| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹36.8 LAccepted-AOC | L1 | Accepted-AOC low | |
| 2 | L2₹38.9 L+₹2.1 L (5.80%)Rejected-AOC | L2 | Rejected-AOC high |
Tender Value
Refer Docs
EMD Value
₹42,000
Closing Date
9 Nov 2022, 3:00 pmClosed
Block Development Officer (V.Pt),
Block Development Officer (V.Pt), Vandavasi Block, Tiruvannamalai District
Providing Paverblock pavement at MGR nagar Colony Mariyamman Kovil Street (115 M ), Providing Paverblock pavement at MGR nagar Colony Anganvadi Street (69 M ) , Providing Paverblock pavement at MGR nagar Pillaiyar Kovil Street (40 M ) at Sennavar
2022_RDTN_260611_1
Roc. No. AS No 2156/2022/A13-14 Dt.06.10.2022 012
Open Tender
Civil Works
Lump-sum
180 days
Vandavasi
Please refer Tender documents.
3 documents required · 3 mandatory
₹0
₹42,000
Yes
Block Development Officer (V.Pt),
14 Dec 2022
3 Nov 2022
9 Nov 2022
3 Nov 2022
9 Nov 2022
3 Nov 2022
3 Nov 2022
Amount
Providing Paverblock pavement at MGR nagar Colony Mariyamman Kovil Street in Sennavaram Panchayat (115 M )
Earth work excavation for foundation and depositing on bank with initial lead of 10 mts and initial lift of 2.0 in hard stiff clay stiff black cotton soil, hard red earth shales, murram, gravel, stoney earth and earth mixed with 50% fair sized boulders and gravelly soil etc., complete for boxing as per IS 20A.
Base course concrete with C.C.1:4:8 mix using 40mm I.S.S. size HBG metal from approved quarry to work site including cost and conveyance of all materials and labour charges for mixing for base course as per standared specification.
Centering and shuttering for sides including cost and convayance and labour charges etc complete.
Cement Concrete Pavement with C.C.1:2:4 HBG metal from approved quarry to work site including cost and conveyance of all materials and labour charges for mixing, laying compacting, etc., complete
Construction of Granular Sub base by providing well graded material (25 mm to 4.75 mm IRC HBG metal @ 65 %,4.75 to 2.36mm IRC HBG metal @20%&2.36 mm below IRC HBG metal @15%)& (the material passing 425 microns sieve shall have liquid limit and plasticity index not more than 25 & 6% repectively) spreading in uniform layers with motor grader on prepared surface mixing by mix in place method with rotovator at OMC and compacting with three wheel 80-100 KN capacity and finished in accordance with the requirements of the specification and thickness as per approved plans or as directed by the Engineer (Mix -in - place method) .
Providing and Laying of Interlocking Rubber moulded Hydraulic pressed Paver block Pavements specification clause 1504, M30 grade 60 mm thickness paver block
Providing Paverblock pavement at MGR nagar Colony Anganvadi Street in Sennavaram Panchayat (69 M )
Earth work excavation for foundation and depositing on bank with initial lead of 10 mts and initial lift of 2.0 in hard stiff clay stiff black cotton soil, hard red earth shales, murram, gravel, stoney earth and earth mixed with 50% fair sized boulders and gravelly soil etc., complete for boxing as per IS 20A.
Base course concrete with C.C.1:4:8 mix using 40mm I.S.S. size HBG metal from approved quarry to work site including cost and conveyance of all materials and labour charges for mixing for base course as per standared specification.
Centering and shuttering for sides including cost and convayance and labour charges etc complete.
Cement Concrete Pavement with C.C.1:2:4 HBG metal from approved quarry to work site including cost and conveyance of all materials and labour charges for mixing, laying compacting, etc., complete
Construction of Granular Sub base by providing well graded material (25 mm to 4.75 mm IRC HBG metal @ 65 %,4.75 to 2.36mm IRC HBG metal @20%&2.36 mm below IRC HBG metal @15%)& (the material passing 425 microns sieve shall have liquid limit and plasticity index not more than 25 & 6% repectively) spreading in uniform layers with motor grader on prepared surface mixing by mix in place method with rotovator at OMC and compacting with three wheel 80-100 KN capacity and finished in accordance with the requirements of the specification and thickness as per approved plans or as directed by the Engineer (Mix -in - place method) .
Providing and Laying of Interlocking Rubber moulded Hydraulic pressed Paver block Pavements specification clause 1504, M30 grade 60 mm thickness paver block
Providing Paverblock pavement at MGR nagar Pillaiyar Kovil Street in Sennavaram Panchayat (40 M )
Earth work excavation for foundation and depositing on bank with initial lead of 10 mts and initial lift of 2.0 in hard stiff clay stiff black cotton soil, hard red earth shales, murram, gravel, stoney earth and earth mixed with 50% fair sized boulders and gravelly soil etc., complete for boxing as per IS 20A.
Base course concrete with C.C.1:4:8 mix using 40mm I.S.S. size HBG metal from approved quarry to work site including cost and conveyance of all materials and labour charges for mixing for base course as per standared specification.
Centering and shuttering for sides including cost and convayance and labour charges etc complete.
Cement Concrete Pavement with C.C.1:2:4 HBG metal from approved quarry to work site including cost and conveyance of all materials and labour charges for mixing, laying compacting, etc., complete
Construction of Granular Sub base by providing well graded material (25 mm to 4.75 mm IRC HBG metal @ 65 %,4.75 to 2.36mm IRC HBG metal @20%&2.36 mm below IRC HBG metal @15%)& (the material passing 425 microns sieve shall have liquid limit and plasticity index not more than 25 & 6% repectively) spreading in uniform layers with motor grader on prepared surface mixing by mix in place method with rotovator at OMC and compacting with three wheel 80-100 KN capacity and finished in accordance with the requirements of the specification and thickness as per approved plans or as directed by the Engineer (Mix -in - place method) .
Providing and Laying of Interlocking Rubber moulded Hydraulic pressed Paver block Pavements specification clause 1504, M30 grade 60 mm thickness paver block
Providing Paverblock pavement at Sennavaram Navithar Street in Sennavaram Panchayat (48 M )
Earth work excavation for foundation and depositing on bank with initial lead of 10 mts and initial lift of 2.0 in hard stiff clay stiff black cotton soil, hard red earth shales, murram, gravel, stoney earth and earth mixed with 50% fair sized boulders and gravelly soil etc., complete for boxing as per IS 20A.
Base course concrete with C.C.1:4:8 mix using 40mm I.S.S. size HBG metal from approved quarry to work site including cost and conveyance of all materials and labour charges for mixing for base course as per standared specification.
Centering and shuttering for sides including cost and convayance and labour charges etc complete.
Cement Concrete Pavement with C.C.1:2:4 HBG metal from approved quarry to work site including cost and conveyance of all materials and labour charges for mixing, laying compacting, etc., complete
Construction of Granular Sub base by providing well graded material (25 mm to 4.75 mm IRC HBG metal @ 65 %,4.75 to 2.36mm IRC HBG metal @20%&2.36 mm below IRC HBG metal @15%)& (the material passing 425 microns sieve shall have liquid limit and plasticity index not more than 25 & 6% repectively) spreading in uniform layers with motor grader on prepared surface mixing by mix in place method with rotovator at OMC and compacting with three wheel 80-100 KN capacity and finished in accordance with the requirements of the specification and thickness as per approved plans or as directed by the Engineer (Mix -in - place method) .
Providing and Laying of Interlocking Rubber moulded Hydraulic pressed Paver block Pavements specification clause 1504, M30 grade 60 mm thickness paver block
Providing Paverblock pavement at Sennavaram Navithar 1 St Street in Sennavaram Panchayat (86 M )
Earth work excavation for foundation and depositing on bank with initial lead of 10 mts and initial lift of 2.0 in hard stiff clay stiff black cotton soil, hard red earth shales, murram, gravel, stoney earth and earth mixed with 50% fair sized boulders and gravelly soil etc., complete for boxing as per IS 20A.
Base course concrete with C.C.1:4:8 mix using 40mm I.S.S. size HBG metal from approved quarry to work site including cost and conveyance of all materials and labour charges for mixing for base course as per standared specification.
Centering and shuttering for sides including cost and convayance and labour charges etc complete.
Cement Concrete Pavement with C.C.1:2:4 HBG metal from approved quarry to work site including cost and conveyance of all materials and labour charges for mixing, laying compacting, etc., complete
Construction of Granular Sub base by providing well graded material (25 mm to 4.75 mm IRC HBG metal @ 65 %,4.75 to 2.36mm IRC HBG metal @20%&2.36 mm below IRC HBG metal @15%)& (the material passing 425 microns sieve shall have liquid limit and plasticity index not more than 25 & 6% repectively) spreading in uniform layers with motor grader on prepared surface mixing by mix in place method with rotovator at OMC and compacting with three wheel 80-100 KN capacity and finished in accordance with the requirements of the specification and thickness as per approved plans or as directed by the Engineer (Mix -in - place method) .
Providing and Laying of Interlocking Rubber moulded Hydraulic pressed Paver block Pavements specification clause 1504, M30 grade 60 mm thickness paver block
Construction of PDS Building at Near Sennavaram GYM in Sennavaram Panchayat
EARTHWORK EXCAVATION for foundation in all soils and sub soils and to full depth as may be directed except in rock requiring blasting but inclusive of shoring, strutting and baling out water wherever necessary and refilling the sides of foundation with excavated earth in layers of not more than 15cm thick, well rammed and consolidated and depositing the surplus earth within the compound in places shown by the departmental officers with initial lead and lift etc.,including levelling the sites complete complying with standard specifications and as directed. (Hard Soil )
Collection and supply of sand and filling in to the basement including cost and conveyance to the siteand all labour charges for filling as per standard specifications
Cement concrete 1:4:8 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing,laying and curing etc complete
Cement concrete 1:1.5:3 using 20mm ISS HBG metal for all RCC item of works excluding cost of Rein forcement and fabricating charges, centering and shuttering but including curing and providing fixtures like fan clamps in the RCC floor or roof slabs wherever necessary and bearing surfaces of walls , sides and bottom of the slabs, beams etc., as directed by the departmental officers complete complying with standard specifications.
Brick work in CM 1:5 mix using country bricks ground moulded of size 83/4"x41/4"x21/4" for the following including curing etc., complete complying with standard specifications. Rate for 10m3
Walls Above Basement (Super Structure)
Supplying and fabrication of steel including cost and conveyance of bending to shape and tying in position and forming grills for all R.C.C works including cost and conveyance of all materials to site and all labour charges for mixing, laying, and curing
Supplying and erecting centering shuttering including necessary supports for plane etc., complete.
Above GL
Floor finish with granolithic flooring in CC 1:2:4 mix using 10 to 12mm chips for 25mm thick including cost and conveyance of all materials and labours etc., complete
Paving the floor with scratch proof ceramic tiles of any colour and any size laid in CM 1:2, 20mm thick. And pointing with white cement 0.4 Kg per Sqm mixed with colouring pigment to suit the colour of the tiles including finishing the joints neatly complying with the standard specifications and as directed by the departmental officers. (The ceramic tiles should be got approved from the Departmental officers before execution).
Plastering with cement mortar 1:5 mix to 12mm thick including cost and conveyance of all materials to site and all labour charges etc
Plastering with cement mortar 1:3 mix to 10 mm thick including cost and conveyance of all materials to site and all labour charges etc complete
Plastering with cement mortar 1:3 mix to 20 mm thick including cost and conveyance of all materials to site and all labour charges etc complete
Distembering two coats with best approved distember including cost and conveyance of all materials to site and all labour charges etc complete
Distembering two coats with best approved distember including cost and conveyance of all materials to site and all labour charges etc complete
Exterior Emulsion painting two coats with best approved quality and colour paint over one coat of Base coat including cost and convyance of all materials to work site and labour charges etc., complete.
Doors D
Doors D1
Window W(1.00x1.30)m
Ventilator V (0.45 x 0.60m)
Rolling shutter
Painting two coats over new iron works using ready mixed enamel paint including cost and conveyance of paint and all labour charges etc complete
Labour Charges for Fixing the Doors inculding all Charges etc..
Labour Charges for Fixing theSteel Window inculding all Charges etc..
Supplying & fixing with cuddapah slabs 20-30mm thick for cup board including all cost and conveyance and all labour charges etc .comp.
Cost and supply of Oriya type Indian baby friendly water closet with "P" or "S" trap etc., complete. ( White )
Supply and fixixng of 15mm dia Brass CP screw down tap
Supply and fixixng of 1000 litre HDPE tank
Wiring with 2 X 1.5 Sq.mm (22 / 0.3) PVC insulated SC unsheathed Copper conducutor cable of 1100V grade in suitable PVC rigid pipe concealed in wall and ceiling with PVC accessories inflush with wall with 3 mm thick Hylum sheet cover with TW box And 5 A FT switch with continuous earth connection of 14 SWG TC wire for making good of the concealed portion with suitable colour for PVC Open Light point / fan point (For electronic Regulator) SD 18
Wiring with 2 X 1.5 Sq.mm (22 / 0.3) PVC insulated SC unsheathed Copper conducutor of 1100V grade in suitable PVC rigid pipe concealed in wall and ceiling with PVC accessories inflush with wall with 150 mm X 100 mm X 113 mm TW switch box with 3 mm thick Hylum sheet cover for 5 A 3 pin non interlocking CS plug with continuous earth wire connection of 14 SWG TC wire for making good of the concealed portion with suitable colour for concealed PVC plug point SD 36
Supply and run of 2 of 1.50 sq.mm (22/0.30) PVC insulated SC unsheathed copper Conductor of 1100 V grade on 7/20GI bearer wire for service connection mains SD 65
Supply and run of 2 X 1.5 sq.mm (22 / 0.30) PVC insulated SC unsheathed copper Conductor of 1100 V grade in 25 mm dia GI pipe ( Class ' B ' ) suitably bent at both ends with necessary angle iron upright and end supports for mains. SD 70
Supply and fixing of WT bulk head fitting with guard ( Philips / Bajaj / Crompton / K Lite ) suitable for incandescent lamp with 60 W bulb.SD 84
Supply and fixing of CFL bulb SD 80
Supply and fixing of 1200 mm ( 48") AC ceiling fan complete with stepped electronic 300 W regulator with 300 mm down rod on the existing clamp. SD 110
Supply and fixing of 16 Amps DPIC Switch of 500 V with fuse and neutral (Side Handle) on suitable TW box PWD Earthing SD 142
Supply and fixing of TNEB Meter board SD 125
Construction of Side Drainage at MGR Nagar Colony Anganvadi Street in Sennavaram Panchayat (65 M )
Earth work excavation and depositing on bank with initial lead of 10 mts and initial lift of 2.0 in hard stiff clay stiff black cotton soil, hard red earth shales, murram, gravel, stoney earth and earth mixed with 50% fair sized boulders and gravelly soil
Cement concrete 1:4:8 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for 10 cum.
Plain Cement concrete 1:3:6 using 20mm hbg jelly for dummy column
Supply and errection of centring including cost and conveyance of all materials at site.
Plastering with Cement Mortar 1:4(one cement and five sand) 20 mm. thick in all floors including curing etc., complete complying with standard specification and as directed
Construction of Side Drainage at Sennavaram ADC in Sennavaram Panchayat (140 M )
Earth work excavation and depositing on bank with initial lead of 10 mts and initial lift of 2.0 in hard stiff clay stiff black cotton soil, hard red earth shales, murram, gravel, stoney earth and earth mixed with 50% fair sized boulders and gravelly soil
Cement concrete 1:4:8 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for 10 cum.
Plain Cement concrete 1:3:6 using 20mm hbg jelly for dummy column
Supply and errection of centring including cost and conveyance of all materials at site.
Plastering with Cement Mortar 1:4(one cement and five sand) 20 mm. thick in all floors including curing etc., complete complying with standard specification and as directed
Construction of Side Drainage at sennavaram Annai Sathiya Nagar in Sennavaram Panchayat (125 M )
Earth work excavation and depositing on bank with initial lead of 10 mts and initial lift of 2.0 in hard stiff clay stiff black cotton soil, hard red earth shales, murram, gravel, stoney earth and earth mixed with 50% fair sized boulders and gravelly soil
Cement concrete 1:4:8 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for 10 cum.
Plain Cement concrete 1:3:6 using 20mm hbg jelly for dummy column
Supply and errection of centring including cost and conveyance of all materials at site.
Plastering with Cement Mortar 1:4(one cement and five sand) 20 mm. thick in all floors including curing etc., complete complying with standard specification and as directed
GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column "BB" for all works in this package}
A.RAJESHKUMAR
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .