| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹38.5 LAccepted-AOC | ₹38.5 L | L1 | Accepted-AOC Qualified |
| 2 | L2₹40.2 LRejected-Finance | ₹40.2 L | L2 | Rejected-Finance 2nd Lowest |
| 3 | L3₹41.2 LRejected-Finance GADE LAYOUT LAKHALA WASHIM DIST WASHIM MAHARASHTRA | WASHIM | WASHIM | MAHARASHTRA | 444505 | ₹41.2 L | L3 | Rejected-Finance 3rd Lowest |
| 4 | Not Admitted-Fee/PreQual/Technical SARDAR NAGAR KHAWAT | - | - | Not Admitted-Fee/PreQual/Technical Others-Written refusal to open |
| 5 | Not Admitted-Fee/PreQual/Technical | - | - | Not Admitted-Fee/PreQual/Technical Not Complied with technical specification |
Tender Value
₹38.5 L
EMD Value
₹38,488
Closing Date
27 Dec 2025, 5:00 pmClosed
Add CEO Z P Washim
Zilla Parishad Washim
Improvement, Strengthning and Upgradation to Asola khu to Gavha Road VR 221 KM 0/00 to 3/850 Tq- Manora, Dist-Washim. Dist. Washim
2025_WASHI_1261564_33
ZPWASHIM/WORKS/Tender NIT No.7/2025-2026/1stcall
Open Tender
Civil Works
30 days
Washim
Please refer Tender documents.
8 documents required · 8 mandatory
₹1,180
₹38,488
Works Division z p Washim
10 Apr 2026
20 Dec 2025
29 Dec 2025
20 Dec 2025
27 Dec 2025
20 Dec 2025
24 Dec 2025
Improvement, Strengthning and Upgradation to Asola khu to Gavha Road VR 221 KM 0/00 to 3/850 Tq- Manora, Dist-Washim. Dist. Washim
Clearing and grubbing road land including uprooting rank vegetation, grass, bushes, shrubs, saplings and trees girth up to 300 mm, removal of stumps of trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned up to a lead of 1000 metres including removal and disposal of top organic soil not exceeding 150 mm in thickness. (SSR 2022-23I.N.2.09 Page No.73)
Excavation for catch / side water gutter in all sorts of soils to the specified section including stacking the excavated stuff in a regular bund and disposing of unsuitable or excess stuff as directed all sorts of soils.(SSR 2022-23 item No.2.18 Page No.11)
Supplying trap /granite /quartzite / gneiss stone metal of required size by bringing the boulders at the road side breaking them to required gradation including conveying the boulders and stacking the broken metal etc.complete. (Prior approval of sample stack of broken metal by the Ex.Engineer is necessary, the date of approval will form part of the measurements) (For Diversion only)I. 80 mm metal SSR 2022-23I.N.50.56)
Supplying hard murum/ kankar at the road site, including conveying and stacking complete.(SSR 2022-23 item No.2.29a Page No.12) KM1
Spreading 80/40 mm metal for road work including sectionong etc complete as directed by Engineer in charge .(SSR 2022-23 I.N50.58)
Spreading gravel / sand / soft murum /avilable murum over rubble soling /W.B.M.surface blanketing berms etc.complete. (SSR 2022-23 I.N.2.30 )
Watering and compacting of embankment formed of materials obtained from the road cutting with in a lead of50m,notlessthan97%ofstandardProctordensityafterlayingthem in layers of 20 cm. to 30 cm. with Power roller. SSR 2022-23 IT No. 2.24
Excavation for foundation in earth, soils of all types, sand, gravel, soft murum including shoring and strutting as necessary and disposing off excavated stuff as directed etc. complete. By mechanical means (SSR 2022-23 item No.12.03 Page No.73)
Excavation for foundation in hard murum including shoring and strutting as necessary and disposing off excavated stuff as directed etc.complete.(SSR 2022-23 item No.12.04 Page No.73)
Providing and laying in situ / ready mix / ready mix M10 cement concrete of trap/ granite/ quartzite/ gneiss metal in foundation including necessary centering, formwork, bailing out water, compacting and curing etc. complete. (with fully automatic micro processor based PLC with SCADA enabled with reversible drum type mixer/ concrete batch mix plant (pan mixer) with natural /artifical sand)(SSR 2022-2312.25Page No.137)
Providing and laying in situ / ready mix M-20 plain cement concrete of trap /granite/quartzite/ gneiss metal for cast in citu piers, abutment, returns, wings etc. including provision of "V" shaped false joints to form suitable panels on the faces to approve design with compacting by vibrating and curing complete, including plywood/steel form work centering ( excluding dewatering by means of pump) and including bailling out water and curing finishing in CM 1:3 etc. complete. as directed by engineer in charge basic rate shall be increased for height above 5.00 m in followinh manners (a) Height upto 5 M. (With Concrete Mixer)With fine agreegates(SSR 2022-23 I.N.17.39/108)
Providing and laying cement concrete pipe of IS 458:2003 NP-2 class of 1000mm diameter in proper line, level and slope including providing and fixing collars in cement mortar 1:2 and curing etc. complete.(SSR 2022-23 I.N.11.12 /81)
stage.html
html • 0.05 MB
techsummary_2174394.pdf
BOQ Comparative Chart
xlsx
finsummary_2174394.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.72 MB
BOQ_2174394.xls
BOQ • 0.32 MB