| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹3.9 LAccepted-AOC | ₹3.9 L | L1 | Accepted-AOC L1 |
| 2 | L2₹3.9 LRejected-Finance | ₹3.9 L | L2 | Rejected-Finance L2 |
| Sl No | Description | Qty | Unit | C PONNUCHAMY L1 | S. ANANDABABU L2 |
|---|---|---|---|---|---|
| 1.00Construction of Compound wall at Sangampatti PUE School in Maravamadurai Panchayat | |||||
| 2.00 | Earth work excavation and depositing on sides with initial lead and lift in hard graually soil as per SS 20B for foundation. | 18.36 | Cum | 263 ₹4,828.68 | 265 ₹4,865.40 |
| 3.00 | Filling with M.Sand including cost and conveyance of sand to work site including all labour charges for filling etc complete. | 2.71 | Cum | 1,950 ₹5,284.50 | 1,955 ₹5,298.05 |
| 4.00 | Cement Concrete 1:48 mix using 40mm ISS HBG metal including all cost and conveyance and all labour charges and all other incidental charges etc., completed. | 3.44 | Cum | 5,603 ₹19,274.32 | 5,605 ₹19,281.20 |
| 5.00 | Centering for the sides and soffits RCC items including all cost and conveyance and all labour charges etc., complete. | 55.48 | Cum | 547.5 ₹30,375.30 | 550 ₹30,514 |
| 6.00 | Supplying and fabrication of steel rods including all cost and conveyance and all labour charges and all other incidental charges. | 0.65 | Mt | 91,963 ₹59,775.95 | 91,965 ₹59,777.25 |
| 7.00 | R.C.C 1:11/2:3 mix using 20mm ISS HBG metal including cost and conveyance and all labour charges etc.complete. | 7.56 | Cum | 9,242 ₹69,869.52 | 9,245 ₹69,892.20 |
| 8.00 | Brick work in cement mortar 1:5 (one cement and five sand) using country bricks ground moulded of size 23 x 11 x 7 cm. For the following including curing etc. complete complying with standard specification. For super structure in Ground floor. | 8.46 | Cum | 6,165.5 ₹52,147.80 | 6,165 ₹52,143.57 |
| 9.00 | Plastering with cement mortor 1:5 mix 12mm thick including cost of conveyance of all materials to work site and all labour charges etc. complete. | 140.18 | Sqm | 285.5 ₹40,019.96 | 290 ₹40,650.75 |
| 10.00 | Emulsion Painting the two coats with one coat of primer including cost and conveyance of all materials to work site and all labour charges etc., complete. | 140.18 | Sqm | 262.5 ₹36,795.94 | 270 ₹37,847.25 |
Tender Value
₹3.9 L
EMD Value
₹3,930
Closing Date
23 Jan 2026, 3:00 pmClosed
Block Development Officer(BP)
Panchayat Union Office, Ponnamaravathy
Construction of Compound wall at Sangampatti PUE School in Maravamadurai Panchayatt
2026_RDTN_643867_1
PNR/PUGF/Maravamadurai_01
Open Tender
Civil Works
Ponnamaravathy
Please refer Tender documents.
4 documents required · 4 mandatory
₹0
₹3,930
4 Mar 2026
14 Jan 2026
23 Jan 2026
14 Jan 2026
23 Jan 2026
14 Jan 2026
Construction of Compound wall at Sangampatti PUE School in Maravamadurai Panchayat
Earth work excavation and depositing on sides with initial lead and lift in hard graually soil as per SS 20B for foundation.
Filling with M.Sand including cost and conveyance of sand to work site including all labour charges for filling etc complete.
Cement Concrete 1:48 mix using 40mm ISS HBG metal including all cost and conveyance and all labour charges and all other incidental charges etc., completed.
Centering for the sides and soffits RCC items including all cost and conveyance and all labour charges etc., complete.
Supplying and fabrication of steel rods including all cost and conveyance and all labour charges and all other incidental charges.
R.C.C 1:11/2:3 mix using 20mm ISS HBG metal including cost and conveyance and all labour charges etc.complete.
Brick work in cement mortar 1:5 (one cement and five sand) using country bricks ground moulded of size 23 x 11 x 7 cm. For the following including curing etc. complete complying with standard specification. For super structure in Ground floor.
Plastering with cement mortor 1:5 mix 12mm thick including cost of conveyance of all materials to work site and all labour charges etc. complete.
Emulsion Painting the two coats with one coat of primer including cost and conveyance of all materials to work site and all labour charges etc., complete.
Provision for Grill Gate Arrangements
GST Amount for providing Service to Government Contract Works for the above Construction & Maintenance Works. { GST Amount is the Total GST Amount for overall quoted amount (Both Construction and Maintenance) above this row in column "BB" for all works in this package} (Refer Clause 1 & 12 of Section 2 of Instruction to Bidders (ITB) of SBD)
Please Enable Macros to View BoQ information
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.35 MB
TeckPNR01.pdf
Tender Documents • 0.17 MB
BOQ_771514.xls
BOQ • 0.29 MB
Download all tender documents and submit your bid