto 10cm thick as directed the departmental officers | 50 | Sqm | 23 ₹1,150 Lowest | 23.36 ₹1,168 |
| 4.00 | Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) specification including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 250mm thick with pavers in SubBase/Base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete. | 22.5 | Cum | 2,813 ₹63,292.5 Lowest | 2,813.83 ₹63,311.18 |
| 5.00 | Providing and laying PRIME COAT over the WMM surface using 7.00 Kg of Bituminous Emulsion SS I for 10 sqm. Including cost of bituminous emulsion which will be supplied by the department at section stores and its cost will be recovered as per special condition appended including labour charges for preparing the surface for laying prime coat and for applying required quantity of bituminous emulsion by mechanical sprayer including hire and fuel charges for all tools and plants employed etc., complete as per clause 503 of MOST specification. | 150 | Sqm | 84 ₹12,600 Lowest | 84.12 ₹12,618 |
| 6.00 | Providing and laying TACK COAT over the WMM surface (treated with primer) using 2.50 Kg of Bituminous Emulsion RS I for 10 sqm. Including cost of bituminous emulsion which will be supplied by the department at section stores and its cost will be recovered as per special condition appended including labour charges for preparing the surface for laying tack coat and for applying required quantity of bituminous emulsion by mechanical sprayer including hire and fuel charges for all tools and plants employed etc., complete as per clause 503 of MOST specification. | 150 | Sqm | 18 ₹2,700 Lowest | 18.19 ₹2,728.5 |
| 7.00 | Providing and laying open graded premix carpet of 20mm compacted thick using 0.18cum of 13.20mm IRC size HBG machine crushed chips and 0.09 cum of 11.20mm IRC HBG machine crushed chips with 14.60Kg of bitumen for 10 Sqm. of premix carpet including laying of seal coat 'A' over the premix carpet using 0.09 cum of 6.70mm IRC size HBG machine crushed chips with 9.80Kg of bitumen per 10 Sqm. including cost and conveyance of chips and stacking them to departmental gauge for pre-measurements including cost of bitumen which will be supplied by the department at departmental section stores and its cost will be recovered as per special condition appended including heating the bitumen and metal mixing the materials in mini hot mix plant for premix carpet including spreading the same and finishing and compacting the same by power rolling to the specified lines and grades including all labour charges application of bitumen for seal coat over the premix carpet and spreading the seal coat and power roller rolling separately as per MOST specification 509 and 513 (III revision) including all labour charges hire and fuel charges for mini hot mix plant, power roller 80-100KN capacity and all other tools and plants employed therefor etc.com. | 150 | Sqm | 337 ₹50,550 Lowest | 337.24 ₹50,586 |
| 8.00 | GST Amount for providing Service to Government Contract Works for the above Construction & Maintenance Works. { GST Amount is the Total GST Amount for overall quoted amount (Both Construction and Maintenance) above this row in column "BB" for all works in this package}(Refer Clause 13.2 & 13.3 of Section 2 of Instruction to Bidders (ITB) of SBD) | 1 | nom | 23,906.25 ₹23,906.25 Lowest | 23,929.16 ₹23,929.16 |
Tender Value
₹1.6 L
EMD Value
₹1,620
Closing Date
2 Mar 2026, 3:00 pmClosed
BDO (B.PT)
PT UNION OFFICE
Strengthening to the road From ECR to Chellanendal Lakshmi Veedu in Keelamajakkudi Pancahayat
2026_RDTN_665768_1
Panchayat G.Fund-Work (02) in Keelamanjakudi Panchayat at Manamelkudi Block
Open Tender
Civil Works - Roads
Works
180 days
MANAMELKUDI
Please refer Tender documents.
4 documents required · 4 mandatory
₹0
₹1,620
Yes
20 Mar 2026
24 Feb 2026
2 Mar 2026
24 Feb 2026
2 Mar 2026
24 Feb 2026
Strengthening to the road From ECR to Chellanendal Lakshmi Veedu in Keelamajakkudi Pancahayat
Earth work excavation in all classes of soils except hard rock requiring blsating depositing on bank with initial lead of 10M and lift of 2M including all labour charges and incidental charges such as shorting,strutting,providing coffer dams,bailing out of water as per SS 20A
Picking old Wornout WBM Surface upto 10cm thick as directed the departmental officers
Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) specification including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 250mm thick with pavers in SubBase/Base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete.
Providing and laying PRIME COAT over the WMM surface using 7.00 Kg of Bituminous Emulsion SS I for 10 sqm. Including cost of bituminous emulsion which will be supplied by the department at section stores and its cost will be recovered as per special condition appended including labour charges for preparing the surface for laying prime coat and for applying required quantity of bituminous emulsion by mechanical sprayer including hire and fuel charges for all tools and plants employed etc., complete as per clause 503 of MOST specification.
Providing and laying TACK COAT over the WMM surface (treated with primer) using 2.50 Kg of Bituminous Emulsion RS I for 10 sqm. Including cost of bituminous emulsion which will be supplied by the department at section stores and its cost will be recovered as per special condition appended including labour charges for preparing the surface for laying tack coat and for applying required quantity of bituminous emulsion by mechanical sprayer including hire and fuel charges for all tools and plants employed etc., complete as per clause 503 of MOST specification.
Providing and laying open graded premix carpet of 20mm compacted thick using 0.18cum of 13.20mm IRC size HBG machine crushed chips and 0.09 cum of 11.20mm IRC HBG machine crushed chips with 14.60Kg of bitumen for 10 Sqm. of premix carpet including laying of seal coat 'A' over the premix carpet using 0.09 cum of 6.70mm IRC size HBG machine crushed chips with 9.80Kg of bitumen per 10 Sqm. including cost and conveyance of chips and stacking them to departmental gauge for pre-measurements including cost of bitumen which will be supplied by the department at departmental section stores and its cost will be recovered as per special condition appended including heating the bitumen and metal mixing the materials in mini hot mix plant for premix carpet including spreading the same and finishing and compacting the same by power rolling to the specified lines and grades including all labour charges application of bitumen for seal coat over the premix carpet and spreading the seal coat and power roller rolling separately as per MOST specification 509 and 513 (III revision) including all labour charges hire and fuel charges for mini hot mix plant, power roller 80-100KN capacity and all other tools and plants employed therefor etc.com.
GST Amount for providing Service to Government Contract Works for the above Construction & Maintenance Works. { GST Amount is the Total GST Amount for overall quoted amount (Both Construction and Maintenance) above this row in column "BB" for all works in this package}(Refer Clause 13.2 & 13.3 of Section 2 of Instruction to Bidders (ITB) of SBD)
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.30 MB
PRE_QUAL.pdf
Tender Documents • 0.48 MB
BOQ_799647.xls
BOQ • 0.23 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .