Tender Value
₹1.9 Cr
EMD Value
₹2.9 L
Closing Date
6 Jul 2026, 9:30 pm
Similar tender results from the same govt authority in the past 3 years.
Hubli Electricity Supply Company Limited
Replacement of existing 2 X 5MVA by 2 X 8 MVA Power Transformer at 33/11 KV Sub-station Balekundri in Belagavi Taluk. Belagavi District on Total turnkey basis
308341
HESCOM/2026-27/EL/WORK_INDENT1226
Open
Electrical
HESCOM Superintending Engineer (PMC)Corporate Office Hubli
20 documents required · 20 mandatory
The bidder should have executed work of installation and commissioning of minimum of Two No. 5MVA and above higher capacity power transformers of 33/11KV and above voltage class with associated switchgears and ODS on Total Turnkey or Partial turnkey or labour Contract basis in the last five financial years (i.e., ,2020-21 2021-22, 2022-23, 2023-24 & 2024-25) on Total Turnkey/Partial Turnkey Basis/ Labour contract basis /self-execution basis in any State/ Central Govt. Distribution Companies / PSUs.Such works shall be in successful operation for a period of at least 1(One) year as on date of submission of bid.As a proof of documentary evidence Award copies and work completion certificates duly mentioning date of work completion and Executed cost issued by the competent authority not below the rank of Executive Engineer (Ele) of any State/Central Govt. Distribution Companies / PSUs shall be uploaded. The Experience certificate shall be submitted as per Annexure-IV.Note: Please note that the date of issuance of the work completion or performance certificates must be at least one year after the actual date of work completion.
The Bidder should have achieved in at least Two financial year, a minimum financial turnover of not less than Two Times the amount put to tender in the last five financial years (i.e., ,2020-21 2021-22, 2022-23, 2023-24 & 2024-25).The bidder shall upload the downloaded Form GSTR-9/9C, 3CA/3CB & 3CD from the portal along with Copies of Annual turnover certificate and audited balance sheet of profit and loss account duly mentioning the UDIN No duly certified by Chartered Accountant as applicable.Documents without UDIN No, GSTR-9/9C, 3CA/3CB & 3CD downloaded from portal are liable for rejection.Note: Updated to the FY in which the tenders are invited. Financial turnover of previous years shall be given a weight of 10% (say) per year to bring them to the price level of the FY in which the tenders are invited.
The cash at bank, term deposits and availability of fund based credit facilities shall not be less than Rs. 57.36 Lakhs (30% of the amount put to tender) which shall be supported by a certificate issued by Nationalized/ scheduled .commercial Bank as per the Annexure format attached shall be uploaded .If the Tenderer has banking with more than one Bank, then the available liquid assets mentioned above on a particular date i.e., as on date of bid submission or at a later date before the last date for bid submission of tender shall be the same date for all the banks. The said Credit Facility Certificate should possess the name of the Firm and tender Indent number and the credit facility to be issued in the name of Superintending Engineer (Ele),PMC, Corporate Office,HESCOM, Navanagar, Hubli. The credit facility certificate should be in the Format Annexed to this bid.ANNEXURE. The conditional credit certificates are liable for rejection
The bidder should have Satisfactorily completed (at least 90% of the contract value), as prime a contractor, at least one contract involving work of installation and commissioning of 5MVA and above higher capacity power transformers 33/11KV and above voltage class of value not less than Rs. 95.60 Lakhs (50% of the amount put to Tender) in any State/Central Govt./ Distribution Companies/PSUs in the last Five Financial Years (i.e., ,2020-21 2021-22, 2022-23, 2023-24 & 2024-25)..As a proof of documentary evidence Award copies and work completion/Performance certificates duly mentioning date of work completion and Executed cost issued by the competent authority not below the rank of Executive Engineer (Ele) of any State/Central Govt. Distribution Companies / PSUs shall be uploaded. The Experience certificate shall be submitted as per Annexure-IV. Note: Please note that, Award cost and Executed cost must be mentioned in the work completion/Performance certificates.Note- Updated to the FY in which the tenders are invited. The value of the completed works shall be given a weight of 10% per year to bring them to the price level of the FY in which the tenders are invited.
The bidder shall be a sole proprietorship firm or a partnership firm or a company incorporated under companies Act 1956/2013. Copy of the Certificate of Incorporation in case of Registered Company/ Partnership deed in case of Partnership Firm/GST or PAN registration in case proprietor ship firm is to be uploaded.
The bidder should possess valid Class-I / Super grade Electrical Contractor license issued by the Electrical Inspectorate, Govt. of Karnataka. The validity of the license should be in force at the time of submission of Bids. The bidder should possess valid Class-I / Super grade Electrical Contractor license issued by the Electrical Inspectorate, Govt. of Karnataka. The validity of the license should be in force at the time of submission of Bids.(Note: Firm name in the license as well as all the statutory documents should be same otherwise bid is liable for rejection).Scanned original copy of the Class-1 / Super grade Electrical Contractors License issued by Electrical Inspectorate, Government of Karnataka is to be uploaded by the bidder.
The bidder should upload original scanned copy of ESI issued by the respective competent authorities of the concerned department.
The bidder should upload original scanned copy of EPF Reg. No issued by the respective competent authorities of the concerned department
The bidder should upload original scanned copy of Pan No issued by the respective competent authorities of the concerned department.
The bidder should upload original scanned copy of GST No. issued by the respective competent authorities of the concerned department.
The bidder should possess valid original scanned copy of Registration Certificate of Establishment FORM C (Labour Reg.) issued by Department of Labour, Government of Karnataka. The bidder should upload original scanned copy of Registration Certificate of Establishment FORM C (Labour Reg.) issued by Department of Labour, Government of Karnataka
The bidder should not have been Black-Listed by ESCOMs/ KPTCL/ any other Government Distribution/ Transmission utilities including PSUs as on date of bid submission. Self-declaration for the same shall be uploaded (Annexure-I).
The bidder should not have been defaulted & Terminated due to non-performance in execution of works against the order placed by ESCOMs/KPTCL/any other Government Distribution/Transmission utilities including PSUs as on date of bid submission. Self-declaration for the same shall be uploaded (Annexure-II)
The bidder should provide detailed information on any litigation or arbitration arising out of contracts completed or under execution by it over the last five years with /KPTCL/ESCOMS. A history of awards involving litigations against the bidder or any part may result in rejection of bid. Self-declaration for the same shall be uploaded (Annexure-III)
Tender Capacity: The bidder should upload available tender capacity calculated in the prescribed format through e-procurement portal within due date of submission of bids. The available tender capacity shall be more than the total tender value.
Pre Survey: The bidder at his own responsibility must visit and examine the site of works & its surroundings and obtain all information that may be necessary for participating in the tender. The cost of the visiting/survey of the proposed works shall be at the bidders own expenses.The site inspection survey certificate of the proposed works issued by the concerned Executive Engineer (Ele).33KV S&L Division, HESCOM should be obtained by the bidder and shall be uploaded
The bidder from Nations sharing Border with India should upload the certificate issued by GOI.OR Self-declaration for not from Nations sharing Border with India.Registration certificate issued by the competent authority shall be uploaded. OR If not Self-declaration in the prescribed format as per Annexure-VII shall be uploaded.The self-declaration shall clearly indicate the tender enquiry number & date on which declaration is done.
₹4,790
₹2.9 L
20 Jun 2026
20 Jun 2026
7 Jul 2026
29 Jun 2026
29 Jun 2026
Tender Capacity Format
Details of work Executed during last 05 years ( To asses the value of A)
Sl No Year Work Executed Other related Electrical Works if any Cost of executed work in Rs Lakhs
New substations / Augmentation in Nos HT line in Rkms(11KV & above) DTC in Nos
Details of existing commitments and on-going works to be completed during next '9 months ( To asses the value of B) Attached in the next sheet
SL No Details of On Going works Award amount Rs in Lakhs Amount of work to be completed during next "9 months" Rs in Lakhs Completion period as per award Completion period remaining
Tender Capacity Formula= A*N*1.5-B
Where 'N'=13months of completion period for above subject work
Seal and signature of the Bidder
A= Maximum value of Distribution network work executed in any one year during the last 5 years i.e 2020-21,2021-22 ,2022-23,2023-24,2024-25 ( UP dated to __________________ price level) taking into account the completed as well as works in progress
N= Number of years/months prescribed for completion of the works for which Tenders are invited
B= Value,at________price level, of existing commitments and on-going works to be completed during the 'N'
Note: 1) The available tender capacity shall be more than the total tender value 2) Documentary Proof in support of value ‘A’, the Total value of works executed and payments received annually in the last 5 years shall be uploaded in the form of certificates issued by Chartered Accountant. In case if the same is not uploaded, then the maximum value of annual payments received towards the works executed which is indicated in the audited balance sheet in any one year during the last five years will be considered.
Tender Capacity Format
Details of existing commitments and on-going works to be completed during next "9 months ( To asses the value of B)
SL No Details of On Going works Award amount Rs in Lakhs Amount of work to be completed during next "9 months" Rs in Lakhs Completion period as per award Completion period remaining
Where 'N'= 13 months of completion period for above subject work
Note: The statement showing the value of existing commitments and ongoing works as well as the stipulated period of completion remaining for each of the works listed shall be countersigned by the Employer in charge, not below the rank of Executive Engineer or equivalent.( Note: L-1 in any of the recently called tender amount is also be considered as value of B along with the above)
Seal and signature of the Executive Engineer(Ele)
HUBLI ELECTRICITY SUPPLY COMPANY LIMITED
Self-Declaration statement of Bidder/Contractor for works Done…as on date of Bid submission.
Note: Please fill all required data and upload the signed copy in e-procurrement portal.
Bid Indent No: HESCOM/2026-27/EL/WORK_INDENT1226 Format-I
Work done certificate details as per QR.
Sl.No. Year of Completion Name of the Department Work Done Certificate No.& Date. Work Done Certificate issued by (Executive Engineer, Superintending Engineer .,.etc.,) Station voltage Class (220kV, 110kV, 66kV, 33kV) Station Capacity (MVA) 33 KV Line in R.Kms 33KV ROC in R.Kms 11 KV & above in R.Kms Others Cost of the work/project Rs.in Lakhs
Note:Works completed during the period from (i.e., ,2020-21 2021-22, 2022-23, 2023-24 & 2024-25) shall only be furnished, others will not be accepted.
I/We hereby declare that I/We had carried out above works and completed in all respects and are in successful operation for the last 1 (One) year i.e.,as on date of Bid submission. Further notice for defects in executed works is not received from concerned Department/recieved and same have been attended within the time. Any information, if found to be incorrect, wrong, misleading or misrepresenting , I/We am/are aware that I/We may be held liable for it.
HUBLI ELECTRICITY SUPPLY COMPANY LIMITED
Estimate for Replacement of existing 2 X 5MVA by 2 X 8 MVA Power Transformer at 33/11 KV Sub-station Balekundri in Belagavi Taluk. Belagavi District on Total turnkey basis.
Sl. No Particulars Material Labour Civil Total
1 Materials cost (Exclusive of GST) 15553688.33 15553688.33
2 Labour charges+ Decommissioning (Exclusive of GST) 356076.56 356076.56
3 Civil Engineering Charges (Exclusive of GST) 24285.00 24285.00 2.806226956
5 Area Specific Loading @ 5% on labour charges 0 0 0.00 0.00
Contractors Profit @ 10% on Sl No. Sl No. 4 & 5 1555368.83 35607.66 2428.50 1593404.99
% age of tender compenents included 862.54 236.00
Executive Engineer (EL), Superintending Enginner (El),
Projects - 1 , HESCOM, Hubli PMC, HESCOM, Hubli
HUBLI ELECTRICITY SUPPLY COMPANY LIMITED
Estimate for Replacement of existing 2 X 5MVA by 2 X 8 MVA Power Transformer at 33/11 KV Sub-station Balekundri in Belagavi Taluk. Belagavi District on Total turnkey basis.
PART-A (Material portion)
Sl. No. Particulars Unit Qty Rate Amout in Rs.
A.1 Power Transformers:
a) Power Transformer: 33/11KV, 8 MVA, DELT/STAR, DY 11, 3Ph, 50Hz,Core type winding with OLTC, RTTC panel etc., complete filled with Transil Oil and 10% spare Oil in Non Returnable Drums. (As per ESCOMs SR 2025-26, Page No:81 of 33KV system SL No:2.) Nos 2 7449292.00 14898584.00
B a) 11kV NCTs 600-300/1-1-1A (for PCVCBs upto 10 MVA Transformer) (As per ESCOM's CSR- 2025-26 33KV Material. page No- 81 SL.No-14, Item No-2.10) No's 2 66582 133164.00
C a) Mounting Structures:11KV NCT 2 No. 0.146x 2 =0.292 t ( (As per KPTCL SR- 2025-26, No- 02, SL.No-16) ii) (The weight of structure is 0.240t X2 Nos=480t) t 0.292 106667 31146.67
b) Bolts & Nuts for all Station Mounting Structures, such as, a.)11KV NCT(0.011x 8 No =0.088t) (Asper KPTCL SR 2023-24, Page No-247 Sl.NO:II, Item.No:D(viii), t 0.088 118983 10470.53
C Conductors 0.00
a) Coyote ACSR (26/2.54 mm Al + 7/1.90 mm St), Std Wt: 521 Kg/KM As per ESCOM's CSR- 2025-26 33KV page No- SL.No- Item No-22.8)(Extracted from KPTCL SR) Km 0.050 135537 6776.85
D Control Cable with Accessories: (With glands/lugs/ferruels) 0.00
a) 4 core 2.5 Sq.mm As per KPTCL SR-2025-26 No- 10, SL.No-176) Kms. 0.100 149167 14916.67 feederwise
b) 10 Core 2.5 Sq.mm As per KPTCL SR- 2025-26, No- 10, SL.No-179) Kms. 0.120 340833 40900.00
11kV, 3X400 Sqmm Core, XLPE HTUG Cable (ROUND Armoured Cable) 0.00
b) 11 kV, 3x240Sqmm Core, XPLE HTUG Cable with pressure extruded inner sheeth, ROUND WIRE ARMOURED as per IS-7098 (Part-2) Armouring wires dia and Resistivity as per IS-3975 ( As per ESCOM's CSR- 2025-26 33KV Material. page No- 128 SL.No-1) Kms. 0.080 1948466 155877.28
g) 11kV Jointing and Cable Termination Kits 0.00
j) Heat Shrinkable Outdoor Type Cable Termination Kit for XLPE Cable 3X240 Sqmm (As per ESCOMs SR- 2025-26, No- 32, SL.No-425) Set 2 4659 9318.00
k) Heat Shrinkable Indoor Type Cable Termination Kit for XLPE Cable 3X240 Sqmm (As per ESCOMs SR- 2025-26, No- 33, SL.No-428) Set 2 4110 8220.00
A.7 33 KV Isolators : 0.00
2) 11KV 400A Special Roaster switch with H frame for mounting Structure. ( As per ESCOM's CSR- 2025-26. page No- 17 SL.No-220 Item No-24.09) 0.00
a) 11KV 400A Special Roaster switch with H frame for mounting Structure.(As per ESCOM's SR- 2023-24, SL.No-174, Item No-24.09 ) ,Material Code-304204 RS-14956.00 Set 1 13295 13295.00
A.14 11 KV D.P.Structures: 0.00
a) 9 Mtr. Long, 150 kg RCC pole for 11KV ODS.(Asper ESCOM CSR2025-26 11 KV System, Page No.: 87 , Sl.No:2,Item.No:1.02, ) Nos 2 7345.00 14690.00
a) D.P. Structures with hardware consisting of double power X-arms, horizonontal cross brace, cross braces, back cleat, strain plate, bolt & nuts, painted with two coats of metal primer and aluminium paint, etc as per drawing. ( As per ESCOM's CSR- 2025-26. page No- 17, SL.No-225 Item No-26.02) Set 1 7374 7374.00
E Insulators & Hardware materials: 0.00
a) Pad clamp for Coyote ACSR As per ESCOM's CSR- 2025-26. page No- 7 SL.No-77 Item No-10.09 Nos 18 734 13212.00
b) NCT Pad Clamp As per KPTCL SR- 2025-26, No- 16, SL.No-327) Nos 4 849 3396.67
c) Terminal Connector Clamps Suitable for 36 kV class bushing to suit Coyote / Lynx conductor for HV Bushings of Power Transformers (Asper KPTCL SR-2023-24, Page No 135, Sl.No-E Item No-viii HSN Code:8536 Total Rs =512) Nos 6 427 2560.00
d) Terminal Connector Clamps Suitable for 12.1 kV class bushing to suit Drake conductor for Bushings of Power Transformers (As per KPTCL SR-2023-24, Page No 135, Sl.No.2E Item No-ix HSN Code:8536 Total Rs.1113/-) Nos 8 928 7420.00
a) GI Pipe, 150 mm Dia for drain crossing, cable raising etc.,(( As per ESCOM's CSR- 2025-26 33KV Material. page No- 128 SL.No-9) Mtr 20 1532 30640.00
F Ground Mat & Earthing : 0.00
a) Grounding of equipment by providing Cast iron pipe of 100 mm ID 13 mm thickness, 2.75 metre long with 2 part clamp out of G.I. Flat 50 X 6 mm continuously welded alround the pipe using cast iron welding electrodes as per drawing including the cost of excavation (All materials to be supplied by the contractor) (As per KPTCL SR-2023-24, Page No:115, Sl.No-6 Item No:c Material Rs-12792+3491 Labour Set 8 13569 108553.33
b) Supplying & providing 450 mm dia 450 mm height 1.5" to 2" thick hume pipe collar (non pressure type) for earth pits including all lead and lifts etc.,.(As per KPTCL SR-2023-24, Page No:124, Sl.No-26 Item No:i Material Rs-1499.00 Each 6 1249 7495.00
c) Grounding of equipment with 50X6 mm GI flat & connecting equipment to the earth mat / ground pit. Each point of Earthing with all formation works like bending, twisting, drilling of holes & conncting by welding (inclusive of all T & P consumables) to the earth mat/ ground pit/point of earth connection, all the materails supplied by the contractor (As per KPTCL SR-2023-24, Page No:123, Sl.No-26 Item No:i Material Rs-335.00 Rmt 60 279 16750.00
G Miscellaneous items 0.00
a) Caution/Danger Board (As per KPTCL SR- 2025-26, No- 31 of 50, SL.No-687) Nos 5 131 655.00
b) Phase plates (As per KPTCL SR 2023-24, Page No.43, Sl. No.19, Item No,19.1, Rs.528/- Set (3 Nos) 1 440 440.00
c) Name Plates for equipment/Earth Pit (As per present market rate due to non availability of rates in the current SR) Nos 20 250 5000.00
H Station Service Equipments: 0.00
a) Single line diagram Photo sheet paper (Size 20x20 inch) (As per present market rate) Nos 2 1667 3333.33
b) Supplying and installation of Rubber mat 1mtr x 1mtr -1Omm thick.complete including cost of materials, labour, usage charges of machinery complete as per specifications. (As per PWD SR 2023-24, Page No.93 of 105 Sl.No.15, Item No,15.117, Rs 1900/-) Nos 6 1583 9500.00
Total Material cost 15553688.33 643791.32
HUBLI ELECTRICITY SUPPLY COMPANY LIMITED
Estimate for Replacement of existing 2 X 5MVA by 2 X 8 MVA Power Transformer at 33/11 KV Sub-station Balekundri in Belagavi Taluk. Belagavi District on Total turnkey basis.
PART-B (Electricals Erection Works)
Sl. No. Particulars Unit Qty Rate Amout in Rs.
A. ERRECTION OF POWER TRANSFORMERS
a a) Moving the transformers on to the plinth to a (Maximum allowable distance is 50 mtrs.) more than 50 mtrs. approval of the CEE, O&M Zone has to be obtained) (16.0 MT X 2= 32 MT X 60 Mtr= 1920 MT/Mtr). As per KPTCL SR-Labour Portion, PG No 116 Sl.No:9 a Mt/mtr 1920 67 128000 720 640
b b) i) Assembly of 8MVA.33/11KV Power transformers parts like bushing, radiators, conservators, tank, filling oil into transformer for total weight of the transformer. As per KPTCL SR-Labour Portion, PG No 116 Sl.No:9 b MT 32 945 30240 1280 1000
c ii) Filtration of oil using filter set of the contactor to bring the insulation value to IE specifications. As per KPTCL SR-Part-I, PG No 116 Sl.No:9 d Ltr 10000 6 58333
d C) Wiring of transformer marshalling box, Bucholtz relay, fixing thermometer, OLTC upto control panel and assisting in testing and commissioning by RT/MT/firm Engineers. (As per KPTCL SR-2023-24 Labour,Page No-116, Sl.No-9, Item No-(f&i)) Per Transformer 2 5590 11180 5 8 87.5 140
B a) Erection of NCTs including movement from the point of unloading to the point of erection with grounding connections (As perKPTCL CSR 2023-24, Labour, Page No: 118, Sl No.:15(a) Rs-733.00 Set 2 611 1222
b) Assisting in Testing & Commissioning:(As per KPTCL CSR 2023-24, Labour, Page No: 118, Sl No.:15(c) Rs-99.00 Set 2 83 165
B Laying of copper control cables from equipments to control panels. 0
a) 4 core 2.5 Sq.mm (As per KPTCL SR 23-24, Labour, page No: 120, Sl.No:22, (b) Rs- Per Mtr-15.00 Rmtr 100 13.00 1300
b) 10 core 2.5 Sq.mm (As per KPTCL SR 23-24, Labour, page No: 120, Sl.No:22, (b) Rs- Per Mtr-15.00 Rmtr 120 13.00 1560
B.14 Laying of Power cables from switchgears to DP of 11 kV cables in existing trench/G.I. pipe/stoneware pipe/RCC hume pipe using wooden/aluminium rollers as directed by KPTCL staff. 0
a) Cables of sizes 3C x 185 to 3C x 240 Sq mm (As per ESCOM's SR 25-26, Labour, page No:41 of 50,Sl.No.172 ,Item No.21.02) Km 0.080 58866.00 4709 #REF!
c) Making and Fixing of Pothead of 3C X 185 to 3C X 240 Sq mm (Indoor and Outdoor) page No:42 of 50,Sl.No.182, item No. 22.05 Set 4 2215.00 8860 2658
g) Laying of GI Pipe (HESCOM SR-2025-26,Labour ,Cost data sheet-23, Sl No- 11 (i) Rs:93 Mtr 20 83 1660
2) 11KV Isolators: 0
a) Erection of 400A, special roster switch with H-frame & clamps to be mounted on DP (As per ESCOM SR- 23-24, Labour, Pg No:48 of 81 Sl No.: 98 ,itme no:13.03 ) Rs-1214 Nos 1 1370.00 1370
B.13 b) Erection of 2 Pole DP Structure using RCC/PSCC Pole 9 to 10 Mtr long (As per ESCOMs Labour SR-2025-26 Page No- 58 Sl.No-34 Item No-2.06)4 Per Structure 1 3682 3682 1403 only dp #REF! 1341
1) Digging of Pit 1.8 Mtr depth (Hard Soil) for errection of 9Mtr 11KV ODS pole- ESCOMs Labour SR-23-24 Page No- 43 of 81 Sl.No-2 Item No-1.1.2 RS- 11322) Errection of 9 Mtr. Long, 145kg RCC pole for 11KV ODS. (As per ESCOMs Labour SR-2025-26 Page No- 58 Sl.No-30 Item No-2.02) RS-991 (Total Rs 561+9991=1552) Nos 2 1552 3104
D Miscellaneous items 0 #REF!
a) Fixing Caution/Danger Boards (As per ESCOM SR- 2025-26, Labour, Pg No:60 Sl No.: 63 ,itme no:5.15) Nos 5 71 355
b) Fixing Phase Plates As per KPTCL Labour SR 23-24,Pg No.113 ,Sl No.3(c) Rs-238 Set (3Nos) 4 198 793 71.5986
c) Fixing Name Plates for equipment/Earth Pit ,KPTCL SR 21-22, page No-09 of 27 Sl No-7 Item No:- (d), Labour Charge Rs.54 Nos 20 45.00 900
Total cost 257433.61
HUBLI ELECTRICITY SUPPLY COMPANY LIMITED
Estimate for Replacement of existing 2 X 5MVA by 2 X 8 MVA Power Transformer at 33/11 KV Sub-station Balekundri in Belagavi Taluk. Belagavi District on Total turnkey basis.
Sl No Description of work Unit Qty Rates Amount
PARTA -LABOUR CHARGES
1 Dismantaling of exisiting 2X5 MVA Power transformer
a Dismantling of Transformer parts like bushings, radiators, oil from Tr. etc., (for the total wt. of the Tr.) ( 13.9+16.41=30.31 )(Common SR 2018-19 33KV labour Page No:16 SL No:227 It.No 49i.) MT 30.31 945.00 28642.95 4826.7 +13.59+16.41 8228
b Moving the Transformer from Tr. Bed to safest point. 30.0 MT X 30 Mtr= 755MT/Mtr) (Common SR 2018-19 33KV labour Page No:16 SL No:227 It.No 49i.) MT/Mtr 900 67 60000.00 30.0000 4826.7
c transporation of relesed transil oil barrels from station premises to divisional stores L/s 1 10000.00 10000.00
Grand Total 98642.95
HUBLI ELECTRICITY SUPPLY COMPANY LIMITED
Estimate for Replacement of existing 2 X 5MVA by 2 X 8 MVA Power Transformer at 33/11 KV Sub-station Balekundri in Belagavi Taluk. Belagavi District on Total turnkey basis.
PART-C-(CIVIL WORKS)
Sl No. Item Description Unit Qty Unit Price (Rs) Deloaded 21% Rate Total Price (Rs)
A Foundations: Engineering, supply of all labour,material and construction of RCC footing including the cost of excavation, cement concreting, reinforcement, backfilling, waterproof cement painting, for all works, grouting underpinning etc ,for the following works
f) 11 KV NCT mounting structure (1.1 mtrX0.55 mtr X 1mtr Depth) Nos 2 5941.00 4909.92 4951 9901.67
B Foundations: Engineering, supply of all labour,material and construction of RCC footing including the cost of excavation, cement concreting, reinforcement, backfilling, waterproof cement painting, for all works, grouting underpinning etc ,for the following works 0.00
a) 9 mtrs long RCC poles for ODS (As per ESCOM's SR 2023-24,Base concreting Rs.312+Pole concreting Rs.3434,Coping Rs.312) No's 2 4058.00 3353.72 3382 6763.33
C a) Providing PVC ringtite pipes conforming to IS 4985:2000 with latest amendments and conveying to worksite, rolling and lowering into trenches, laying true to line and level and perfect linking at joints, testing and commissioning, including loading unloading at both destinations and cuts of pipes wherever necessary including jointing of PVC pipes and specials (excluding cost of specials) with jointing of approved type, with all labour with all lead & lift including encasing the pipe alround to a depth of not less than 15 cms. with soft gravel or selected earth available from the excavation etc. complete and giving necessary hydraulic test to the required pressure as per ISS (Contractor will make his own arrangements for procuring water for testing) etc. complete For: 0.00
a) PVC pipes 63mm dia., 6 kg/sqcm & class 3 Mtrs 20 161.00 133.06 161.00 3220.00
b) PVC pipes 75mm dia., 6 kg/sqcm & class 3 Mtrs 20 220.00 181.82 220.00 4400.00
Total cost 24285.00
HUBLI ELECTRICITY SUPPLY COMPANY LIMITED
PART II : Particulars to be Furnished by field staff : 1020.6 4134.75
S.No Particulars RELEASED GOOD RELEASED GOOD
I POWER TRANSFOMERS
1 Year of commissioning 2008 2008
2 Year of dismantling to be dismental to be dismental
3 Particulars of equipment to be returned to stores: - 5MVA, 33/11 KV Power Transformer with oil and aceesories. 5MVA, 33/11 KV Power Transformer with oil and aceesories.
4 Capacity 5 MVA 5 MVA
6 Make ETE KIRLOSKAR
Year of mfg 1996 1980
7 Voltage HV 33000 KV HV 33000 KV
8 LV 11000 KV LV 11000 KV
9 Total mass 13.9 MT 16.41MT
Untanking mass 7.4 MT
10 Insulating oil IN LITERS 3250 4440 3300 760 4060 406 3654
11 Wastage of oil during releasing the accessories from the Power Transformer 10% Less 325 444 3654
12 To be returned to store with 10% Less wastage oil =(4060-406 =3654) 2925 3996 2970 14.85 18.27
PART III - Particulars to be Furnished by Accounts staff: - 3120
S.No Particulars Amount in Rs.
1 Original value of asset to be dismantled
2 Number of years in service
3 Depreciation value earned: -
4 Written off value of asset: -
Certificate: Certified that I have personally visited the spot and prepared this estimate as per KPTCL/HESCOM common SR 2023-24, for most economical & safe way of execution of work.
Junior Engineer(El) Asst. Executive Engineer(El)
33/11 KV MUSS Balekundri 33KV S & L Sub-Division, HESCOM,
HUBLI ELECTRIC SUPPLY COMPANY LIMITED
SINGLE LINE DIAGRAM OF 33/11KV MUSS BALEKUNDRI in O&M RURAL DIVISION HESCOM BELAGAVI
Replacement of existing 2 X 5MVA by 2 X 8 MVA Power Transformer at 33/11 KV Sub-station Hebale in Bhatkal Taluk, Uttar kannada District on Total Turnkey basis.
Bid Indent NO: HESCOM/2026-27/EL/WORK_INDENT1226
Bidder’s Name and Address (Sole Bidder) : To:
Superintendent Engineer El, Project Monitoring Cell, Corporate Office, HESCOM, Hubli. - 580025
We declare that the ratings, performance figures and availability of the system furnished by us for subject Package covered under this specification are guaranteed by us. We further declare that in the event of any deficiencies in meeting the guarantees in respect of the characteristics mentioned below as established after conducting the factory test, you may at your discretion, reject or accept the equipment after assessing the liquidated damages as specified in the relevant clauses of Bid document.
Equipment Guaranteed losses at rated output (KW per unit)
Copper/Aluminium Loss at 75 degree C at rated current Iron loss at rated voltage and frequency
Distribution Transformers:
8 MVA, 33/11 KV, 3ph.Power transformer
Date : (Signature)
Place : (Printed Name)
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
9 tender capacity.xlsx
Others - 9 tender capacity • 0.01 MB
10-format-i- work done.xls
Others - 10-format-i- work done • 0.03 MB
11 Balekundri 5 by 8 mVA.xlsx
Others - 11 Balekundri 5 by 8 mVA • 1.09 MB
8 technical specification.doc
Others - 8 technical specification • 0.58 MB
7 Annexures.doc
Others - 7 Annexures • 0.16 MB
13 FD417EXP.pdf
Others - 13 FD417EXP • 0.12 MB
15 KPTCL Cicrcular insurance surety bond.pdf
Others - 15 KPTCL Cicrcular insurance surety bond • 1.59 MB
2 section 1 IFB 1226.doc
Others - 2 section 1 IFB 1226 • 1.41 MB
1 NIT INDENT 1226.doc
Others - 1 NIT INDENT 1226 • 0.14 MB
3 section ii ITB 1226.doc
Others - 3 section ii ITB 1226 • 0.11 MB
16 loss declaration.xlsx
Others - 16 loss declaration • 0.01 MB
12 Advisory NOte.pdf
Others - 12 Advisory NOte • 0.67 MB
4 section iii GCC INDENT 1226.doc
Others - 4 section iii GCC INDENT 1226 • 0.14 MB
6 section v SCC INDENT 1226.doc
Others - 6 section v SCC INDENT 1226 • 0.11 MB
5 section iv ECC INDENT 1226.doc