| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹13.8 CrAccepted-AOC NO 30 PERIYAR NAGAR ERODE 638001 | ERODE | TAMIL NADU | 638001 | L1 | Accepted-AOC AOC | |
| 2 | L2₹14.7 Cr+₹27.4 L (1.90%)Rejected-Finance | L2 | Rejected-Finance Rejected | |
| 3 | L3₹15.1 Cr+₹68.3 L (4.75%)Rejected-Finance NO 07 CENTRAL STREET KILPAUK GARDEN COLONY CHENNAI 600010 | CHENNAI | TAMIL NADU | 600010 | L3 | Rejected-Finance Rejected | |
| 4 | Rejected-Technical | - | Rejected-Technical Rejected |
Tender Value
₹13.7 Cr
EMD Value
₹7.0 L
Closing Date
27 Aug 2024, 5:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
Chief Engineer
Fishing Harbour Project Circle Fisheries and Fishermen Welfare Department Chennai35
Construction of Fish Landing Centre with Bait Arch at Kooduthalai in Tirunelveli District.
2024_AHDF_466006_1
02/DB/F.114 N/2024
Open Tender
Civil Works
Lump-sum
365 days
Kooduthalai
As mentioned in PQ Document
4 documents required · 4 mandatory
₹0
₹7.0 L
29 Oct 2024
25 Jul 2024
28 Aug 2024
25 Jul 2024
27 Aug 2024
25 Jul 2024
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Formation of Bedding Layer for rubble mound Groynes with quarry run hard blue granite stone of weight 1kg to 10kg having a specific gravity of not less than 2.65 as per approved design and drawing including quarrying, loading transporting by tippers/lorries weighing in the electronic weigh bridge for measurement, dumping, placing in position to required level, profile and finishing the side slopes 1 : 2.0 on both sides with necessary equipment and devices as per the drawings and specification etc complete as directed by the Departmental Officers. The rate is also inclusive of placing, sectioning and finishing with necessary equipment and devices and hire and operational charges of tools and plants etc. (The payment shall be made on weight basis (ie) laden weight minus unladden weight). The contractor has to make his own arrangements for weigh bridge. | 26,538 | MT | 852 | ₹2,26,10,376 |
| 2 | Formation of core layer for rubble mound Groyneswith quarry run hard blue granite stone of weight 50Kg to 300Kg having a specific gravity of not less than 2.65 as per approved design and drawing including quarrying, loading, transporting by tippers/lorries weighing in the electronic weigh bridge for measurement, dumping, placing in position to required level, profile and finishing the side slopes 1 : 2.0 on both sides with necessary equipment and devices as per the drawing and specification etc., complete as directed by the Departmental Officers. The rate is also inclusive of placing, sectioning and finishing with necessary equipment and devices and hire and operational changes of tools and plants etc. ( The payment shall be made on weight basis (ie) laden weight minus unladden weight). The contractor has to make his own arrangements for weigh bridge. | 44,323 | MT | 852 | ₹3,77,63,196 |
| 3 | Formation of Toe berm for rubble mound Groynes with hard blue granite stone of weight ranging from 500Kg to 800 kg to a thickness of 1.40M &Toe berm having a specific gravity of not less than 2.65 and as nearly cubical as possible as per approved design and drawing. The rate is inclusive of quarrying, loading at quarry using crane and other tools and plants as required, transporting by tippers/ lorries weighing on the electronic weigh bridge for measurement, Unloading/dumping placing in position to required level, profile and finishing the side slopes of 1 :2.0using crane and floating equipment and devices as per the drawing and specification etc., complete and as directed by the Departmental Officers. The rate is inclusive of placing sectioning and finishing with necessary equipments and devices and hire and operational charges of tools and plants etc. (The payment shall be made on weight basis (ie) ladden weight minus unladden weight). The contractor has to make his own arrangements for weigh bridge. | 25,613 | MT | 940 | ₹2,40,76,220 |
| 4 | Formation of Armour layer for rubble mound Groynes with hard blue granite stone of weight ranging from 1500Kg to 2500 kg to a thickness of 1.40M &Toe berm having a specific gravity of not less than 2.65 and as nearly cubical as possible as per approved design and drawing. The rate is inclusive of quarrying, loading at quarry using crane and other tools and plants as required, transporting by tippers/ lorries weighing on the electronic weigh bridge for measurement, Unloading/dumping placing in position to required level, profile and finishing the side slopes of 1 :2.0using crane and floating equipment and devices as per the drawing and specification etc., complete and as directed by the Departmental Officers. The rate is inclusive of placing sectioning and finishing with necessary equipments and devices and hire and operational charges of tools and plants etc. (The payment shall be made on weight basis (ie) ladden weight minus unladden weight). The contractor has to make his own arrangements for weigh bridge. | 27,368 | MT | 940 | ₹2,57,25,920 |
| 5 | Earth work excavation for foundation in all soils and sub-soils and to full depth as may be directed except in rock requiring blasting inclusive of shoring shuttering, bailing out water wherever necessary and depositing the surplus earth within the compound in places shown by the departmental officers with an initial lead of 10 mts and initial lift of 2 mts. and clearing and levelling the site, etc., complete complying with standard specification. | 159 | cum | 219.9 | ₹34,964.1 |
| 6 | Supplying and filling in foundation, basement, etc with filling crushed stone sand in layers of not more than 15 cm thick well watered, rammed and consolidated etc. complete complying with standard specification and as directed by the departmental officers. | 9 | cum | 1,681 | ₹15,129 |
| 7 | Refilling with excavated earth other than sand with an initial head load of 100 mts. and depositing the earth as shown by the departmental officers in layers of not more than 15 cm thick well rammed, watered and consolidated etc. complete complying with standard specification | 113 | cum | 42.85 | ₹4,842.05 |
| 8 | Cement Concrete 1:4:8 (One Cement, Four crushed stone sand and eight hard broken stone jelly) using 40 mm gauge hard broken granite stone jelly for foundation including dewatering wherever necessary and laid in layers of not more than 15 cm thick, well rammed, consolidated and curing etc. complete complying with standard specification | 56 | cum | 5,356.3 | ₹2,99,952.8 |
| 9 | Supplying and erecting steel centering including necessary supports for plane surfaces for Reinforced Cement Concrete works such as column footings, column pedestals, plinth beams, grade beams, staircase steps, etc. which require only nominal strutting using mild steel sheets of size 90cm x 60cm and 10 BG stiffened with welded mild steel angles of size 25mm x 25mm x 3 mm for boarding, laid over silver oak joists of size 10cm x 6.5cm spaced at about 75cm centre to centre or at suitable intervals etc. complete in all floors complying with standard specifcation. (Payment for centering shall be given after the concrete is laid) | 159 | sqm | 932.35 | ₹1,48,243.65 |
| 10Supplying and erecting centering for sides and soffits including necessary supports and strutting upto 3.29 M height for plane surfaces as detailed below in all floors with all cross bracings using Mild Steel sheets of size 90 x 60 cm and 10 BG stiffened with welded Mild Steel angle of size 25mm x 25mm x 3 mm for boarding laid over silver oak joists of size 10cm x 6.50 cm spaced at abote 90 cm centre to centre and supported by casurina props of 10cm to 13 cm dia spaced at not more than 75 cm centre to centre etc. complete complying with the standard specificaiton. (Payment for centering shall be given after the concrete is laid) | |||||
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
BOQ_553767.xls
BOQ Document • 0.27 MB
148979599.pdf
Tender Document • 0.39 MB
PriceCover.pdf
Tender Document • 1.19 MB
PQCover.pdf
Tender Document • 0.82 MB
148979601.html
Tender Document • 0.06 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .