Tender Value
₹2.6 Cr
EMD Value
₹5.2 L
Closing Date
14 Sept 2026, 3:00 pm
No
No
Single Packet System
Normal Tender
No
Not Applicable
Lowest to Highest
60 days
Expenditure
Capital (Works)
LUCKNOW
13 conditions · 2 needing a document upload
The tenderer must have minimum average annual contractual turnover of V/N or 'V' whichever is less; where V= Advertised value of the tender in crores of Rupees N= Number of years prescribed for completion of work for which bids have been invited. The average annual contractual turnover shall be calculated as an average of "total contractual payments" in the previous three financial years, as per the audited balance sheet. However, in case balance sheet of the previous year is yet to be prepared/ audited, the audited balance sheet of the fourth previous year shall be considered for calculating average annual contractual turnover. The tenderers shall submit requisite information as per Annexure-VIIB, along with copies of Audited Balance Sheets dulycertified by the Chartered Accountant/ Certificate from Chartered Accountant duly supported by Audited Balance Sheet.
The Tenderer must have successfully completed or substantially completed any one of the following categories of work(s) during last 07 (seven) years, ending last day of month previous to the one in which tender is invited: Three similar works each costing not less than the amount equal to 30% of advertised value of the tender, or Two similar works each costing not less than the amount equal to 40% of advertised value of the tender, or One similar work each costing not less than the amount equal to 60% of advertised value of the tender. Similar nature for this work is "CTR/TRR/TFR/TTR including raising of track, screening, distressing of track, pre & post works for track maintenance machine like tamping machines/ ballast screening/regulating machines & TTR by T- 28". is for technical experience/competence of advertised work in terms of Pr. Chief Engineer Circular No. 610 (Revised-3). As per the HQ/NDLS letter No. 74-W/0/Pt.XXV/Similar Nature of Works/WA dated 22-01-2020 (S. No. 5(c)).
16 conditions · 8 needing a document upload
Please enter the percentage of local content in the material being offered. Please enter 0 for fully imported items, and 100 for fully indigenous items. The definition and calculation of local content shall be in accordance with the Make in India policy as incorporated in the tender conditions.
I/ We have visited the works site and I / We am / are aware of the site conditions.
Yard Improvement & Layout Correction in LKO Yard in the section of SSE/P- Way/LKO-I under ADEN/LKO-I in the jurisdiction of Sr.DEN-I/LKO.
31-Sr-DEN-I-LKO-2026-27~NR
31-Sr-DEN-I-LKO-2026-27
Open
Works - General
6 Months
Lucknow, Uttar Pradesh
₹0
₹5.2 L
19 Aug 2026
19 Aug 2026
31 Aug 2026
93 items across 9 schedules · ₹1,93,84,777.4 total
| # | Description | Unit | Qty | Rate | Amount |
|---|---|---|---|---|---|
| 1 | Up to 40 m long rail panel | RM | 3000.00 | 10.51 | 31,530 |
| 2 | For Through Rail Renewal work | TRM | 500.00 | 51.55 | 25,775 |
| 3 | For Casual/Scattered Rail Renewal work | RM | 2000.00 | 40.73 | 81,460 |
| 4 | For Through Rail Renewal work | TRM | 500.00 | 53.16 | 26,580 |
| 5 | For Casual/Scattered Rail Renewal work | RM | 2000.00 | 43.13 | 86,260 |
| 6 | For PSC wider base sleepers - For location of work not involving deep screening | Each | 1000.00 | 411.39 | 4,11,390 |
| 7 | For location work not involving deep screening | TRM | 1000.00 | 190.74 | 1,90,740 |
| 8 | Locations other than Ballasted Deck Bridge | Each | 100.00 | 544.17 | 54,417 |
| 9 | Fish plates of 6 bolts. | Joint | 2000.00 | 299.22 | 5,98,440 |
| 10 | Through renewal of Metal / GFN liners in running track condition after cleaning of rail foot at liner seat, greasing of liner, liner seat and sealing of liner contact area at rail foot including removing, cleaning & lubrication of ER Clip & Insert Eye and re-driving the same with contractor's grease graphite of approved quality with all lead & lift. | Sleeper | 10000.00 | 19 | 1,90,000 |
| 11 | Through Fitting Renewal (TFR) on PSC track, comprising of renewal of Grooved Rubber Pads, Liners and ERCs without damaging PSC sleepers. Scope includes removal of all fittings, cleaning of rail seat, rail flange at liner seats, and eye of Inserts with wire brushes and applying Grease Graphite Grade "O" (IS:408) to eye of insert and central leg of ERC with contractor's grease of Railway's specification, fixing all fittings in correct position and sealing liner edges with grease all complete including collection and stacking of released materials at nominated locations within SSE Jurisdiction as directed by Engineer-in-Charge. Note: All the fittings will be supplied at SSE/Stores/Depot. | Sleeper | 10000.00 | 27.16 | 2,71,600 |
| 12 | Through replacement of Grooved Rubber Sole pads(GRSP) on PSC sleepers duly removing the ERCs and liners and replacing the GRSP by just lifting the rail after cleaning the rail seat, refixing the liner and ERC after greasing of ERCs, liners and Liner contact area including sealing with Contractor's Grease Graphite Grade 'O' (IS:408) duly cleaning of rust/scale of ERC, Metal /GFN liners & SGCI insert by using wire brush, scrapper/sand emery paper etc., with all contractor's labour, tools, plants including collection and stacking of released materials at nominated locations within SSE Jurisdiction and as directed by Engineer-in- Charge. Note: GRSP will be supplied at SSE/stores/depot. | Sleeper | 20000.00 | 24.29 | 4,85,800 |
| 13 | Lubrication of ERCs and its liner contact area by removal of ERCs and Metal / GFN liners in rail panel, cleaning of rust / scale of ERC, Metal / GFN liners & SGCI insert by using wire brush, scrapper / sand emery paper etc supply and application of graphite grease, as prescribed by Railway for under side of liners & corresponding area of rail foot & SGCI insert with ERCs and re-fixing the same as per procedure prescribed in latest edition of IRPWM with contractors grease and all other tools & plants complete and as directed. Note: Each ERC in this item shall constitute 1 ERC and its Liner Contact area. | ERC | 100000.00 | 4.55 | 4,55,000 |
| 14 | Removing seized ERC from SGCI inserts of existing track by using suitable approved chemicals and re-fixing after greasing of insert eye and ERC with Contractor's grease of specified quality as per provisions of IRPWM, as directed by Engineer in-charge. Note: 1.List of Seized ERC along with location shall be prepared after inspection of SSE/P.Way and marked prior to execution of this item. 2. Due care shall be taken to avoid any damage to the sleeper 3.A penalty of 50% of the basic cost of new sleeper in nearest sleeper factory shall be levied on each, if SGCI insert is broken or sleeper gets cracked in the process. | ERC | 1000.00 | 57.7 | 57,700 |
| 15 | Lubrication of gauge face of rail on curves, cross overs, points & crossings, turn-in curves and at locations as required with contractor's grease graphite grade "O" IS 408 and as directed. | RM | 1000.00 | 3.77 | 3,770 |
| 16 | By using Contractor's Grease Graphite | Each | 500.00 | 37.95 | 18,975 |
| 17 | GRSP | Each | 1000.00 | 23.91 | 23,910 |
| 18 | ERCs | Each | 2000.00 | 7.98 | 15,960 |
| 19 | Metal/GFN Liners | Each | 2000.00 | 5.32 | 10,640 |
| 20 | Renewal of seized Plate/Rail screws on PSC Sleepers by using gas or any approved methods, duly drilling holes in broken screw and removing existing screw pieces from the holes along with existing dowels and fixing new contractor's dowels (procured from RDSO approved sources) and grouting around dowel with Epoxy materials of approved specification and refixing new Railway's rail/Plate screws duly greasing the screw with specified grease with all contractor's materials, consumables, tools & plants, labour with all lead, lift. Note: 1.Seized screws shall be identified and marked by JE/P.Way and verified at minimum SSE/P.Way In charge) level. 2. Due care shall be taken to avoid any damage to the sleeper 3.A penalty of 50% of the basic cost of new sleeper in nearest sleeper factory shall be levied on each, if sleeper gets damaged in the process. | Each | 2000.00 | 158.79 | 3,17,580 |
| 21 | Hole of dia. 26.5mm and above | Each | 100.00 | 259.11 | 25,911 |
| 22 | Renewal of existing SEJ with improved SEJ with PSC sleepers under traffic block conditions as per approved drawing including fixing of special size bearing plate, rubber pad and other sleeper / rail fittings, greasing to the fittings, leading rails, sleepers & fittings to site, leading and stacking of released materials within a lead of 250m, cutting of Rails, drilling of holes, fixing of related fittings, providing temporary connection with fishplates till welding of SEJ is done and sleepers shall be given initial packing to make track fit for 20KMPH speed. Note: (1) Rail cutting and hole drilling shall be paid separately. (2) One set comprise complete SEJ on both rails at SEJ. | Set | 10.00 | 9,657.84 | 96,578.4 |
| Schedule total | ₹34,80,016.4 | ||||
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
HTML
nit.pdf
NIT
TenderDocumentLKOYard.pdf Tender Document
ATTACHMENT
TenderDocumentLKOYard.pdf
ATTACHMENT
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].