Repairs to I.P.S footpath at 295/2K A.P.C. Road, 3/H/26/ R.D. Street and others in Ward No -28
2026_KMC_993750_1
KMC/IV/28/APAS/01/164/28/0006
Open Tender
CIVIL WORKS
Percentage
14 days
BOROUGH IV
Please refer Tender documents.
4 documents required · 4 mandatory
₹0
₹3,000
13 Feb 2026
26 Jan 2026
2 Feb 2026
26 Jan 2026
31 Jan 2026
26 Jan 2026
Earthwork in cutting to form road section in correct profile including removal of spoils not exceeding initial lead of 50m and initial lift of 1.5m (Mode of measurement: pre works and post works) (i) In ordinary soil
BUILDING WORKS (B) DISMANTLING, CUTTING CHASE, HOLES ETC 6. Dismantling artificial stone flooring upto 50 mm. thick by carefully chiselling without damaging the base and removing rubbish as directed within a lead of 75 m. a) In ground floor including roof.
BUILDING WORKS(P) SOLING, EDGING AND METALLING??(15)Labour for taking out old soling edging including removing debris. (a) Single flat soling
BUILDING WORKS(P) SOLING, EDGING AND METALLING??(2)Labour for laying soiling with departmental bricks including carriage of departmental bricks within a lead of 150 metres preparation of bed as necessary with brick joints properly filled in and packed with brick joints properly filled in and packed with local sand or powdered earth and including necessary cushion of similar materials below the soling (and in between layers when more than one layer is used)(The item included the cost of obtaining local sand or powdered earth)(a) Single brick flat soling (thickness 75 mm)
BUILDING WORKS ( C ) BRICKWORKS, CONCRETE WORKS Etc. A. BRICK WORKS 1. Single Brick Flat Soling of picked jhama bricks including ramming and dressing bed to proper level and filling joints with local sand.
35mm thick Cement Concrete Pavement (1:2:4) in floor/footpath etc. with graded stone chips 11.2mm down,properly leveled with 3mm thick screen on top by cement slurry [email protected] cement per Sqm. Rounding off corners, chequering as required including taking necessary protective measure complete in Gr.floor/footpath.
Taking out stone slab of kerb & channel of road side drain and stacking as directed. b) flat channel stone.
Taking out stone slab of kerb & channel of road side drain and stacking as directed. a) vertical kerb stone. ( Ref :Rate based on PWD Current SOR. [PWD(B)2017,p-303])
Resetting of Stone Slabs of kerb & channel of road side drain to correct line and level including cement pointing (1:2). b) flat channel stone. ( Ref :Rate based on PWD Current SOR. [PWD(B) 2017, p-303 & 3rd corri. Addea dtd-04.06.2018. P-52 ])
Resetting of Stone Slabs of kerb & channel of road side drain to correct line and level including cement pointing (1:2). a) Vertical Kerb ( Ref :Rate based on PWD Current SOR. [PWD(B) 2017, p-303 & 3rd corri. Addea dtd-04.06.2018. P-52 ])
Cement concrete with graded jhama khoa (30 mm size) excluding shuttering In ground floor and foundation. (a) 1:3:6 proportion ( Ref :PWD (Bldg.)-2017, It. No. 1, Page No.23 & 3rd Corrigenda Addenda dtd-04.06.18, P-9 & 10)
Supplying and laying factory made flat channel stone of cement concrete M-20 (1:1.5:3) machanicaly vibrated; size 500mm X 300mm X 100 mm; making joints with cement mortar (1:4) incldg cost of all materials and labours but excluding the cost of under bed (for road-diveder) ( Ref :Rate based on PWD Current SOR [PWD(B) 2017, p-26 (it -10(i)), consumption chart pg-B-60, sl-3 and Annex-II , Format-A & 3rd Corr. & adda. dtd-04.06.2018, p-303 , p-191 (i -6) and 3rd Corr. & Adda, page-52, PWD-2018(R & B) p-332 (it -18.05)), Chapter-1, pg-227 I-1.03, pg-230,Table-I , Table III-2 pg-226, )
Sub Total
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 1.49 MB
Tendernotice_2.pdf
PDF • 0.59 MB
BOQ_2431100.xls
BOQ • 0.29 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .