| 1 | L1₹1.1 CrAccepted-AOC EAST CROSS STREET AT 67 M LENGTH IN VEERAGANU VEERAGANUR TOWN PANCHAYAT SALEM DISTRICT | ₹1.1 Cr | L1 | Accepted-AOC L1 |
| 2 | L2₹1.1 Cr+₹2.5 L (2.32%)Rejected-AOC 53 19 BRINDABON MULLICK LANE KADAMTALA HOWRAH WEST BENGAL 711101 | HOWRAH | WEST BENGAL | 711101 | ₹1.1 Cr+₹2.5 L (2.32%) | L2 | Rejected-AOC L2 |
Tender Value
₹1.1 Cr
EMD Value
₹1.1 L
Closing Date
31 Jan 2025, 3:00 pmClosed
Additional Collector (Development)
DRDA, Salem
Salem District - Gangavalli Block - Strengthening the Road from Goodamalai Vadakku Mariyamman Koil To Eri Kodivaikkal Varai - Gudamalai Panchayat in NABARD -RIDF-XXX -2024-2025 Package No.25
2024_RDTN_514663_9
Roc.No.9140/2023/A4
Open Tender
Civil Works - Roads
Item Wise
180 days
DRDA
As per tender Document
3 documents required · 3 mandatory
₹0
₹1.1 L
DRDA, Salem
21 Mar 2025
30 Dec 2024
31 Jan 2025
30 Dec 2024
31 Jan 2025
30 Dec 2024
2 Jan 2025
Amount
Strengthening of BT road from Goodamalai Vadakku Mariyamman Koil to eri Kodivaikkal varai road KM 0/0-1/400 (VPR-333)
Picking 5 cm to 10 cm old metalled surface and sectioning - 1 sq.m
Clearing the Scrub jungle by uprooting including all cutting charges and disposing of the products and clearing as directed by the departmental officers including all incidental charges etc., complete.
Earth work excavation in all classes of soils except hard rock requiring blasting depositing on bank with initial lead of 10M and lift of 2M including all labour charges and incidental charges such as shoring, strutting, providing coffer dams, bailing out of water as per 20A
Providing and laying including cost and conveyance of gravel from approved sources to work site including labour for spreading, watering and compacting by power roller to achieve the required Proctor density at 100% compaction at Optimum moisture content
Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) specification including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 250mm thick with pavers in SubBase/Base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete.
Providing and laying of prime coat using Emulsion at the rate of 7 Kg per ten square meter over the WMM surface preparatory to another bituminous construction over it.
Providing and laying Tack coat over WMM surface(treated with primer) using 2.5Kg of bitumen emulsion RS-1 for 10sqm for preparatory to another bituminous construction over it including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc.,
BITUMINOUS CONCRETE 25, 30/40 MM THICK USING cmp (Grade-II) Providing and laying Bituminious concrete to 40mm thick using 0.13cum of 19.00-9.50mm. 0.17cum of 9.5-2.36 and below with 50.3kgs of VG30/VG40 heating the bitumen and aggregates to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, carrying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonnes vibratory/phenumatic roller to the required density etc., including labour for attending to paver to site etc.including hire charges and fuel charges foe 20-30t CMP with bitumen boiler, tipper trucks,paver finisher/9m paver finisher,vibratory/phenumatic roller and all other tools and plants required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clauses 507 of MORTH Part-5
Road Marking with Hot Applied Thermoplastic Compound with Reflectorising Glass Beads on Bituminous Surface. Providing and laying of hot applied Thermoplastic compound 2.5 mm thick including reflectorising glass beads @ 250 gms per sqm area,
Provision for Hecta Metre Stone - Nos
Provision for KM Stone- Nos
Provision for Sign Board
Provision for Name Board including erection charges and painting
Provision for SubEstimate Drain CH 100-500
Earth work Excavation in all soils and Sub Soil to full depth as may be directed except in hard rock requiring blasting but inclusive of shoring strutting, Sectioning the street to lay Foundation per SS 20B.
Cement concrete 1:4:8 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete for 10 cum.
Supplying and erecting centering shuttering including necessary supports for plane surface in foundation and basement and in all floors for R C C column footing column plinth beam, beams, roof slabs, staircase steps, bed blocks, critical pier etc...,
Cement concrete 1:3:6 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete for 10 cum.
Plastering with cement mortar 1:5 mix to 12mm thick including cost and conveyance of all materials to site including all labour charges for filling etc.complete,
RCC SLAB Culvert 1.5m Span AT CH90M
Earth work Excavation in all soils and Sub Soil to full depth as may be directed except in hard rock requiring blasting but inclusive of shoring strutting, Sectioning the street to lay Foundation per SS 20B.
Cement concrete 1:4:8 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete for 10 cum.
Cement concrete 1:3:6 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete for 10 cum.
Cement concrete 1:2:4mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete for 10 cum.
Reinforced Cement concrete 1:1.5:3 mix using 20mm I SS size hard granite broken metal from approved quarry including cost and conveyance of all materials to site including cost of cement which will be supplied departmentally at the Departmental section etc..completed
Supplying and erecting centering shuttering including necessary supports for plane surface in foundation and basement and in all floors for R C C column footing column plinth beam, beams, roof slabs, staircase steps, bed blocks, critical pier etc...,
Below GL
Deckslab
Supplying and fabricating and placing inposition mild steel or Ribbed Tor Steel for all reinforced cement concrte works as per the design given incuding cost of steel and binding wire in all floor etc. complete complying with standard specification (MS ro
Collection and supply of gritty gravel from appd quarry including cost and conveyance of all materials to site including all labour charges for filling etc.complete,.
RCC SLAB Culvert 1.5m Span AT CH430
Earth work Excavation in all soils and Sub Soil to full depth as may be directed except in hard rock requiring blasting but inclusive of shoring strutting, Sectioning the street to lay Foundation per SS 20B.
Cement concrete 1:4:8 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete for 10 cum.
Cement concrete 1:3:6 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete for 10 cum.
Cement concrete 1:2:4mix using 20mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete for 10 cum.
Reinforced Cement concrete 1:1.5:3 mix using 20mm I SS size hard granite broken metal from approved quarry including cost and conveyance of all materials to site including cost of cement which will be supplied departmentally at the Departmental section etc..completed
Supplying and erecting centering shuttering including necessary supports for plane surface in foundation and basement and in all floors for R C C column footing column plinth beam, beams, roof slabs, staircase steps, bed blocks, critical pier etc...,
Below GL
Deckslab
Supplying and fabricating and placing inposition mild steel or Ribbed Tor Steel for all reinforced cement concrte works as per the design given incuding cost of steel and binding wire in all floor etc. complete complying with standard specification (MS ro
Collection and supply of gritty gravel from appd quarry including cost and conveyance of all materials to site including all labour charges for filling etc.complete,.
Retainingwall AT CH 1010-1130 M
Earth work Excavation in all soils and Sub Soil to full depth as may be directed except in hard rock requiring blasting but inclusive of shoring strutting, Sectioning the street to lay Foundation per SS 20B.
Cement concrete 1:4:8 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete for 10 cum.
Supplying and erecting centering shuttering including necessary supports for plane surface in foundation and basement and in all floors for R C C column footing column plinth beam, beams, roof slabs, staircase steps, bed blocks, critical pier etc...,
Cement concrete 1:3:6 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete for 10 cum.
Collection and supply of gritty gravel from appd quarry including cost and conveyance of all materials to site including all labour charges for filling etc.complete,
Towards the charges for routline maintenance of the road work executed under NABARD including dressing of berms by refilling the gully with the earth from borrow pits, cleaning of wild seasonal growth on berms, destilting of side drains and CD works, white washing guard stones, painting of KM, HM stones, parapets, cutting of branches of trees, refixing displaced guard stones, caution boards, speed limit boards etc., with the periodicity for the above activities as prescribed in IRC-SP-20:2002 and as directed by the departmental officers except for the constructional defects which has to be rectified by the contractor at his own cost for carriageway width of 3.00m & 3.75m
For the First Year from the date of completion of work
For the Second Year from the date of cpmpletion of work
For the Third Year from the date of completion of work
For the Fourth Year from the date of completion of work
For the Fifth Year from the date of completion of work
GST Amount for providing Service to Government Contract Works for the above Construction & Maintenance Works. { GST Amount is the Total GST Amount for overall quoted amount (Both Construction and Maintenance) above this row in column "BB" for all works in this package} (Refer Clause 13.2 & 13.3 of Section 2 of Instruction to Bidders (ITB) of SBD)
PHOENIX & CO (BID ID -1225738)
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .