| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹62.5 LAccepted-AOC | L1 | Accepted-AOC L1 | |
| 2 | L2₹62.5 L+₹3,708.34 (0.06%)Rejected-Finance | L2 | Rejected-Finance Highest |
Tender Value
Refer Docs
EMD Value
₹1.3 L
Closing Date
19 Apr 2021, 9:00 amClosed
Superintendent Engineer
UPSCIDCO Ltd Konchhabhanwar Jhansi
Construction of Balance wok of Boundry Wall Jail Campus Orai Jalaun
2021_SCIDC_575041_2
137/SE/Jhansi/Orai/2020-21
Open Tender
Civil Works - Others
Item Rate
180 days
Orai Jalaun
Please Refer the Tender Document
2 documents required · 2 mandatory
₹2,000
Yes
UPSCIDCO LTD
₹1.3 L
Yes
13 Sept 2021
13 Apr 2021
19 Apr 2021
13 Apr 2021
19 Apr 2021
13 Apr 2021
13 Apr 2021 - 19 Apr 2021
Amount
Construction of Pile Boundry Wall 85.50 (Material with Labour)
Clearing Jungle including prooting of rank vegeatation grass, bush, wood trees and sapling f gitrh up 30cm measured at a height of 1 mtr above ground lavel & removal of rubbish up to a distance of 50 mtr out side the periphery of area cleared.
Earth Work in Excavation in Black Cotton Soil
Boring of 30cm dia Piles of single under reamed of 127 cm dia of bulb and 3.5 m depth in black cotton soil with hand operated auger machin including all labour and t&p etc.For P1
Boring of 30cm dia Piles of single under reamed of 127 cm dia of bulb and 3.5 m depth in black cotton soil with hand operated auger machin including all labour and t&p etc.For P1
Boring of 25cm dia Piles of single under reamed of 113 cm dia of bulb and 3.5 m depth in black cotton soil with hand operated auger machin including all labour and t&p etc.For P2
R.C.C work with cement approved coarse sand and 2cm.(3/4")Gauge approved stone ballast in the proportio of 1:1.5:3 in pile excluding supply of reinforcement and its binding but including its fixing and binding the same with 24 B.W.G.G.i binding wire and including necessary cenetering and shuttering etc. and also including supply of all materials, labour& T&Petc.required for proper completion of the work.
R.C.C work with cement approved coarse sand and 2cm.(3/4")Gauge approved stone ballast in the proportio of 1:1.5:3 in the lighter beam excluding supply of reinforcement and its binding but including its fixing and binding the same with 24 B.W.G.G.i binding wire and including necessary cenetering and shuttering etc. and also including supply of all materials, labour& T&Petc.required for proper completion of the work.in plinth beam
R.C.C work with cement approved coarse sand and 2cm.(3/4")Gauge approved stone ballast in the proportio of 1:1.5:3 in column excluding supply of reinforcement and its binding but including its fixing and binding the same with 24 B.W.G.G.i binding wire and including necessary cenetering and shuttering etc. and also including supply of all materials, labour& T&Petc.required for proper completion of the work.over p1
R.C.C work with cement approved coarse sand and 2cm.(3/4")Gauge approved stone ballast in the proportio of 1:1.5:3 in coloum excluding supply of reinforcement and its binding but including its fixing and binding the same with 24 B.W.G.G.i binding wire and including necessary cenetering and shuttering etc. and also including supply of all materials, labour& T&Petc.required for proper completion of the work.binding wire cost being including in the item over over p2
R.C.C work with cement approved coarse sand and 2cm.(3/4")Gauge approved stone ballast in the proportio of 1:1.5:3 in the Bend excluding supply of reinforcement and its binding but including its fixing and binding the same with 24 B.W.G.G.i binding wire and including necessary cenetering and shuttering etc. and also including supply of all materials, labour& T&Petc.required for proper completion of the work. over p1 R.C.C BEND
R.C.C work with cement approved coarse sand and 2cm.(3/4")Gauge approved stone ballast in the proportio of 1:1.5:3 in the column excluding supply of reinforcement and its binding but including its fixing and binding the same with 24 B.W.G.G.i binding wire and including necessary cenetering and shuttering etc. and also including supply of all materials, labour& T&Petc.required for proper completion of the work.including in the item R.C.C coloum over p1
R.C.C work with cement approved coarse sand and 2cm.(3/4")Gauge approved stone ballast in the proportio of 1:1.5:3 in the Bend excluding supply of reinforcement and its binding but including its fixing and binding the same with 24 B.W.G.G.i binding wire and including necessary cenetering and shuttering etc. and also including supply of all materials, labour& T&Petc.required for proper completion of the work.top bend
First class brick work in 1:6 cement and Course sand of mortar including supply of all material ,labour and T&P in super structure 9 inch thick Wall
providing and fixing of M.S ralling as per design
12 mm thick cement plaste 1:6 cement sandmortar supply of all material labour T&P etc. complete Work
15 mm thick cement plaste 1:6 cement sandmortar supply of all material labour T&P etc. complete Work
Painting on m.S ralling in two courts
making puuty over wall Both side
Finishing Wall with Water proofing cement paint over wall
Steel Reinforcemet in R.c.c work
Construction of Pile Boundry Wall 164 Rm (Material with Labour)
Boring of 30cm dia Piles of single under reamed of 127 cm dia of bulb and 3.5 m depth in black cotton soil with hand operated auger machin including all labour and t&p etc.For P1
Boring of 25cm dia Piles of single under reamed of 113 cm dia of bulb and 3.5 m depth in black cotton soil with hand operated auger machin including all labour and t&p etc.For P2
R.C.C work with cement approved coarse sand and 2cm.(3/4")Gauge approved stone ballast in the proportio of 1:1.5:3 in pile excluding supply of reinforcement and its binding but including its fixing and binding the same with 24 B.W.G.G.i binding wire and including necessary cenetering and shuttering etc. and also including supply of all materials, labour& T&Petc.required for proper completion of the work.
R.C.C work with cement approved coarse sand and 2cm.(3/4")Gauge approved stone ballast in the proportio of 1:1.5:3 in the lighter beam excluding supply of reinforcement and its binding but including its fixing and binding the same with 24 B.W.G.G.i binding wire and including necessary cenetering and shuttering etc. and also including supply of all materials, labour& T&Petc.required for proper completion of the work.in plinth beam
R.C.C work with cement approved coarse sand and 2cm.(3/4")Gauge approved stone ballast in the proportio of 1:1.5:3 in column excluding supply of reinforcement and its binding but including its fixing and binding the same with 24 B.W.G.G.i binding wire and including necessary cenetering and shuttering etc. and also including supply of all materials, labour& T&Petc.required for proper completion of the work.over p1
R.C.C work with cement approved coarse sand and 2cm.(3/4")Gauge approved stone ballast in the proportio of 1:1.5:3 in coloum excluding supply of reinforcement and its binding but including its fixing and binding the same with 24 B.W.G.G.i binding wire and including necessary cenetering and shuttering etc. and also including supply of all materials, labour& T&Petc.required for proper completion of the work.binding wire cost being including in the item over over p2
R.C.C work with cement approved coarse sand and 2cm.(3/4")Gauge approved stone ballast in the proportio of 1:1.5:3 in the Bend excluding supply of reinforcement and its binding but including its fixing and binding the same with 24 B.W.G.G.i binding wire and including necessary cenetering and shuttering etc. and also including supply of all materials, labour& T&Petc.required for proper completion of the work. over p1 R.C.C BEND
R.C.C work with cement approved coarse sand and 2cm.(3/4")Gauge approved stone ballast in the proportio of 1:1.5:3 in the column excluding supply of reinforcement and its binding but including its fixing and binding the same with 24 B.W.G.G.i binding wire and including necessary cenetering and shuttering etc. and also including supply of all materials, labour& T&Petc.required for proper completion of the work.including in the item R.C.C coloum over p1
R.C.C work with cement approved coarse sand and 2cm.(3/4")Gauge approved stone ballast in the proportio of 1:1.5:3 in the Bend excluding supply of reinforcement and its binding but including its fixing and binding the same with 24 B.W.G.G.i binding wire and including necessary cenetering and shuttering etc. and also including supply of all materials, labour& T&Petc.required for proper completion of the work.top bend
First class brick work in 1:6 cement and Course sand of mortar including supply of all material ,labour and T&P in super structure 9 inch thick Wall
providing and fixing of M.S ralling as per design
12 mm thick cement plaste 1:6 cement sandmortar supply of all material labour T&P etc. complete Work
15 mm thick cement plaste 1:6 cement sandmortar supply of all material labour T&P etc. complete Work
Painting on m.S ralling in two courts
making puuty over wall Both side
Finishing Wall with Water proofing cement paint over wall
Steel Reinforcemet in R.c.c work
Construction of Retaining Wall 43.5 m length (Material with Labour)
cement concrete with 4cm(1.5")gauge approved stone ballast,approved coarse sand and cement in the proportion of 1:4:8 including supply of all materials labour and T&P etc.in Foundation
R.C.C work with cement approved coarse sand and 2cm.(3/4")Gauge approved stone ballast in the proportio of 1:1.5:3 in Foundation excluding supply of reinforcement and its binding but including its fixing and binding the same with 24 B.W.G.G.i binding wire and including necessary cenetering and shuttering etc. and also including supply of all materials, labour& T&Petc.required for proper completion of the work. Raft Foundation
Retaining Wall
First Class brick Work in 1:6 cement and fine sand of 1.25 Fm.mortar in Super Structure and plinth including supply of all materials, labour and T&P etc. required for proper completion of the Work.9 inch thick Wall
R.C.C work with cement approved coarse sand and 2cm.(3/4")Gauge approved stone ballast in the proportio of 1:1.5:3 in colum excluding supply of reinforcement and its binding but including its fixing and binding the same with 24 B.W.G.G.i binding wire and including necessary cenetering and shuttering etc. and also including supply of all materials, labour& T&Petc.required for proper completion of the work.
R.C.C work with cement approved coarse sand and 2cm.(3/4")Gauge approved stone ballast in the proportio of 1:1.5:3 in Bend excluding supply of reinforcement and its binding but including its fixing and binding the same with 24 B.W.G.G.i binding wire and including necessary cenetering and shuttering etc. and also including supply of all materials, labour& T&Petc.required for proper completion of the work.
Supply of M.S Grill of a approved Design and Drawing
12 mm thick cement plaster over fair face wall 1:6 cement sand mortar
15 mm thick cement plaster over rough face wall 1:6 cement sand mortar
Painting in two coat over steel gril both side including Supply of all material T&P etc complete Work
Finishing Wall with putty
Finishing Wall with Water proofing cement paint
Mild steel or iron in plain work such as reinforced concrete or reinforced brick work (when not including in an over all rates ) wrought to required shape as necessary including supply of all steel and Wastage & over lapping & hooks.P1 12 mm dia VERTICAL bar
Pradeep kumar Upadhyay
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .