Loading…
Loading…
| # | Company | Status |
|---|---|---|
| 1 | Admitted-Finance | Admitted-Finance |
| 2 | Admitted-Finance | Admitted-Finance |
Tender Value
₹3.8 L
EMD Value
₹7,570
Closing Date
28 Jun 2024, 6:00 pmClosed
Executive Engineer Civil Tender KTK Circle
Room No 324 3rd Floor Office of CGMT Doorasamparka Bhavan No 1 Swamy Vivekananda Road Bengaluru 560008
Reconstruction of collapsed portion of compound wall at Administrative Building Davangere
2024_BSNL_198764_1
12NITBSNLCDHBL202425
Open Tender
Civil Works - Buildings
Item Rate
30 days
DAVANGERE
Please refer Tender documents.
2 documents required · 2 mandatory
₹590
The Accounts officer Cash BSNL HUBBALLI
₹7,570
2 Jul 2024
19 Jun 2024
1 Jul 2024
20 Jun 2024
28 Jun 2024
20 Jun 2024
20 Jun 2024 - 27 Jun 2024
Amount
Demolishing brick work manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge.
Cement Mortar
Dismantling steel work in single sections including dismembering and stacking within 50 metres lead in:
Channels, angles, tees and flats
Credit for old barbed wire, M.S. angle, including removing the wire from posts/MS angle etc., and disposal from site and as per direction of Engineer - in - charge.
Demolishing stone rubble masonry manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge :
In cement mortar
Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift upto 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m.
All kinds of soil
Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level :
1:4:8 (1 Cement : 4 coarse sand (zone-III) derived from natural sources : 8 graded stone aggregate 40 mm nominal size derived from natural sources)
Random rubble masonry with Available stone in foundation and plinth including levelling up with cement concrete 1:6:12 (1 cement : 6 coarse sand : 12 graded stone aggregate 20mm nominal size) upto plinth level with :
Cement mortar 1:6 (1 cement : 6 coarse sand).
Random rubble masonry with hard stone in foundation and plinth including levelling up with cement concrete 1:6:12 (1 cement : 6 coarse sand : 12 graded stone aggregate 20mm nominal size) upto plinth level with :
Cement mortar 1:6 (1 cement : 6 coarse sand).
Brick work with common burnt clay F.P.S. (non modular) bricks of class designation 3.5 in foundation and plinth in:
Cement mortar 1:6 (1 cement : 6 coarse sand)
Brick work with common burnt clay F.P.S. (non modular) bricks of class designation 3.5 in superstructure above plinth level up to floor V level in all shapes and sizes in :
Cement mortar 1:6 (1 cement : 6 coarse sand)
Providing and laying cement concrete in retaining walls, return walls, walls (any thickness) including attached pilasters, columns, piers, abutments, pillars, posts, struts, buttresses, string or lacing courses, parapets, coping, bed blocks, anchor blocks, plain window sills, fillets, sunken floor, etc., up to floor five level, excluding the cost of centering, shuttering and finishing
1:2:4 (1 Cement : 2 coarse sand (zone-III) derived from natural sources : 4 graded stone aggregate 20 mm nominal size derived from natural sources)
Centering and shuttering including strutting, propping etc. and removal of form work for :
Retaining walls, return walls, walls (any thickness) including attached pilasters, buttresses, plinth and string courses fillets, kerbs and steps etc..
Structural steel work in single section, fixed with or without connecting plate,including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer all complete
Fencing with angle iron post placed at required distance embedded in cement concrete blocks, every 15th post, last but one end post and corner post shall be strutted on both sides and end post on one side only and provided with horizontal lines and two diagonals interwoven with horizontal wires, of barbed wire weighing 9.38 kg per 100 m (minimum), between the two posts fitted and fixed with G.I. staples, turn buckles etc. complete. (Cost of posts, struts, earth work and concrete work to be paid for separately). Payment to be made per metre cost of total length of barbed wire used.
With G.I. barbed wire
15 mm cement plaster on the rough side of single or half brick wall of mix : 1:4 (1 cement: 4 fine sand)
6 mm cement plaster of mix :
1:3 (1 cement : 3 fine sand)
Pointing on stone work with cement mortar 1:3 (1 cement: 3 fine sand) :
Flush/ Ruled pointing
Finishing walls with water proofing cement paint of required shade :
New work (Two or more coats applied @ 3.84 kg/10 sqm)
Painting with synthetic enamel paint of approved brand and manufacture to give an even shade :
Two or more coats on new work
Cutting branches of trees alongside the compound wall including necessary ropes, cutting tools, ladder etc. and clearing the site etc. complete as per the direction of Engineer in charge.
Beyond 30 cm girth upto and including 60 cm girth
Cutting the roots of trees abuting the compound wall carefully without causing the damage to adjuscent building or tree including necessary excavation, refilling after cutting the root etc as per the direction of Engineer in charge.
Disposal of building rubbish / malba / similar unserviceable, dismantled or waste materials by mechanical means, including loading, transporting, unloading to approved municipal dumping ground or as approved by Engineer-in-charge, beyond 50 m initial lead, for all leads including all lifts involved.
S ESWARAPPA AND CO
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .