| 1 | L1₹6.6 LAccepted-AOC 40 E SUNDARAVELPURAM 7TH STREET TUTICORIN 628 002 | TUTICORIN | TAMIL NADU | 628002 | ₹6.6 L Quoted ₹7.0 L | L1 | Accepted-AOC L1 |
| 2 | L2₹7.5 LRejected-AOC | ₹7.5 L | L2 | Rejected-AOC L2 |
| Sl No | Description | Qty | Unit | S. MURUGAN CONTRACTOR L1 | SRI SATHYA ENTERPRISES L2 |
|---|---|---|---|---|---|
| 1.00 | Charges for complete removing of 10 T /15 T capacity Electrical hoist from the mono rail by providing “A” frame / Derrick & chain block arrangement , loading and unloading and transporting to the workshop, erection of the Hoist after completion of the repair work , testing and commissioning etc. | 5 | Operation | 2,24,975 ₹2,65,470.5 Lowest | 2,35,000 ₹2,77,300 |
| 2.00 | Charges for draining the dirty oil from the gear box by opening the top cover by loosening the fixing bolt and nuts. Cleaning and checking all the gear wheel teeth, slagness of gear wheel and checking the tightness of all the gear. After the works completed the gear box pushed with new oil and refilling with new oil to the required quantity. Closing the gear box top cover by using fixing bolt and nut. | 5 | Operation | 1,62,075 ₹1,91,248.5 Lowest | 1,75,000 ₹2,06,500 |
| 3.00 | Charges for dismantling of rope drum, inspection, cleaning and applying compound & rewinding the steel wire rope and assembling the drum with hoist. | 5 | Operation | 59,875 ₹70,652.5 Lowest | 70,000 ₹82,600 |
| 4.00 | Charges for overhauling of hoist hook assembly, compensating pulleys and changing of hook pulley bearings. | 5 | Operation | 1,49,975 ₹1,76,970.5 Lowest | 1,60,000 ₹1,88,800 |
| 5.00 | Charges for cleaning of all electrical accessories such as motor contactors, push buttons, panel etc., and checking for proper operation | 5 | Operation | 19,050 ₹22,479 Lowest | 23,000 ₹27,140 |
| 6.00 | Charges for Fixing of Hoist system rotary geared type limit switch for lifting operation including supply of limit switches. | 5 | Operation | 50,995 ₹60,174.1 Lowest | 54,500 ₹64,310 |
| 7.00 | Charges for load testing of 10T/ 15T electrical hoists by using test weights with the presence of the competent authority and site Engineer incharge, loading, transporting and unloading of test weights from Switch Yard-II to SCH-I area to the respective hoist and return back the test weights to Switch Yard-II after completion the load test (necessary transport vehicle, crane & test weights will be supplied by TNPGCL at free of cost) | 5 | Operation | 30,800 ₹36,344 Lowest | 36,000 ₹42,480 |
Tender Value
Refer Docs
EMD Value
₹7,800
Closing Date
17 Mar 2026, 2:00 pmClosed
Chief Engineer/TTPS
O/o CE/TTPS
ECHP-I- Complete overhauling and load testing of 2 Nos. 15 Ton and 3 Nos. 10 Ton electrical wire rope hoists located at SCH-I
2026_EB_669791_1
CE/TTPS/SE/MI/229/2025-2026
Open Tender
Miscellaneous Works
Works
45 days
TTPS
Please refer Tender documents.
2 documents required · 2 mandatory
₹0
₹7,800
Yes
29 Jul 2026
3 Mar 2026
18 Mar 2026
3 Mar 2026
17 Mar 2026
3 Mar 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Charges for complete removing of 10 T /15 T capacity Electrical hoist from the mono rail by providing “A” frame / Derrick & chain block arrangement , loading and unloading and transporting to the workshop, erection of the Hoist after completion of the repair work , testing and commissioning etc. | 5 | Operation | 55 | ₹275 |
| 2 | Charges for draining the dirty oil from the gear box by opening the top cover by loosening the fixing bolt and nuts. Cleaning and checking all the gear wheel teeth, slagness of gear wheel and checking the tightness of all the gear. After the works completed the gear box pushed with new oil and refilling with new oil to the required quantity. Closing the gear box top cover by using fixing bolt and nut. | 5 | Operation | 55 | ₹275 |
| 3 | Charges for dismantling of rope drum, inspection, cleaning and applying compound & rewinding the steel wire rope and assembling the drum with hoist. | 5 | Operation | 55 | ₹275 |
| 4 | Charges for overhauling of hoist hook assembly, compensating pulleys and changing of hook pulley bearings. | 5 | Operation | 55 | ₹275 |
| 5 | Charges for cleaning of all electrical accessories such as motor contactors, push buttons, panel etc., and checking for proper operation | 5 | Operation | 55 | ₹275 |
| 6 | Charges for Fixing of Hoist system rotary geared type limit switch for lifting operation including supply of limit switches. | 5 | Operation | 55 | ₹275 |
| 7 | Charges for load testing of 10T/ 15T electrical hoists by using test weights with the presence of the competent authority and site Engineer incharge, loading, transporting and unloading of test weights from Switch Yard-II to SCH-I area to the respective hoist and return back the test weights to Switch Yard-II after completion the load test (necessary transport vehicle, crane & test weights will be supplied by TNPGCL at free of cost) | 5 | Operation | 55 | ₹275 |
stage.html
html • 0.04 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.27 MB
BOQ_804906.xls
BOQ • 0.25 MB
22925.pdf
PDF • 0.26 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].