Loading…
Loading…
Tender Value
₹13.6 Cr
EMD Value
₹27.2 L
Closing Date
17 Aug 2026, 2:00 pm
Yes (up to 3 members)
No
Two Packet System
Normal Tender
No
Not Applicable
Lowest to Highest
90 days
Expenditure
Capital (Works)
BRIDGE
15 conditions · 4 needing a document upload
For works costing more than Rs.50 Lakhs:The tenderer must have minimum average annual contractual turnover of V/N or "V" whichever is less; where V = Advertised value of the tender in crores of Rupees. N = Number of years prescribed for completion of work for which bids have been invited. The average annual contractual turnover shall be calculated as an average of "total contractual payments" in the previous three financial years, as per the audited balance sheet. However, in case balance sheet of the previous year is yet to be prepared/ audited, the audited balance sheet of the fourth previous year shall be considered for calculating average annual contractual turnover. The tenderers shall submit requisite information as per Annexure-VIB, along with copies of Audited Balance Sheets duly certified by the Chartered Accountant/ Certificate from Chartered Accountant duly supported by Audited Balance Sheet. Non submission of the above,the offer will be summarily rejected.(Ref : Advance Correction Slip No.1 dt:14/07/2022 to IRSGCC- 2022 ).
Bid Capacity: The tender/technical bid will be evaluated based on bid capacity formula detailed as Annexure-VI
52 conditions · 9 needing a document upload
Whether required test certificates/samples, if any have been uploaded?
Tenderers are requested to ensure the uploading of mandatory documents under the relevant tabs as per check list and put(tick) mark wherever applicable as per CE/Works/Chennai letter No.W.496/Tender policy dt.03.07.2023. The check list is available under DOCUMENTS tab. The check list is only exhaustive. Tenderer should ensure that all the documents required as per relevant clauses are uploaded. The mere submission of documents mentioned in the check list alone will not qualify for the eligibility of the tender.
Multiple L-1 :- In case of more than one L-1 bidders, tender may be awarded to tenderer having higher bid capacity. In case bid capacity is also the same, tenderer having done more value of similar work in last three previous financial years and the current financial year up to the date of opening of tender may be selected for award. Railway reserves the right and may seek the above details within specified period, if not submitted by the tenderers along with the bid.
The contractor should ensure that the staff employed are physically fit, with a sound mind and of good character. To this effect, necessary police clearance certificate should be obtained from local police authorities before the contractor's staff are put into service. This will be in accordance with the Railway Board Letter No. 2020/Sec(CCB)/45/50/Misc Dt.03.02.2020. Refer Annexure I & II.
Advance Correction Slip No.11 to the Indian Railway Standard General Conditions of Contract (April 2022) has been incorporated and copy uploaded for reference.
Bidders are requested to submit the Performance Guarantee (PG) strictly in accordance with the new prescribed format and within the stipulated timeline to avoid any delay in processing. (Copy enclosed)
Maintenance period of four (4) years shall be stipulated for works involving construction of ROB/RUB/LHS, new Rail Bridges/ROR, and rebuilding of existing bridges, to ensure quality and standardization across Zonal Railways; whereas, for construction of quarters and other buildings, a maintenance period of up to three (3) years shall be applicable as per Dy. CVO/Engg letter No. VO/E/Sys.Imp dated 17/02/2026.
All the contracts on works/goods/services will be subject to the new GST act as applicable from time to time. Contractors have to register themselves with GST authorities and to furnish the GST registration number in order to process the bills from 01.07.2017
Please enter the percentage of local content in the material being offered. Please enter 0 for fully imported items, and 100 for fully indigenous items. The definition and calculation of local content shall be in accordance with the Make in India policy as incorporated in the tender conditions.
Deployment Of Qualified Engineers At Work Sites By The Contractor. The contractor shall also employ Qualified Graduate Engineer or Qualified Diploma Holder Engineer, based on value of contract, as may be prescribed by the Ministry of Railways through separate instructions from time to time.(As per RB ltr no.2012/CE-I/CT/O/20 dt:10.05.2013)
One qualified Graduate Engineer when the cost of the work is Rs. 200 lakhs and above.
One qualified Diploma holder Engineer when the cost of the work to be executed is more than Rs.25 lakhs but less than Rs.200 lakhs.
In case the contractor fails to employ the technical staff as aforesaid, he shall be liable to pay a an amount of Rs.40,000/ (Rupees Forty thousand) for each month or part thereof for the default incase of Graduate Engineer and Rs.25,000/- (Rupees Twenty five thousand) for each month or part thereof for the default in case of Diploma holder (Engineer)
I/WE also hereby agree to abide by the INDIAN RAILWAY GENERAL CONDITIONS OF CONTRACT- April 2022, with all correction slips up to date and to carry out the works accordingly.
Until a formal agreement is prepared and executed, acceptance of this tender shall constitute a binding contract between us subject to modifications, as may be mutually agreed to between us and indicated in the letter of acceptance of my/our offer for this work.
I/We also agree to keep this tender open for acceptance for a period of 90 days from the date fixed for opening the same
I/We offer to do the work for DRM/W/O/SA, at the rates quoted in the attached schedule and hereby bind myself/ourselves to complete the work in all respects within the period of completion stipulated in the tender document, from the date of issue of letter of acceptance of the tender. The Bid security shall stand forfeited without prejudice to any other right or remedies in case my/our Tender is accepted and if : (a) I/We do not execute the contract documents as stipulated in performance guarantee clause of GCC as detailed in general instructions. (b) I/We do not commence the work within seven days after receipt of orders to that effect.
I/We hereby Confirm that the rates, rebates and/or other financial terms, if any, quoted by us in the relevant fields of the Financial Bid page will only be the ruling terms for deciding the inter-se ranking, and any such condition having financial repercussions, if quoted by us anywhere else including attached documents shall not be considered for deciding inter-se ranking
However, Railways shall have the right to incorporate any such condition quoted by us, in the contract, at their discretion, if contract is placed on us.
I/We have read the various conditions attached/ referred to in this tender document, and agree to abide by the said conditions.
A tenderer claiming credentials as an individual for their share in a partnership firm, has to submit both the deeds of (i) partnership deed, showing % of their share and (ii) retirement deed from the partnership firm(or) deed showing the closure of business operations of the partnership firm, as applicable. Failing to submit the above deeds, the offer of the tenderer will be summarily rejected.
The tenderer shall clearly specify whether the tender is submitted on his Own (Proprietary Firm) or on behalf of a Partnership Firm / Company / Joint Venture (JV) I Registered Society/ Registered Trust / Hindu Undivided Family( HUF) / Limited Liability Partnership (LLP) etc. , The tenderer(s) shall enclose the attested copies of the requisite documents (including Power of Attorney, if opted) for constitution of their concern as per Cl.14 of GCC-Part-l and as per a)Clause 17 of GCC - Part-1, for JV b)Clause 18 of GCC - Part-I, for Partnership Firm.
Copies of the following documents are to be uploaded: (i) Details such as Name of the tenderer/ Contractor, Validity of DSC, Complete address with pin code, contact number (ii) Copy of PAN card (iii) Copy of GSTIN card.
A copy of NEFT form duly filled in the details as necessary to be uploaded. (The Tenderer/Contractor not having NEFT form may down load the empty NEFT form available in Document site)
Submission of physically signed Annexure-V by the tenderer is discontinued vide Rly Bd letter dt:14/05/2024 (Uploaded)
Submission of Annexure-V(A) under Document Verification Certificate. In case of other than company/Proprietary firm, Annexure-V(A) shall also be submitted by the each member of a Partnership Firm/ Joint Venture (JV) /Hindu Undivided Family (HUF) / Limited Liability Partnership (LLP) etc., as the case my be. Non-submission of the above Certificate(s) by the bidder shall result in summarily rejection of his/their bid
SW-I-Rebuilding of RUB no:378 at km -406/300-400 as 1x7.00x5.50m RCC box in ED-PTJ section. SW-II - Rebuilding of RUB no:361 at km -395/100-200 as 1x7.00x5.50m RCC box in ED-PTJ section SW-III - SA-DIVN Protecting of minor RUB against road users by providing height gauge in SSE/W/ED jurisdiction (20 numbers).
SA-OT-08-2026-06
SA-OT-08-2026-06
Open
Works - General
12 Months
Salem, Tamil Nadu
₹0
₹27.2 L
25 Jul 2026
25 Jul 2026
3 Aug 2026
157 items across 10 schedules · ₹8,66,51,246.31 total
| # | Description | Unit | Qty | Rate | Amount |
|---|---|---|---|---|---|
| 1 | All kinds of soil | cum | 1041.24 | 177.5 | 1,84,820.1 |
| 2 | Ordinary rock | cum | 1309.75 | 498.9 | 6,53,434.28 |
| 3 | Hard rock (requiring blasting) | cum | 7 | 874.4 | 6,120.8 |
| 4 | Hard rock (blasting prohibited) | cum | 323.44 | 1,432.95 | 4,63,473.35 |
| 5 | Ordinary rock | cum | 150 | 632.95 | 94,942.5 |
| 6 | Hard rock (requiring blasting) | cum | 50 | 1,049.8 | 52,490 |
| 7 | Hard rock (blasting prohibited) | cum | 30 | 1,523.05 | 45,691.5 |
| 8 | 1:1 1/2:3 (1 Cement: 1 1/2 coarse sand (zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources) | cum | 54.44 | 8,340.85 | 4,54,075.87 |
| 9 | 1:3:6 (1 Cement : 3 coarse sand (zone-III) derived from natural sources : 6 graded stone aggregate 20 mm nominal size derived from natural sources) | cum | 13 | 7,294.7 | 94,831.1 |
| 10 | 1:3:6 (1 Cement : 3 coarse sand (zone-III) derived from natural sources : 6 graded stone aggregate 40 mm nominal size derived from natural sources) | cum | 4 | 7,178.75 | 28,715 |
| 11 | Foundations, footings, bases for columns | Sqm | 50 | 392.15 | 19,607.5 |
| 12 | Retaining walls, return walls, walls (any thickness) including attached pilasters, buttresses, plinth and string courses fillets, kerbs and steps etc. | Sqm | 67 | 842.5 | 56,447.5 |
| 13 | Concrete of M20 grade with minimum cement content of 270 kg /cum | cum | 16 | 9,212.6 | 1,47,401.6 |
| 14 | Foundations, footings, bases of columns, etc. for mass concrete | Sqm | 206.02 | 392.15 | 80,790.74 |
| 15 | Walls (any thickness) including attached pilasters, buttresses, plinth and string courses etc. | Sqm | 552.96 | 842.5 | 4,65,868.8 |
| 16 | Concrete of M30 grade with minimum cement content of 350 kg /cum | cum | 97.06 | 9,655.7 | 9,37,182.24 |
| 17 | Concrete of M25 grade with minimum cement content of 330 kg /cum | cum | 97.61 | 9,860.4 | 9,62,473.64 |
| 18 | Concrete of M30 grade with minimum cement content of 350 kg /cum | cum | 57 | 10,011.35 | 5,70,646.95 |
| 19 | Cement mortar 1:6 (1 cement : 6 coarse sand) | cum | 10 | 7,132.25 | 71,322.5 |
| 20 | Cement mortar 1:6 (1 cement : 6 coarse sand) | cum | 13 | 9,105.95 | 1,18,377.35 |
| 21 | Structural steel work riveted, bolted or welded in built up sections, trusses and framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer all complete. | Kg | 6407 | 133.7 | 8,56,615.9 |
| 22 | Using M.S. angels 40x40x6 mm for diagonal braces | Sqm | 3 | 5,804.35 | 17,413.05 |
| 23 | Providing and fixing mild steel round holding down bolts with nuts and washer plates complete. | Kg | 215 | 97.2 | 20,898 |
| 24 | In gratings, frames, guard bar, ladder, railings, brackets, gates and similar works | Kg | 3926 | 172.6 | 6,77,627.6 |
| 25 | 1:6 (1 cement: 6 fine sand) | Sqm | 216 | 333.35 | 72,003.6 |
| 26 | New work (Two or more coats applied @ 3.84 kg/10 sqm) | Sqm | 2000 | 116.9 | 2,33,800 |
| 27 | New work (Two or more coat applied @ 1.67 ltr/10 sqm over and including priming coat of exterior primer applied @ 0.90 litre/10 sqm) | Sqm | 120 | 160.6 | 19,272 |
| 28 | With ready mixed red oxide zinc chromate primer of approved brand and manufacture on steel galvanised iron/ steel works | Sqm | 100 | 67.4 | 6,740 |
| 29 | Two or more coats on new work | Sqm | 100 | 155.9 | 15,590 |
| 30 | Two or more coats on new work over an under coat of suitable shade with ordinary paint of approved brand and manufacture | Sqm | 7 | 226.25 | 1,583.75 |
| 31 | Nominal concrete 1:3:6 or richer mix (including equivalent design mix) | cum | 22.5 | 2,434.25 | 54,770.63 |
| 32 | Demolishing R.C.C. work manually/ by mechanical means including stacking of steel bars and disposal of unserviceable material within 50 metres lead as per direction of Engineer - in- charge. | cum | 123.67 | 3,551.25 | 4,39,183.09 |
| 33 | In cement mortar | cum | 42.84 | 2,458.95 | 1,05,341.42 |
| 34 | Water bound macadam road | Sqm | 46.5 | 217.45 | 10,111.43 |
| 35 | bituminous road | Sqm | 46.5 | 428.5 | 19,925.25 |
| 36 | Cement concrete manufactured in automatic batching plant (RMC plant) including transportation to site in transit mixer | cum | 5 | 11,098.45 | 55,492.25 |
| 37 | Providing and laying C.C. pavement of mix M-25 with ready mixed concrete from batching plant. The ready mixed concrete shall be laid and finished with screed board vibrator , vacuum dewatering process and finally finished by floating, brooming with wire brush etc. complete as per specifications and directions of Engineer-in- charge. (The panel shuttering work shall be paid for separately). | cum | 45.5 | 9,823.8 | 4,46,982.9 |
| 38 | Deduct for using of M-20 grade concrete instead of M-25 grade concrete in C.C. pavement. | cum | 45.5 | -203.8 | -9,272.9 |
| 39 | Taking out existing kerb stones of all types from footpath/ central verge, including removal of mortar etc., disposal of unserviceable material to the dumping ground, for which payment shall be made separately and stacking of serviceable material within 50 metre lead as per direction of Engineer-in-Charge. | Metre | 50.01 | 39.35 | 1,967.89 |
| Schedule total | ₹85,54,759.18 | ||||
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
HTML
nit.pdf
NIT
ANNEXUREIIIFORPOLICEVERIFICATION.pdf
ATTACHMENT
SPECIFICATIONFORBUILDINGSBRIDGEWORKSDEC2025.pdf
ATTACHMENT
TrackStandardDocument20122022.pdf
ATTACHMENT
RBCECEICTImplementationofContractoremb.pdf
ATTACHMENT
ANNEXUREVVAVIAVIB.pdf
ATTACHMENT
GCCApril2022NEW.pdf
ATTACHMENT
INSTRUCTIONSTOTHETENDERER.pdf
ATTACHMENT
ProcedureforLetterofCredit.pdf
ATTACHMENT
Workonhanddetails.pdf
ATTACHMENT
SafetyprecautionstobeadoptedwhileworkinginElectrifiedArea.pdf
ATTACHMENT
Splconditionsofcontractformovementofvehicle.pdf
ATTACHMENT
ACS1to10.pdf
ATTACHMENT
NewFormatofBG.pdf
ATTACHMENT
ACS112026_compressed.pdf
ATTACHMENT
SCCOFLUS.pdf
ATTACHMENT
CheckListandNEFTform.pdf
ATTACHMENT
RlyBdletterClarificationofAnnexureV.pdf
ATTACHMENT
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].