| Sl No | Description | Qty | Unit | Selvam Infrastructures L1 | M/S Annanmar Constructions L2 |
|---|---|---|---|---|---|
| 1.00 | Earth Work excavation for foundation in all soils and sub soils & to full depth as may be directed except in hard rock requiring blasting inclusive of shorting,strutting and baling out water, wherever necessary and refilling the side of foundation with excavated earth in 15cm thick layers well rammed and depositing the surplus earth within the compound in places shown by the officers with all leads and lifts etc., complete complying with std. specifications | 206.84 | Cum | 187.5 ₹38,782.50 | 190 ₹39,299.60 |
| 2.00 | Filling with foundation trenches and basement with filling m-sand as leveling course including watering and consolidation | 43.03 | Cum | 1,428 ₹61,446.84 | 1,450 ₹62,393.50 |
| 3.00 | Filling with foundation trenches and basement with filling soil as leveling course including watering and consolidation | 190.58 | Cum | 500 ₹95,290 | 520 ₹99,101.60 |
| 4.00 | Plain Cement Concrete 1:4:8 (One cement, four m-sand and eight hard broken granite stone jelly ) using 40mm HBG metal as foundation concrete including dewatering wherever necessary and laid in layers of not more than 15cm. thick complying with std specification | 41.76 | Cum | 4,708 ₹2.0 L | 4,725 ₹2.0 L |
| 5.00Plain Cement Concrete 1:1.5:3 (One Cement one and Half sand Three hard broken granite stone jelly ) for footing plinth beams, lintels square (or) rectangular columus floor or roof slab conopy slab and other similar item of works etc., complete excluding cost of reinforcement grill in position centering , shuttering but including placing curing & finishing all the RCC works as detailed and as directed by the officers etc., complete | |||||
| 5.10 | a.In Foundation & Basement | 67.72 | Cum | 8,136 ₹5.5 L | 8,150 ₹5.5 L |
| 5.20 | b.Ground floor- RCC Column in Super Structure above base to 3.35m ht | 69.79 | Cum | 8,324 ₹5.8 L | 8,350 ₹5.8 L |
| 5.30 | c. Fist floor - RCC Column in Super Structure above Ground floor to 3.35m ht | 70.05 | Cum | 8,471 ₹5.9 L | 8,480 ₹5.9 L |
| 5.40 | Second floor - RCC Column in Super Structure above Fisr floor floor to 2.43m ht | 6.06 | Cum | 8,692 ₹52,673.52 | 8,700 ₹52,722 |
| 6.00 | Supplying fabrication and placing in position of M.S. or RTS rods reforcement grill in position for all RCC works inculding cost of steel rods and binding wire etc ., complete | 245.66 | Qtl | 8,354 ₹20.5 L | 8,360 ₹20.5 L |
Tender Value
₹1.4 Cr
EMD Value
₹82,500
Closing Date
9 Dec 2024, 3:00 pmClosed
Tender Committee, S.351, TAPCMS LTD., TIRUCHENGODE
S.351, TAPCMS LTD., TIRUCHENGODE, Namakkal Dt.
Construct the Multipurpose Mini Hall at Konganapuram Branch
2024_ROCS_506702_1
1/2024-25
Open Tender
Civil Works - Buildings
Konganapuram
Please refer Tender documents.
2 documents required · 2 mandatory
₹0
₹82,500
16 Dec 2025
3 Dec 2024
10 Dec 2024
3 Dec 2024
9 Dec 2024
3 Dec 2024
Amount
Earth Work excavation for foundation in all soils and sub soils & to full depth as may be directed except in hard rock requiring blasting inclusive of shorting,strutting and baling out water, wherever necessary and refilling the side of foundation with excavated earth in 15cm thick layers well rammed and depositing the surplus earth within the compound in places shown by the officers with all leads and lifts etc., complete complying with std. specifications
Filling with foundation trenches and basement with filling m-sand as leveling course including watering and consolidation
Filling with foundation trenches and basement with filling soil as leveling course including watering and consolidation
Plain Cement Concrete 1:4:8 (One cement, four m-sand and eight hard broken granite stone jelly ) using 40mm HBG metal as foundation concrete including dewatering wherever necessary and laid in layers of not more than 15cm. thick complying with std specification
Plain Cement Concrete 1:1.5:3 (One Cement one and Half sand Three hard broken granite stone jelly ) for footing plinth beams, lintels square (or) rectangular columus floor or roof slab conopy slab and other similar item of works etc., complete excluding cost of reinforcement grill in position centering , shuttering but including placing curing & finishing all the RCC works as detailed and as directed by the officers etc., complete
a.In Foundation & Basement
b.Ground floor- RCC Column in Super Structure above base to 3.35m ht
c. Fist floor - RCC Column in Super Structure above Ground floor to 3.35m ht
Second floor - RCC Column in Super Structure above Fisr floor floor to 2.43m ht
Supplying fabrication and placing in position of M.S. or RTS rods reforcement grill in position for all RCC works inculding cost of steel rods and binding wire etc ., complete
Centering for soffits of reinforced cement concrete slabs , plain surfaces including strutting 3 meter height using M.S. Plate of size 90 cm x60cm and 10 gange stiffen and with welded mild steel angles of size25x25x3mm laid over silver oak(country wood)
a) Columns ,footing , Grade beam
b) Ground floor
c) First floor
d) Second floor
Brick work in following Cement Mortar using best quality Fly Ash Bricks of size 230 x 110 x70mmfor foundation and basement including curing, etc., complete complying with standard specifiction.
a.In foundation& basement
b) Ground floor
c) First floor
d) Second floor
Supply and fixing of Teak wood fully panelled First Quality Teak Wood and single leaf (two equal panels) shutter for door including all labour charges cost and conveyance of all materials to site etc.,Complete as per standard specification
Fabricating, supplying and fixing in position MS grill for all windows with UPVC Top Window madeup of full 70mm high impact resistant PVC frames reinforced with galvanised steel having night vent facility , internal glazing , locking handles , integral gaskets excellent thermal and insulation efficiency with standard profiles, as per drawings and specifications and as directed by the Engineer.
Supplying and fixing 18 Gauge steel rolling shutters for a clear opening 1.80mx 2.40 of approved make inculding suppling and fixing top hood cover and all other accessories, locking arrangements etc ., with one coat of red oxide primer paint etc., complete
Plastering with Cement Mortar 1:5 (One Cement and Five m-sand) 12mm thick including curring etc ., complete
Special plastering with cement mortar1:3( one cement and three m-sand )10mm thick for the exposed faces of RCC works inculding hacking curring etc., complete
Paving the floor with descrigned coloured Vitrified tiles of size 600 x 600 x 8mm of best quality and approved variety complying / confirming ISI specification land over cement mortar 1:3 (one cement and three sand) 20mm thick and pomted with same coloured cement neatly etc., complete.
Paving the Toilet wall tiles coloured Dadoing tiles of size 300 x 450 x 8mm of best quality and approved variety complying / confirming ISI specification land over cement mortar 1:3 (one cement and three m-sand) 20mm thick and pointed with same coloured cement neatly etc., complete.
Painting the walls with two coasts with first class quality Emulsion paint of approved colour over a priming cost, including thorough scraping, clean removal of dirt. The Rate includes cost of brushes, Sand paper, plaster of parries, putty wherever required and neat finishung etc. complete complying with standard specification ( for Inner & Outer Side)
Painting two coats for new iron works such as iron bars flats and orhers similar works etc., complete complying with std specification
Supply and fixing of Teak wood polish work Remove dust and grime with a damp cloth or vacuum. For stubborn stains, use a mild soap solution and wipe dry Use sandpaper to smooth the surface and remove rough edges Choose the right polish for your door's surface, whether it's painted, stained, or bare. Apply the polish with a soft cloth and rub polish dry completely.
Weathering course using concrete broken brickly 20mm gauge in pure laked lime over Rcc Roof slab in proportion of 32:12 ½ wek setean by wooden treater for giving required slope eh complete
Finishing the top or roof with one course of machine Aessed tiles of size 23 x 23 x 2 cm of approved Quality laid in cement mortan 1:3 (one cement, three m-sand) mixed with water proof compound @ 2% by weight of cement used and pointed with Water proof chemical mortar etc., complete
Anti- Termite treatment
Providing Internal and external electrification and all tube light & Fan Fitting
Providing plumbing work of pipe line and tap fitting for toilet area with 5000 liter syntex tank with all sanitary items and CC tap fittings
Provision for satircase and entrance steps granite laying work with S.S Handrails
Provision for Elevation with border work
Provision for Rain Water Harvesting 1 Pits
Provision for Septic Tank & Soak Pit
M/S Annanmar Constructions (BID ID -1201527)
stage.html
html • 0.03 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid