Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹4.9 LAdmitted-Finance | ₹4.9 L | L1 | Admitted-Finance |
| 2 | L2₹5.1 LAdmitted-Finance | ₹5.1 L | L2 | Admitted-Finance |
| Sl No | Description | Qty | Unit | M/S PARVAIZ ENTERPRISES L1 | MS BISMILLAH ENTERPRISES L2 |
|---|---|---|---|---|---|
| 1.00 | Supply, Installation, Testing & Commissioning of 11/0.433kV, 3-phase, 63KVA Distribution Transformer with Bimetallic Terminal Connectors Energy Level-2, Aluminium wound, and with LV Cable Box having detachable Aluminium Gland plate. Transformer should have arrangement for vertical Take off | 1 | No.'s | 1,44,000 ₹1.4 L | 1,25,000 ₹1.3 L |
| 2.00 | Supply, Installation, Testing & commissioning of 9 Mtr. Long Pole (ST-410 SP33) | 4 | No.'s | 15,500 ₹62,000 | 18,500 ₹74,000 |
| 3.00 | Supply, Installation, Testing & commissioning of 8 Mtr. Long Pole (ST-410 SP15) | 10 | No.'s | 13,000 ₹1.3 L | 15,000 ₹1.5 L |
| 4.00 | Supply, Installation, Testing & commissioning of ACSR 0.05 Conductor (50 mm² ACSR Conductor) | 1 | Km.'s | 37,000 ₹37,000 | 37,000 ₹37,000 |
| 5.00 | Supply, Installation, Testing & commissioning of G I Channel/ Angle/ Flat iron for cross, braces of sizes including clamps and GI Nut Bolts with all accessories | 400 | Kgs | 100 ₹40,000 | 120 ₹48,000 |
| 6.00 | Supply, Installation, Testing & commissioning of Mucki clamps/LT Shackles with insulators | 40 | No.'s | 175 ₹7,000 | 260 ₹10,400 |
| 7.00 | Supply, Installation, Testing & commissioning of 11kV Polymeric composite Pin Insulator 12kV, 5kN, Lighting Impulse 75kV Positive and 80kV Negative, creepage distance 320mm | 20 | No.'s | 175 ₹3,500 | 160 ₹3,200 |
| 8.00 | Supply, Installation, Testing & commissioning of 11 kV Horn Gap Fuse Set 3 Phase 200A | 1 | Sets | 3,500 ₹3,500 | 3,000 ₹3,000 |
| 9.00 | Supply, Installation, Testing & commissioning of 11KV GO, AB Switch 3-Phase, 3-Pole, 200 Amp, Vertical Type | 1 | Sets | 10,000 ₹10,000 | 9,000 ₹9,000 |
| 10.00 | Supply, Installation, Testing & commissioning of Gapless Surge Arrestor,9 kV, 10 kA,LA with polymer housing, Stn. Type | 1 | Sets | 3,500 ₹3,500 | 2,800 ₹2,800 |
Tender Value
₹6.7 L
EMD Value
₹13,320
Closing Date
5 Feb 2026, 11:00 amClosed
XEN ED PULWAMA
OFFICE OF THE XEN ED PULWAMA
Creation of 63KVA Sub Station PHE Colony, Marval under MPLADS Grants for the year 2025-26
2026_PDD_301592_1
OM/PUL/52 of 2025-26 Dated 28-01-2026
Open Tender
Electrical Works
30 days
XEN ED PULWAMA
Please refer Tender documents.
2 documents required · 2 mandatory
₹500
Executive Engineer ED Pulwama
₹13,320
4 May 2026
28 Jan 2026
5 Feb 2026
28 Jan 2026
5 Feb 2026
28 Jan 2026
Supply, Installation, Testing & Commissioning of 11/0.433kV, 3-phase, 63KVA Distribution Transformer with Bimetallic Terminal Connectors Energy Level-2, Aluminium wound, and with LV Cable Box having detachable Aluminium Gland plate. Transformer should have arrangement for vertical Take off
Supply, Installation, Testing & commissioning of 9 Mtr. Long Pole (ST-410 SP33)
Supply, Installation, Testing & commissioning of 8 Mtr. Long Pole (ST-410 SP15)
Supply, Installation, Testing & commissioning of ACSR 0.05 Conductor (50 mm² ACSR Conductor)
Supply, Installation, Testing & commissioning of G I Channel/ Angle/ Flat iron for cross, braces of sizes including clamps and GI Nut Bolts with all accessories
Supply, Installation, Testing & commissioning of Mucki clamps/LT Shackles with insulators
Supply, Installation, Testing & commissioning of 11kV Polymeric composite Pin Insulator 12kV, 5kN, Lighting Impulse 75kV Positive and 80kV Negative, creepage distance 320mm
Supply, Installation, Testing & commissioning of 11 kV Horn Gap Fuse Set 3 Phase 200A
Supply, Installation, Testing & commissioning of 11KV GO, AB Switch 3-Phase, 3-Pole, 200 Amp, Vertical Type
Supply, Installation, Testing & commissioning of Gapless Surge Arrestor,9 kV, 10 kA,LA with polymer housing, Stn. Type
Supply, Installation, Testing & commissioning of 185 mm2 Single Phase Cable, 1.1K V Grade, PVC Insulated Al. Stranded Conductor FRLS type
Supply, Installation, Testing & commissioning of LT Fuse set of standard make & quality.
Supply, Installation, Testing & commissioning of Al-Thimbles
Earthing of substation --Excavation of earth pit of dia 650 mm & depth 3000 mm, installation of Earthing pipe of 40 mm Nominal bore & 4mm wall thickness & length 2.5 mtr long as Per IS 1239.GI Strip for neutral earthing of size 25 mm x 3 mm for connection of transformer body,G.O Set & lightening arrestor as per IS 2629/85, GI nuts & bolts,refilled with earth enhancement materials and earth Chamber made of brick masonary with RCC slab cover as per REC standards.
Earthing Complete by GI Pipe 40 mm 3 mtr long through GI Strip 25x3 mm as per REC Standards.
Providing of Painting of Poles Red Oxide as per standards
Providing of Painting of Poles Aluminium Paint as per standards (double coat)
Providing of Cement bottoming of poles 1:2:4 mix as per REC standards 0.48cum /pole
Providing of Cement bottoming of poles 1:2:4 mix as per REC standards 0.44cum /pole
Providing of Danger Plates with Clamps for 9 meter HT Poles as per REC standards.
computerized site plan of work's depicting complete details of works along with land marks on 12X18 inch good quality paper sheet
GEO tagged photographs of size not less than 8x6 inches on good quality photopaper (along with soft copy).
Please Enable Macros to View BoQ information
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 0.24 MB
SBD52.pdf
Tender Documents • 1.73 MB
DRAWINGS.pdf
Tender Documents • 15.02 MB
BOQ_978573.xls
BOQ • 0.29 MB
SpecificationsTransformerACSRPoles.pdf
Tender Documents • 2.36 MB
Download all tender documents and submit your bid