| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹2.0 CrAccepted-AOC | ₹2.0 Cr Quoted ₹2.1 Cr | L1 | Accepted-AOC First Lowest |
| 2 | L2₹2.1 Cr+₹2.0 L (0.96%)Rejected-AOC | ₹2.1 Cr+₹2.0 L (0.96%) | L2 | Rejected-AOC Second Lowest |
| 3 | L3₹2.1 Cr+₹4.0 L (1.92%)Rejected-AOC | ₹2.1 Cr+₹4.0 L (1.92%) | L3 | Rejected-AOC Third Lowest |
| Sl No | Description | Qty | Unit | VIDHYASAGAR L2 | K.SURESHKUMAR L3 | N.RAMAN L1 |
|---|---|---|---|---|---|---|
| 1.00 | Earth work excavation for foundation by Mechanical means for Isolated & Combined Footing etc in all soils and sub-soils and to full depth as may be directed except in rock requiring blasting inclusive of shoring shuttering, bailing out water wherever nec essary and depositing the surplus earth within the compound in places shown by the departmental officers with an initial lead of 100 mts and clearing and levelling including dressing of sides and raming of bottoms etc., complete complying with standard speci fication and as directed by the departmental officers.- Upto 2.40m Footing Depth. | 324 | M3 | 378 ₹1,22,472 | 381.6 ₹1,23,638.4 | 374.41 ₹1,21,308.84 Lowest |
| 2.00 | Earth work Open excavation by Mechanical Means for Open Earthwork in all soils and sub-soils and to full depth as may be directed except in rock requiring blasting in clusive of shoring shuttering, bailing out water wherever necessary and depositing the surplus earth within the compound in places shown by the departmental officers with an initial lead of 100 mts and clearing and levelling including dressing of sides and raming of bottoms etc., complete complying with standard specification and as directed by the departmental officers.Upto 2.40m Footing Depth. | 34 | M3 | 205 ₹6,970 | 206.93 ₹7,035.62 | 203.03 ₹6,903.02 Lowest |
| 3.00 | Cement Concrete 1:5:10 (One Cement, Five crushed stone sand and Ten hard broken stone jelly) using 40 mm gauge hard broken granite stone jelly for foundation including dewatering wherever necessary and laid in layers of not more than 15 cm thick well rammed, consolidated and including curing etc. complete complying with standard specification and as directed by the departmental officers -Mixing by mechanical means | 26 | M3 | 5,857 ₹1,52,282 | 5,913.49 ₹1,53,750.74 | 5,802.08 ₹1,50,854.08 Lowest |
| 4.00 | Supplying and filling in foundation, basement, etc with conveyed earth in layers of not more than 150mm thick layers well watered, rammed with surface vibrator and consolidated including conveyance charges etc. complete complying with standard specification and as directed by the departmental officers. | 239 | M3 | 538 ₹1,28,582 | 543.05 ₹1,29,788.95 | 532.82 ₹1,27,343.98 Lowest |
| 5.00 | Providing ANTI-TERMITE treatment to soil adjacent under building foundation, plinth periphery of the building by application of chemicals of ISI 63613 part I to IV in stages to suit the progress of work as per the detailed specification as below. Including breaking of termite mounds, making holes with clow bar, closing the holes after the treatment and including cost of chemicals, labour charges, transport and storing etc., complete and as directed by the departmental officers. | 235 | M2 | 148 ₹34,780 | 149.8 ₹35,203 | 146.98 ₹34,540.3 Lowest |
| 5.01Stage - 1 Spraying anti-termite chemical solution for the foundation before laying concrete in bottom and sides of foundation. | ||||||
| 5.02Stage - 2 Spraying anti-termite chemical solution to the grade beam level, spraying has to be done for grade beam, brick masonry contact with the back fill earth | ||||||
| 5.03Stage - 3 Spraying anti-termite chemical solution on the top layer for flooring before laying the flooring concrete. This treatment has to be carried out on the top layer of filling by making holes with crow bar to a depth of 60cms and at 60cms intervels on both | ||||||
| 5.04Stage - 4 Spraying anti-termite chemical solution alround building out side by making holes through bar before laying plinth protection and the holes to be closed after the treatment. | ||||||
| 6.00 | Supplying and erecting steel centering including necessary supports for plane surfaces for Reinforced Cement Concrete works such as column footings, column pedestals, plinth beams, grade beams, staircase steps, Sill slabs etc. which require only nominal strutting using mild steel sheets of size 90cm x 60cm and 10 BG stiffened with welded mild steel angles of size 25mm x 25mm x 3 mm for boarding, laid with silver oak joists of size 10cm x 5cm & 7.5cm x 5cm as support runner , vertical stiffener, side support and Top Horizontal stiffener spaced at about 60cm to 90cm centre to centre or at suitable intervals etc. complete in all floors complying with standard specifcation. (Payment for centering shall be given after the concrete is laid). | 204 | M2 | 732 ₹1,49,328 | 738.93 ₹1,50,741.72 | 725 ₹1,47,900 Lowest |
Tender Value
₹2.0 Cr
EMD Value
₹1.1 L
Closing Date
9 Sept 2025, 3:00 pmClosed
Superintending Engineer
Office of the Superintending Engineer, PWD., Buildings Construction and Maintenance Circle, Tirunelveli
Construction of 9 Class room building and Drinking water supply arrangements in Government Higher Secondary School at Mukkani in Thoothukudi District.
2025_PWD_597653_1
14(7) SE/2025-26 dated 12.08.2025
Open Tender
Civil Works - Buildings
Lump-sum
240 days
Mukkani
Please refer Tender documents.
3 documents required · 3 mandatory
₹0
₹1.1 L
27 Oct 2025
26 Aug 2025
10 Sept 2025
26 Aug 2025
9 Sept 2025
26 Aug 2025
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .