Tender Value
₹20.3 L
EMD Value
₹40,680
Closing Date
7 Oct 2026, 3:00 pmClosed
DHARAM VIR
DIV Karnal
Construction and Rising of manholes, Providing and Laying of Sewerage line
2026_HBC_551852_1
20264492DF16 BC2C 434F 87ED 4E9D0455902A240HSV
Open Tender
Civil Works
Works
120 days
Kaithal
2 documents required · 2 mandatory
₹500
₹40,680
Yes
1 Oct 2026
1 Oct 2026
8 Oct 2026
1 Oct 2026
7 Oct 2026
1 Oct 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | [11.5.1]12 mm cement plaster of mix : 1. 1:2 (1 cement: 2 fine sand) [Through Rate] | 179.14 | Sqm | 139 | ₹24,900.46 |
| 2 | [11.52]Cement rendering on plaster 1 mm thick [Through Rate] | 201.13 | Sqm | 28 | ₹5,631.64 |
| 3 | [17.6]Construction of Embankment with Material obtained from Borrow pits NA Construction of Embankment CBR 8% (for new road/ raising/ berms/ etc.) with approved material obtained from borrow pits, including compensation of earth with all lead and lift transporting to site, spreading, grading to required slope and compacting to meet requirement of table 300-2, as per technical clause 305 of MORT&H specifications. [Through Rate] | 216 | cum | 184 | ₹39,744 |
| 4 | [21.43]Extra over the rate laid down in this schedule for cement concrete work more making and finishing benching and complicated floor work in manholes, including formation of channels and bulldozing and smooth finishing the surface accurately to template. [Through Rate] | 49.8 | Per sqm benching and flooring surface measures horizontaly | 160 | ₹7,968 |
| 5 | [21.93.1]Providing and fixing SFRC MANHOLE COVERS AND FRAMES MARKED WITH IS: 12592 including setting the same to correct lines and levels in 1:3 cement sand mortar over manhole including carriage loading unloading stacking handling re-handling etc. complete in all respects to the satisfaction to the Engineer-in-charge. 1. Type:- Extra Heavy Duty Set (EHD-35) 560MM Clear Opening [Through Rate] | 120 | Each | 1,155 | ₹1,38,600 |
| 6 | [22.163.3]Providing, laying and jointing glazed stoneware pipes class SP-1 with stiff mixture of cement mortar in the proportion of 1:1 (1 cement : 1 fine sand) including testing of joints etc. complete : 3. 200 mm diameter [Through Rate] | 675 | Metre | 450 | ₹3,03,750 |
| 7 | [4.14.1]Earth work in excavation by mechanical means (Hydraulic excavator) / manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan), including dressing of sides and ramming of bottoms, lift up to 1.5 m, including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. 1. All kinds of soil. [Through Rate] | 985.57 | cum | 83 | ₹81,802.31 |
| 8 | [6.1.2]Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work below plinth level and up to Floor IV level: 2. 1:2:4 (1 cement : 2 coarse sand (zone-III) : 4 graded stone aggregate 20 mm nominal size) [Through Rate] | 58.7 | cum | 3,476 | ₹2,04,041.2 |
| 9 | [6.1.6]Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work below plinth level and up to Floor IV level: 6. 1:4:8 (1 Cement : 4 coarse sand (zone-III) : 8 graded stone aggregate 40 mm nominal size) [Through Rate] | 54.51 | cum | 2,442 | ₹1,33,113.42 |
| 10 | [6.16]Reinforced cement concrete work in beams, suspended floors, roofs having slope up to 15° landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases above plinth level up to floor four level, excluding the cost of centering, shuttering, finishing and reinforcement with 1:1.5:3 (1 cement : 1.5 coarse sand(zone-III) : 3 graded stone aggregate 20 mm nominal size). [Through Rate] | 46.96 | cum | 6,113 | ₹2,87,066.48 |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.90 MB
BOQ_631679.xls
BOQ • 0.34 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .