Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹85.9 LAdmitted-Finance | ₹85.9 L | L1 | Admitted-Finance |
| 2 | L2₹86.1 L+₹25,245 (0.29%)Admitted-Finance | ₹86.1 L+₹25,245 (0.29%) | L2 | Admitted-Finance |
| 3 | L3₹86.4 L+₹49,800 (0.58%)Admitted-Finance | ₹86.4 L+₹49,800 (0.58%) | L3 | Admitted-Finance |
| 4 | L4₹88.0 L+₹2.1 L (2.45%)Admitted-Finance | ₹88.0 L+₹2.1 L (2.45%) | L4 | Admitted-Finance |
| 5 | L5₹99.2 L+₹13.3 L (15.5%)Admitted-Finance | ₹99.2 L+₹13.3 L (15.5%) | L5 | Admitted-Finance |
| Sl No | Description | Qty | Unit | IMPLA GENERAL SUPPLIERS L1 | WULAR INFRASTRUCTURE PVT LTD L3 | M/S WANI ELECTRICAL L5 | HARMUKH INFRASTRUCTURE PRIVATE LIMITED L4 | A One Engineers L2 |
|---|---|---|---|---|---|---|---|---|
| 1.00Work items identified; | ||||||||
| 1.01 | Supply, installation, testing and commisioning of 11/0.433KV, 3-phase(EE Level-II) Distribution Transformers 63 KVA with Bimetallic Terminal complete in all respect as per REC Standard (as mentioned in SBD) | 7 | No. | 1,35,000 ₹9,45,000 | 1,70,000 ₹11,90,000 | 1,60,000 ₹11,20,000 | 1,50,000 ₹10,50,000 | 1,33,000 ₹9,31,000 Lowest |
| 1.02 | Supply, installation, testing and commisioning of 9 mtr (410 SP-33) long Steel Tubular Poles complete with base plate(300x300x5mm), top cap, including digging of pit (1/6th of pole height) positioning etc, complete in all respect as per REC Standard (as mentioned in SBD) | 62 | Nos. | 20,500 ₹12,71,000 | 19,000 ₹11,78,000 Lowest | 21,500 ₹13,33,000 | 20,000 ₹12,40,000 | 19,200 ₹11,90,400 |
| 1.03 | Supply, installation, testing and commisioning of 8 mtr(410 SP-15) long Steel Tubular Poles complete with base plate(300x300x5mm), top cap, including digging of pit (1/6th of pole height) positioning etc, complete in all respect as per REC Standard (as mentioned in SBD) | 207 | Nos. | 15,000 ₹31,05,000 Lowest | 16,700 ₹34,56,900 | 16,400 ₹33,94,800 | 15,900 ₹32,91,300 | 16,000 ₹33,12,000 |
| 1.04 | Supply, laying, stringing, tensioning, binding of 50 Sqmm ACSR Conductor complete in all respects as per REC standards (as mentioned in SBD). | 16.56 | Km. | 60,000 ₹9,93,600 | 58,000 ₹9,60,480 | 63,000 ₹10,43,280 | 57,000 ₹9,43,920 Lowest | 60,000 ₹9,93,600 |
| 1.05 | Supply, laying, stringing, tensioning, binding of 30 Sqmm ACSR Conductor complete in all respects as per REC standards (as mentioned in SBD) | 7.44 | Km. | 38,000 ₹2,82,720 | 26,000 ₹1,93,440 Lowest | 38,000 ₹2,82,720 | 38,000 ₹2,82,720 | 39,000 ₹2,90,160 |
| 1.06 | Supply,Carraige upto site and fixing of GI V Cross arm & GI F Top with clamps duly fabricated as per site requirement including clamps(50x6 mm), GI Nuts & Bolts,washers etc complete in all respects as per REC standards. | 1,302 | Kg | 170 ₹2,21,340 | 130 ₹1,69,260 | 170 ₹2,21,340 | 125 ₹1,62,750 Lowest | 150 ₹1,95,300 |
| 1.07 | Supply,Carraige upto site, fixing and installation of GI Channels of different sizes including clamps and braces. | 1,960 | Kg | 165 ₹3,23,400 | 130 ₹2,54,800 | 170 ₹3,33,200 | 125 ₹2,45,000 Lowest | 150 ₹2,94,000 |
| 1.08 | Supply,Carraige upto site,Installation,testing and Commissioning of 11 KV porecelain composite Pin Insulators 12 kv.5KN, Lighting impulse 75 Kv positive and 80 Kv negative, Creepage distance 320mm complete in all respects as per REC standards | 186 | No. | 250 ₹46,500 | 200 ₹37,200 Lowest | 250 ₹46,500 | 250 ₹46,500 | 230 ₹42,780 |
| 1.09 | Supply, Carraige upto site, installation, testing and Commissioning of Gapless Surge Arrestor 9 kV, 10 kA, LA with polymer housing, Stn. Type complete in all respects as per REC standards. | 7 | Set | 4,000 ₹28,000 | 2,000 ₹14,000 Lowest | 8,000 ₹56,000 | 5,000 ₹35,000 | 6,000 ₹42,000 |
Tender Value
Refer Docs
EMD Value
₹1.8 L
Closing Date
30 May 2022, 2:00 pmClosed
Executive Engineer, ED Budgam, KPDCL
Office of the Executive Engineer, ED Budgam, KPDCL
Supply, installation, testing and commissioning of distribution transformers and various line materials for improvement cum stabilization of Electrical Network under under District Capex Budget-PRI Grants IN ED BUDGAM
2022_PDD_169470_1
EDB_30_of_2022_23
Open Tender
Electrical and Maintenance Works
Turn-key
30 days
ED BUDGAM
AS PER SBD
7 documents required · 7 mandatory
₹2,000
Executive Engineer, ED Budgam, KPDCL
₹1.8 L
2 Jun 2022
17 May 2022
31 May 2022
17 May 2022
30 May 2022
18 May 2022
17 May 2022 - 18 May 2022
Amount
Work items identified;
Supply, installation, testing and commisioning of 11/0.433KV, 3-phase(EE Level-II) Distribution Transformers 63 KVA with Bimetallic Terminal complete in all respect as per REC Standard (as mentioned in SBD)
Supply, installation, testing and commisioning of 9 mtr (410 SP-33) long Steel Tubular Poles complete with base plate(300x300x5mm), top cap, including digging of pit (1/6th of pole height) positioning etc, complete in all respect as per REC Standard (as mentioned in SBD)
Supply, installation, testing and commisioning of 8 mtr(410 SP-15) long Steel Tubular Poles complete with base plate(300x300x5mm), top cap, including digging of pit (1/6th of pole height) positioning etc, complete in all respect as per REC Standard (as mentioned in SBD)
Supply, laying, stringing, tensioning, binding of 50 Sqmm ACSR Conductor complete in all respects as per REC standards (as mentioned in SBD).
Supply, laying, stringing, tensioning, binding of 30 Sqmm ACSR Conductor complete in all respects as per REC standards (as mentioned in SBD)
Supply,Carraige upto site and fixing of GI V Cross arm & GI F Top with clamps duly fabricated as per site requirement including clamps(50x6 mm), GI Nuts & Bolts,washers etc complete in all respects as per REC standards.
Supply,Carraige upto site, fixing and installation of GI Channels of different sizes including clamps and braces.
Supply,Carraige upto site,Installation,testing and Commissioning of 11 KV porecelain composite Pin Insulators 12 kv.5KN, Lighting impulse 75 Kv positive and 80 Kv negative, Creepage distance 320mm complete in all respects as per REC standards
Supply, Carraige upto site, installation, testing and Commissioning of Gapless Surge Arrestor 9 kV, 10 kA, LA with polymer housing, Stn. Type complete in all respects as per REC standards.
Supply, Carraige upto site, installation, testing and Commissioning of 11 kV G.O AB Switch 3-phase, 3pole 200-Amp, vertical Type with fittings complete in all respects as per REC standards.
Supply, Carraige upto site, installation, testing and Commissioning of 11 kV Horn Gap Fuse Set 3 Phase 200A complete in all respects as per REC standards.
Supply, Carraige upto site, laying, stringing, tensioning, binding of 1.1 KV grade, 1-core 185 Sqmm PVC Conductor FRLS type complete in all respects as per REC standards
Supply,Carraige upto site, fixing of Aluminium Thimbles of size 185 Sqmm.
Supply,Carraige upto site, fixing and Commissioning of Aluminium Solderless Clamps of size 185 Sqmm.
Supply, Carraige upto site, installation, testing and Commissioning of LT Fuse Unit complete in all respects as per standards
Earthing of substation-Excavation of earth pit of dia 650 mm & depth 3000 mm, installation of Earthing pipe of 40 mm Nominal bore & 4mm wall thickness & length 2.5 mtr long as Per IS 1239. GI Strip for neutral earthing of size 75 mmx10 mm, 50 mmx6 mm for connection of transformer body & lightening arrestor as per IS 2629/85, GI nuts & bolts,refilled with earth enhancement materials and earth Chamber made of brick masonary with RCC slab cover.
Supply,Carraige upto site, fixing of G I Muky Clamps. As per standards
Supply,Carraige upto site, fixing of Shackale insulators.
Cement bottoming of S T poles in 1:2:4 mix,up to 1/6th plantation depth of pole below ground, 9" above ground,circular with radius 6" around the pole girth/surface ,top surface tappered outwards 0.5 cum/pole as per the diagram given in technical specifications.
Earthing of steel tubular poles complete by GI pipe 40mm or GI rod 20mm 2.5mtr long through GI strip.
Painting of Poles with one coat of Red Oxide (1ltr/pole) and two coats of alimunium paint (1ltr/pole).
Supply and fixing of Anti climbind Device complete in all respects as per REC Standards
Supply and fixing of danger plates complete in all respects as per REC Standards
Wooden Ladder(Bambo Ladder 15 feet)
Link rod
NOTE: 1.The rates quoted by the bidder for all the items shall be inclusive of GST/freight/insurance/storage/installation/testing and any other charges FOR Creation of 63 kVA new Substations along with HT/LT network under the jurisdiction of ED Budgam, KPDCL.
A One Engineers
WULAR INFRASTRUCTURE PVT LTD
HARMUKH INFRASTRUCTURE PRIVATE LIMITED
M/S WANI ELECTRICAL
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .