Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹3.3 LAccepted-AOC | L1 | Accepted-AOC L1 | |
| 2 | L2₹3.4 L+₹8,016.30 (2.41%)Rejected-AOC | L2 | Rejected-AOC L2 | |
| 3 | L3₹4.0 L+₹65,171.52 (19.6%)Rejected-AOC | L3 | Rejected-AOC L3 |
Tender Value
₹4.9 L
EMD Value
₹10,000
Closing Date
4 Jul 2022, 5:00 pmClosed
Executive Engineer
Executive Engineer, Provincial Division, PWD BandR Br., Palwal
Restoration of Road D.M. road to Tikri Brahman ID 3417 RD 0.00 to 450 Mtr. damaged by Public Health for lying of Water Supply Pipe line in Palwal Distt.
2022_HRY_227601_1
PWD/Palwal/98990/2
Open Tender
Civil Works - Roads
Works
120 days
Palwal
As per DNIT
2 documents required · 2 mandatory
₹500
₹10,000
Yes
Palwal
2 Aug 2022
28 Jun 2022
5 Jul 2022
28 Jun 2022
4 Jul 2022
28 Jun 2022
28 Jun 2022 - 4 Jul 2022
1 Jul 2022
Amount
Civil Works
Demolishing cement concrete manually/ by mechanical means including disposal of material with all lead and lift as per direction of Engineer - in - charge. Nominal concrete 1:2:4 or leaner mix (i/c equivalent design mix) (Based on HSR 5.23.2)
Excavation for roadwork in soil by mechanical means including cutting and loading in tippers, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross sections, and disposal within all lead and lift as per technical clause 301 of MORT&H specifications per (HSR 17.10.1)
Compaction of & preparation of sub grade including loosening, levelling of earth 225 mm thick top layer, rough dressing of soil, final dressing of earth to give level, camber, watering, rolling with road roller, compacting the bed to achieve minimum dry density as given in the Table 3000-2 as per technical clause 305 of MORT&H Specifications.[HSR 17.5.3]
Providing & laying _______ mm Granular Sub-Base with Coarse Graded Material - Grading-I (Table:- 400-2) Construction of granular sub-base by providing coarse graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with Rotavator at OMC, and compacting with vibratory roller to achieve the desired density, complete as per clause 401.of MORT&H specifications. Grading I material (Based on HSR 17.15.1) Note: - 1.Only crushed metal material should be used. No local earth sand shall be used. The material finer than 425 micron shall have zero Plasticity Index (PI). 2. Materials to be used and operations of manufacturing shall be approved by the engineer.
Construction of 150 mm dry lean cement concrete Sub- base over a prepared sub-grade with coarse and fine aggregate conforming to IS: 383, the size of coarse aggregate not exceeding 25 mm, aggregate cement ratio not to exceed 15:1, aggregate gradation after blending to be as per table 600-1, cement content not to be less than 150 kg/ cum, optimum moisture content to be determined during trial length construction, concrete strength not to be less than 10 Mpa at 7 days, mixed in a batching plant, transported to site, laid with a paver with electronic sensor, compacting with 8-10 tonnes vibratory roller, finishing and curing, as per clause 601 of MORT&H specifications. (HSR 17.44)Note: - Minimum cement content for this item will be 150 kg. per cum of concrete as per approved job mix formula. If the cement content is more than 150 kg /cum, then the extra cement will be incidental to work and nothing shall be payable on this account.
Construction of 250 mm un-reinforced M-40 grade concrete pavement with dowel jointed, over a prepared sub base with 43 grade OPC cement concrete coarse and fine aggregate conforming to IS 383, maximum size of coarse aggregate not exceeding 25 mm, mixed in a fully computerised batching and mixing plant as per approved mix design, transported to site in transit mixer with a fixed form or slip form paver, spread, compacted and finished in a continuous operation including provision of contraction, expansion, construction and longitudinal joints, joint filler, separation membrane, sealant primer, joint sealant, debonding strip, dowel bar, tie rod, admixtures as approved, curing compound, finishing to lines and grades as per drawing, complete as per clause 602 of MORT&H specifications. (minimum content of cement 440 kg/cum) (Based on HSR 17.45.6) Note: - Minimum cement content for this item will be 440 kg. per cum of concrete as per approved job mix formula. If the cement content is more than 440 kg /cum, then the extra cement will be incidental to work and nothing shall be payable on this account.
G and R Buildcon
Yunish Khan Contractor
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .