Tender Value
Refer Docs
EMD Value
₹11,500
Closing Date
3 Mar 2023, 2:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
SE EDCH ASHA NAGAR HARDOI
SE EDCH ASHA NAGAR HARDOI
230/EDC(H)/2022-23
2023_MVVNL_778398_1
230/EDC(H)/2022-23
Open Tender
Miscellaneous Works
Item Rate
90 days
HARDOI
Please refer Tender documents.
2 documents required · 2 mandatory
₹3,540
A/C No. 21342643946, IFSC Code IDIB000E504, India
₹11,500
Yes
22 Mar 2023
25 Feb 2023
3 Mar 2023
25 Feb 2023
3 Mar 2023
25 Feb 2023
Amount
Safe Loading carriage & unloading of following material from store centre to pit site/JE Dump store
Erection and installing of 33/11 KV, 5MVA transformer in a levelled position on the plinth at Behendar. The work includes shifting of transformer to the site of installation within the substation premises. Aseembling fixing and fitting of all accessories and fitting of transformer oil to the desire level and ensuring that there is no leakage. Providing & fixing Copper. L-piece 07 no. for transformer. All the jumpering & connection,packing& oil seal replacement are included in the scope of work with leakege arresting of tf. (All Required material, T&P, Accessories should be supplied by contractor.)
Erection and installing of 33/11 KV, 10MVA transformer in a levelled position on the plinth at Beniganj old . The work includes shifting of transformer to the site of installation within the substation premises. Aseembling fixing and fitting of all accessories and fitting of transformer oil to the desire level and ensuring that there is no leakage. Providing & fixing Copper. L-piece 07 no. for transformer. All the jumpering & connection,packing& oil seal replacement are included in the scope of work with leakege arresting of tf.(All Required material, T&P, Accessories should be supplied by contractor.)
Fabrication & erection of Cable stand as per RESSPO Norms. (All Required material, T&P, Accessories should be supplied by contractor.)
Fixing and connecting of all outgoing/incoming 11KV cables with all switchgares and taping with H.T. Tape, empire and PVC tape properly (strietly to the satisfaction of the site in-charge).(All Required material, T&P, Accessories should be supplied by contractor.)
Fixing and making bus bar connections in between all switchgears after cleaning and traping with H.T. Tape, empire tape and PVC tape properly. Providing and fixing of 6 mm thick Bakelite separators and plugging of all opening & holes with plastic compound-complete work including cost of all material strictly to the satisfaction of site in-charge. (All Required material, T&P, Accessories should be supplied by contractor.)
Shifting carefully & safety 11 KV , I/C & O/G switchgears from Baghauli S/S to Behendar S/S and to switchgear room in proper position and alignment and checking-complete work. (Only VCB supplied by Department & All Required material, T&P, Accessories should be supplied by contractor.)
Providing & fixing of connector & L pieces for CT, isolator & T/F which will be required etc. (All Required material, T&P, Accessories should be supplied by contractor.)
Jumpering with ACSR panther conductor of all equipments in swicth yard with P.G. clamps & proper size aluminium lugs. (All Required material, T&P, Accessories should be supplied by contractor.)
Hoisting of 11 KV cable on 11 switchgear & Cable Stand. (All Required material, T&P, Accessories should be supplied by contractor.)
High pressure testing of XLPE cable. Testing equipment will be arranged by the contractor. (All Required material, T&P, Accessories should be supplied by contractor.)
Carefully shifting of existing panels etc. (which will be required ) for making space in the control room as per instruction of site engineer. Due to installation of new panels including opening controll cable and after shifting reconnection properly with construction of base. (All materials provided by contractor which will be required as copper control cable for shifting. (All Required material, T&P, Accessories should be supplied by contractor.)
Opening and shifting of 11 KV cable from the existing 11 KV O/G VCB panel to new installed 11 KV O/G VCB panel with hoisting and connecting. (All materials provided by contractor which will be required for shifting as straight through and Indoor J/K, Testing Of Pannels)
Leveling and cleaning of proposed switchyard including cutting of plants with its roots and dump misc. items as per instruction of site engineer. (All Required material, T&P, Accessories should be supplied by contractor.)
Dismantling and Re-erection of retaining wall, fencing etc. (All Required material, T&P, Accessories should be supplied by contractor.)
Dismantling & safe shifting (Loading,unloading&carriage) of existing and working 33/11 KV 5 MVA T/F from Plinth at Beniganj old to Behendar S/S after opening Jumper and Cable connection as per instruction of site engineer. (All Required material, T&P, Accessories should be supplied by contractor.)
Dismantling & safe shifting (Loading,unloading&carriage) of existing and working 33/11 KV 10 MVA T/F from Plinth at Behendar to Beniganj old S/S after opening Jumper and Cable connection as per instruction of site engineer. (All Required material, T&P, Accessories should be supplied by contractor.)
Repairing of Plinth for Power Transformers. (All Required material, T&P, Accessories should be supplied by contractor.)
Safe loading , unloading & carriage of used/scrap material from S/S ( Behendar and Beniganj) to store centre Hardoi.
Maintenance and repairing of existing isolator set installed at behandar and beniganj substation
A.A. ENGINEERING CO.
NATIONAL CONTRACTOR & GENERAL ORDER SUPPLIER
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .