| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹5.8 LAccepted-Finance | ₹5.8 L | L1 | Accepted-Finance LESS |
| 2 | L2₹5.8 L+₹2,815 (0.49%)Rejected-Finance | ₹5.8 L+₹2,815 (0.49%) | L2 | Rejected-Finance MORE |
| Sl No | Description | Qty | Unit | D RAJENDRAN L1 | PNAT CONSTRUCTIONS L2 |
|---|---|---|---|---|---|
| 1.00 | Cleaning the Juncle using JCB Complete as per the Direction of the Departmental officers Etc., Complete | 255 | m2 | 9 ₹2,295 Lowest | 10 ₹2,550 |
| 2.00 | Earth work excavation for foundation in hard stiff clay, stiff black cotton,hard red earth mixed with small size boulders SS.20B and sand,silt or other loose soil,wet sand, or silt not under water,light black cotton soil,sandy loam ordinary soil and tofull depth as may be directed expect in hardrock requiring blasting inclusive of shoring shuttering,and baling out water wherever necessary refilling the sides of foundation with excavated soil other than sand in layers of 15cm thick well rammed and completed depositing the surplus excavated soil with in the compound in places shown by the departmental officers with intial lead and lifts and claening and levelling the site etc., complete. | 2 | m3 | 220 ₹440 Lowest | 220 ₹440 Lowest |
| 3.00 | Cement concrete 1:4:8 (one cement, four sand and eight aggregate) using 40mm hard broken granite stone jelly for foundation including dewatering if found necessary and laid in layers of not more than 15 cm thick and compacted etc., complete complying with standard specification. | 1 | m3 | 5,960 ₹5,960 Lowest | 5,962 ₹5,962 |
| 4.00 | Shuttering for soffits of RCC Column,beams ,etc.,including strutting 3m high using mild steel sheets of size 90cm X 60cm X and B.G 10 stiffened with M.Sangles of size 25mm X 25mm X 3mm laid over silver Oak (C.W) joists of size 10cm X 6.5cm (spaced at about 90cmc/c ) and supported by casurina props of 10 cm to13 cm dia (spaced of 75 cm C/C) complying with standard specification and directed - 10 m 2 (P & D)Data 38 | 14 | m2 | 350 ₹4,900 Lowest | 356 ₹4,984 |
| 5.00 | Reinforced Cement concrete 1:1.5:3 (one cement,one and half M.sand & three course aggregate) using 20mm gauge hand broken/and broken granite stone for all RCC items of works excluding centering shuttering and cost of reinforcement but including curingetc.,complete and also including fixing fan clamps and fixtures in rcc works wherever necessary as directed by departmental officer etc., complete. | 2 | m3 | 9,744 ₹19,488 Lowest | 9,744 ₹19,488 Lowest |
| 6.00 | Supplying, fabricating and placing in position RTS rods for all RCC works including cost of steel and binding wire also in all floors complete complying with standard specification | 2 | Qtl | 9,542 ₹19,084 Lowest | 9,542 ₹19,084 Lowest |
| 7.00 | Precast Solid Blocks Masonry in CM 1:4 (One Cement & Four Sand) Using walls of size 400mm x 200mm x 200mm including finishing, curingetc., complete complyingwith standard specification - 100 CFT | 30 | m2 | 6,556 ₹1,96,680 Lowest | 6,556 ₹1,96,680 Lowest |
| 8.00 | Plastering with cement mortar 1:5 (one cement and five sand by volume) 12mm thick for all internal/external surfaces like super structure, rainwater, ducts, elevation in all floors complying with standard specifications. | 68 | m2 | 306 ₹20,808 Lowest | 309 ₹21,012 |
| 9.00 | Painting with First Quality Emulsion paint two coat including cleaning, scrapping, removal of dust and necessary plaster of paris putty works wherever required etc., complete. | 158 | m2 | 290 ₹45,820 Lowest | 290 ₹45,820 Lowest |
| 10.00 | Supplying and Fixing of barbed wire fencing using stone size of 0.15x0.15 to an of 2.10m below 0.60m and above 1.80 with necessary support and barbed wire - 10 gauge 2 ply 4 pronged (Galvinised) of 5 row horizontally and 6 nos vertically to ht. of 1.85m to 0.40, 2.4m C/c for 10 Rmtr including earth work, CC 1:2:4 mix tying the wire with 7 nos size 0.15x0.15x2.10 | 180 | m | 1,180 ₹2,12,400 Lowest | 1,185 ₹2,13,300 |
Tender Value
₹7 L
EMD Value
₹7,000
Closing Date
29 Dec 2025, 3:00 pmClosed
The Assistant Commissioner, East Zone
The Assistant Commissioner , East Zone, Singanallur, Coimbatore - 641005
Providing Fencing and Reconstruction of Compound Wall at Subhadharshan OHT Tank and PMR Layout in Ward 6 and 23 . East Zone.
2025_MAWS_632271_29
E10/East zone/2025
Open Tender
Civil Works - Water Works
Works
90 days
The Assistant Commissioner, East Zone, Singanallur
As per Tender Conditions
5 documents required · 5 mandatory
₹0
₹7,000
23 May 2026
17 Dec 2025
30 Dec 2025
17 Dec 2025
29 Dec 2025
17 Dec 2025
Cleaning the Juncle using JCB Complete as per the Direction of the Departmental officers Etc., Complete
Earth work excavation for foundation in hard stiff clay, stiff black cotton,hard red earth mixed with small size boulders SS.20B and sand,silt or other loose soil,wet sand, or silt not under water,light black cotton soil,sandy loam ordinary soil and tofull depth as may be directed expect in hardrock requiring blasting inclusive of shoring shuttering,and baling out water wherever necessary refilling the sides of foundation with excavated soil other than sand in layers of 15cm thick well rammed and completed depositing the surplus excavated soil with in the compound in places shown by the departmental officers with intial lead and lifts and claening and levelling the site etc., complete.
Cement concrete 1:4:8 (one cement, four sand and eight aggregate) using 40mm hard broken granite stone jelly for foundation including dewatering if found necessary and laid in layers of not more than 15 cm thick and compacted etc., complete complying with standard specification.
Shuttering for soffits of RCC Column,beams ,etc.,including strutting 3m high using mild steel sheets of size 90cm X 60cm X and B.G 10 stiffened with M.Sangles of size 25mm X 25mm X 3mm laid over silver Oak (C.W) joists of size 10cm X 6.5cm (spaced at about 90cmc/c ) and supported by casurina props of 10 cm to13 cm dia (spaced of 75 cm C/C) complying with standard specification and directed - 10 m 2 (P & D)Data 38
Reinforced Cement concrete 1:1.5:3 (one cement,one and half M.sand & three course aggregate) using 20mm gauge hand broken/and broken granite stone for all RCC items of works excluding centering shuttering and cost of reinforcement but including curingetc.,complete and also including fixing fan clamps and fixtures in rcc works wherever necessary as directed by departmental officer etc., complete.
Supplying, fabricating and placing in position RTS rods for all RCC works including cost of steel and binding wire also in all floors complete complying with standard specification
Precast Solid Blocks Masonry in CM 1:4 (One Cement & Four Sand) Using walls of size 400mm x 200mm x 200mm including finishing, curingetc., complete complyingwith standard specification - 100 CFT
Plastering with cement mortar 1:5 (one cement and five sand by volume) 12mm thick for all internal/external surfaces like super structure, rainwater, ducts, elevation in all floors complying with standard specifications.
Painting with First Quality Emulsion paint two coat including cleaning, scrapping, removal of dust and necessary plaster of paris putty works wherever required etc., complete.
Supplying and Fixing of barbed wire fencing using stone size of 0.15x0.15 to an of 2.10m below 0.60m and above 1.80 with necessary support and barbed wire - 10 gauge 2 ply 4 pronged (Galvinised) of 5 row horizontally and 6 nos vertically to ht. of 1.85m to 0.40, 2.4m C/c for 10 Rmtr including earth work, CC 1:2:4 mix tying the wire with 7 nos size 0.15x0.15x2.10
Painting two coats over New iron works such as steel doors, windows, ventilators, window bars, balustrades etc., with best approved best quality of synthetic enamel paint of approved colour over the existing priming coat etc., complete complying with standard specifications and as directed by the departmental officers.
Supplying and fixing of ms angle Truss and Door including cost and all accessories etc.,complete.
Add :- GST @ 18%
stage.html
html • 0.03 MB
tech_eval.pdf
fin_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.22 MB
Tendernotice_2.pdf
PDF • 0.17 MB
ITB.pdf
Additional Documents • 0.09 MB
ez-e10-2025-Watersupply.pdf
Tender Documents • 0.54 MB
BOQ_757830.xls
BOQ • 0.28 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .