| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.5 CrAccepted-AOC | ₹1.5 Cr | L1 | Accepted-AOC Rate quated with in estimate amount |
| 2 | L2₹1.5 Cr+₹1.3 L (0.89%)Rejected-AOC | ₹1.5 Cr+₹1.3 L (0.89%) | L2 | Rejected-AOC rate quated more than L1 amount |
| Sl No | Description | Qty | Unit | msd costructions L1 | E.CHANDRAN L2 |
|---|---|---|---|---|---|
| 1.00 | Charges for Chipping and roughening the surface using milling machine conveying the milled waste materials to atleast for 5 km distance including higher and running machine conveyance charges unloading at and objectionable place cleaning the milled surface as to avoid slippery including all other incidental and unforesceen items etc complete as per direction of the departmental officers. | 453 | M2 | 43.2 ₹19,569.74 Lowest | 44 ₹19,932.14 |
| 2.00 | Providing and laying, spreading and compacting graded stone aggregate to Wet mix macadam (WMM) specification including premixing the material with water at OMC in mechanical mix plant carriage to mixed material by tipper to site laying in uniform layers with paver in sub base / base course on well prepared surface and compacting with vibratory roller to achive the desired density complete as per clasue 406 of MORTH specifications. | 470 | M3 | 2,487.9 ₹11,69,323.68 Lowest | 2,487.9 ₹11,69,323.68 Lowest |
| 3.00 | Providing and laying Prime coat of 7 kgs/10 sqm over the WMM surface treated with primer using 7 kgs of bituminous Emulsion for 10 square meter area including cost of bituminous binder, including labour charges for applying the required quantity of bituminous binder as Prime coat manually etc., complete as per 502 of MORTH Specifications. | 6,028 | M2 | 86.6 ₹5,22,025.03 Lowest | 88 ₹5,30,464.23 |
| 4.00 | Providing and laying tack coat of 2.5 kgs/10 sqm over the WMM surface treated with binder using 2.5 kgs of bituminous Emulsion for 10 square meter area including cost of bituminous binder, including labour charges for applying the required quantity of bituminous binder as tack coat manually etc., complete as per 503 of MORTH Specifications | 6,028 | M2 | 20.09 ₹1,21,102.57 Lowest | 25 ₹1,50,700.07 |
| 5.00 | Providing and laying tack coat of 2kgs/10 sqm over the BT surface treated with binder using 2 kgs of bituminous Emulsion (RS) for 10square meter area including cost of bituminous binder, including labour charges for applying the required quantity of bituminous binder as tack coat manually etc., complete as per 503 of MORTH Specifications | 8,655 | M2 | 28.5 ₹2,46,667.63 Lowest | 31 ₹2,68,305.14 |
| 6.00 | Providing and laying 50mm consolidated thick Dense Bituminous Macadam using 0.24 cum of 26.50- 13.20mm, 0..25cum of 13.20-2.36mm and 0.23cum of 2.36mm & below and with 53.20 Kgs of VG30/ VG40 bitumen for premixing per 10sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, conveying the mix by tipper trucks to work site, spreading the mix to uniform thickness of 50mm with paver to the specified grades and cross sections and compacted by Vibratory / Pneumatic Roller to the required density etc., including labour for attending to paver at site etc., including hire charges and fuel charges for 20-30 t CMP with bitumen boiler, tipper trucks, Paver Finisher / 9m paver finisher, Vibratory / Pneumatic rollers and all other tools and plant required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clause 505 MORTH Rev-5 | 735 | M3 | 10,426 ₹76,63,155.35 Lowest | 10,520 ₹77,32,245.76 |
| 7.00 | Providing and laying bituminous concrte to 30/40 mm thick using 0.13 cum of 19.00 - 9,50 mm,0.17 cum of 9.50-2.36 mm and 0.26 cum of 2.36 and below with 47.28 kg of UG 30 bitumen and 3.02 kgs of waste plastic for pre mixing per 10 sqm inlcuding cost and conveuance of all matreials to CMB site,heating the bitumen and aggregate to recover temperature and mixing them in capacity conveying the mix by tipper trucks paver site,spreading the mix to uniform thickness 40 mm section and consolidated by 8-10 tonnes vibrating rollers to required density etc,inlcuding labour for attending to paver to site etc,including higher charges and fuel charges for 20-30 t CMP with bitumen boiler tippers trucks power finishers vibratory rollers and all other tools and plants recovered,inlcuding fuel and all other incidental charges etc, complete as per specification using CMP as per clause 507 of MORTH rev -5 | 441 | m3 | 10,982.5 ₹48,43,267.23 Lowest | 10,982.5 ₹48,43,267.23 Lowest |
| 8.00 | Add GST 18% | 1 | no | 26,25,320 ₹26,25,320 Lowest | 26,48,562.86 ₹26,48,562.86 |
Tender Value
₹1.7 Cr
EMD Value
₹1.7 L
Closing Date
23 Jan 2026, 3:00 pmClosed
The Commissioner Chengalpattu Municipality
The Commissioner Chengalpattu Municipality
Renewal for black top surface to Azhagesan Nagar 018016R137,Dr. Varadharajanar Street 018023R190,Gandhipan Vedachalam Street-1 018023R196,Gandhipan Vedachalam Street-2 018023R197,Gandhipan Vedachalam Cross Street-2 018023S044,Gandhipan Vedachalam Cr
2026_MAWS_642776_3
9730/2025/ss1
Open Tender
Civil Works
Works
Chengalpattu Municipality
Please refer Tender documents.
2 documents required · 2 mandatory
₹0
₹1.7 L
CHENGALPATTU MUNICIPALITY
17 Feb 2026
13 Jan 2026
23 Jan 2026
13 Jan 2026
23 Jan 2026
13 Jan 2026
14 Jan 2026
Charges for Chipping and roughening the surface using milling machine conveying the milled waste materials to atleast for 5 km distance including higher and running machine conveyance charges unloading at and objectionable place cleaning the milled surface as to avoid slippery including all other incidental and unforesceen items etc complete as per direction of the departmental officers.
Providing and laying, spreading and compacting graded stone aggregate to Wet mix macadam (WMM) specification including premixing the material with water at OMC in mechanical mix plant carriage to mixed material by tipper to site laying in uniform layers with paver in sub base / base course on well prepared surface and compacting with vibratory roller to achive the desired density complete as per clasue 406 of MORTH specifications.
Providing and laying Prime coat of 7 kgs/10 sqm over the WMM surface treated with primer using 7 kgs of bituminous Emulsion for 10 square meter area including cost of bituminous binder, including labour charges for applying the required quantity of bituminous binder as Prime coat manually etc., complete as per 502 of MORTH Specifications.
Providing and laying tack coat of 2.5 kgs/10 sqm over the WMM surface treated with binder using 2.5 kgs of bituminous Emulsion for 10 square meter area including cost of bituminous binder, including labour charges for applying the required quantity of bituminous binder as tack coat manually etc., complete as per 503 of MORTH Specifications
Providing and laying tack coat of 2kgs/10 sqm over the BT surface treated with binder using 2 kgs of bituminous Emulsion (RS) for 10square meter area including cost of bituminous binder, including labour charges for applying the required quantity of bituminous binder as tack coat manually etc., complete as per 503 of MORTH Specifications
Providing and laying 50mm consolidated thick Dense Bituminous Macadam using 0.24 cum of 26.50- 13.20mm, 0..25cum of 13.20-2.36mm and 0.23cum of 2.36mm & below and with 53.20 Kgs of VG30/ VG40 bitumen for premixing per 10sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, conveying the mix by tipper trucks to work site, spreading the mix to uniform thickness of 50mm with paver to the specified grades and cross sections and compacted by Vibratory / Pneumatic Roller to the required density etc., including labour for attending to paver at site etc., including hire charges and fuel charges for 20-30 t CMP with bitumen boiler, tipper trucks, Paver Finisher / 9m paver finisher, Vibratory / Pneumatic rollers and all other tools and plant required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clause 505 MORTH Rev-5
Providing and laying bituminous concrte to 30/40 mm thick using 0.13 cum of 19.00 - 9,50 mm,0.17 cum of 9.50-2.36 mm and 0.26 cum of 2.36 and below with 47.28 kg of UG 30 bitumen and 3.02 kgs of waste plastic for pre mixing per 10 sqm inlcuding cost and conveuance of all matreials to CMB site,heating the bitumen and aggregate to recover temperature and mixing them in capacity conveying the mix by tipper trucks paver site,spreading the mix to uniform thickness 40 mm section and consolidated by 8-10 tonnes vibrating rollers to required density etc,inlcuding labour for attending to paver to site etc,including higher charges and fuel charges for 20-30 t CMP with bitumen boiler tippers trucks power finishers vibratory rollers and all other tools and plants recovered,inlcuding fuel and all other incidental charges etc, complete as per specification using CMP as per clause 507 of MORTH rev -5
Add GST 18%
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.23 MB
bid.pdf
Tender Documents • 0.75 MB
BOQ_770217.xls
BOQ • 0.25 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .