| 1 | L1₹5.9 CrAccepted-AOC | ₹5.9 Cr | L1 | Accepted-AOC L1 |
| 2 | L2₹5.9 Cr+₹47,747 (0.08%)Rejected-Finance | ₹5.9 Cr+₹47,747 (0.08%) | L2 | Rejected-Finance L2 |
Tender Value
₹6.1 Cr
EMD Value
₹12.2 L
Closing Date
4 Dec 2020, 3:00 pmClosed
Additional Director/Project Director
DRDA, SALEM
TN15-197-PMGSY III 2020-2021 BATCH -I - 01 ROAD AT YERCAUD BLOCK IN- SALEM DISTRICT
2020_RDTN_101503_1
TN15197
Open Tender
Civil Works - Roads
Item Rate
270 days
DRDA
As per tender Schedule
3 documents required · 3 mandatory
₹0
₹12.2 L
DRDA, SALEM
18 Feb 2021
23 Oct 2020
4 Dec 2020
23 Oct 2020
4 Dec 2020
23 Oct 2020
20 Nov 2020
Amount
1) MRL19 - Koothamuthal Kovilur Road to Kombuthuki Village Road
Clearing and grubbing road land including uprooting wild vegetation,grass ,bushes, shrubs, saplings and trees of girth upto 300mm, removal of stumps of such trees cut earlier and disposal of unserviceable materials and stacking of serviceable material to be used or auctioned, upto a lead of 1000m including removal and disposal of top organic soil not exceeding 150 mm in thickness as per MORD Technical Specification Clause 201.
excuation for road work in soil with hydraulic excavator of 9.0 cum bucket capacity inculding cutting and loading in tipper, trimming bottom and side slopes, in accordance with requrements of lines, grades and cross section, and transporting to the embankment location with a lift upto 1.5m and lead upto 1000m as per technical specification
Construction of embankment with approved materials deposited at site from roadway cutting and excavation from drain and foundation of other structures graded and compacted to meet requirement of Tables 300.1 and 300.2 as per Technical Specification Clause 301.5 (Filling With Cut Earth)
Construction of embankment with approved materials deposited at site from roadway cutting and excavation from drain and foundation of other structures graded and compacted to meet requirement of Tables 300.1 and 300.2 as per Technical Specification Clause 301.5 (Gravel shoulder)
Construction of embankment using tractor with approved materials deposited at site from roadway cutting and excavation from drain and foundation of other structures graded and compacted to meet requirement of Tables 300.1 and 300.2 as per Technical Specification Clause 301.5 (Gravel shoulder)
Construction of granular sub-base by providing well graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with three wheel 80-100 kN static roller capacity to achieve the desired density, complete as per technical specification clause 401 grading III
Providing layer spreading and compacting graded stone aggregate to wet mix macadam specifaction inculding premixing the material with water at OMC in mechanical mixer Pug mill carring of mixed material by tipper to site, laying in uniform layers in sub base/base course on a well prepared sub -base and compacting with smooth wheel roller of 80 to 100 KN weight to achieve the desired density inculding lighting.
Providing, Laying and Spreading Base Course on a prepared surface, including mixing of 50% 22.4 mm Down Aggregate, 50% Stone Dust and 2.5% RBI -81 by mix in place with rotavator and grading with motor grader and compacting with 8-10 tonne Vibratory Compactor at OMC to the desired density as per specifications MoRTH 403
Providing and applying Primer coat with Bitumen emulsion (SS-1) using emulsion distributor at the rate of 0.70 - 1.0 kg per sqm on the prepared granular surface treated with Primer cleaned with Hydraulic broom as per Technical Specification Clause 502.
Providing and applying Tack coat with Bitumen emulsion (RS-1) using emulsion distributor at the rate of 0.25 - 0.30 kg per sqm on the prepared granular surface treated with Primer cleaned with Hydraulic broom as per Technical Specification Clause 502.
Provding, laying and rolling of Open Graded Premix Carpet of 20mm thickness composed of 13.2mm to 5.6mm aggregatees either using penetration grade bitument or emulsion to required line, grade and level to serve as wearing course on apreviously prepared bse, inculding mixing in a suitable palnt, laying and rolling with a three wheeel 80-100km staic roller capacity, finished
Providing and laying seal coat sealing the voids in a bituinous surface - laid to the specified levels, grade and cross fall using Type -A as per MORD technical Specification clause 510
Logo Board
Kilometer Stone
Hecta Meter
Sign Board
90cm Equilateral Triangle Cautionary Sign Board
Reflector
Bus Stop
Information Board
Maintenance Board
Name Board
1.A) Construction of 1.50m span RCC Slab Culvert at Ch 3940
Earth work Excavation for Foundation of structres upto 3m depth as per drawing and techincal specification Clause 1104 including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and back filling with approved material.
Providing and laying concrete for plain/ Reinforeced concrete in open foundations complete as per drawings and MORD technical specification Cuauses 802,803,1202 & 1203 M20 M20
Providing and laying concrete for plain /Rainforced Concrete in open foundations complte as per drawings and MORD technical specification clauses 802,803,1202, & 1203 M20
Below Sill
Above Sill
Supplying, fitting and placing HYSD bar reinforcement in superstructure complete as per drawing and MORD technical specification Clauses 1002, 1010 and 1202
Providing and laying concrete for Reinforced concrete in super structure complete as per drawings and MORD technical specification Clauses 800, 1205.4 & 1205.5 (RCC M25)
Providing weepholes in abutment, wing wall, return wall with 100mm dia AC pipe extending through the full widht of strucures with slope of 1(V) : 2(H) towards drawing face complete as per drawing and techinical specification
Providing and fixing 20mm thick compressible fibre board in expansion joint complete as per dreeing and technical specifications
Providing and fixing tar paper for bearing
Backfilling behaind abutment, wing wall and return wall complete as per drawing & MORD
1.B) Construction of 1.50m span RCC Slab Culvert at Ch 4145
Earth work Excavation for Foundation of structres upto 3m depth as per drawing and techincal specification Clause 1104 including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and back filling with approved material.
Providing and laying concrete for plain/ Reinforeced concrete in open foundations complete as per drawings and MORD technical specification Cuauses 802,803,1202 & 1203 M20 M20
Providing and laying concrete for plain /Rainforced Concrete in open foundations complte as per drawings and MORD technical specification clauses 802,803,1202, & 1203 M20
Below Sill
Above Sill
Supplying, fitting and placing HYSD bar reinforcement in superstructure complete as per drawing and MORD technical specification Clauses 1002, 1010 and 1202
Providing and laying concrete for Reinforced concrete in super structure complete as per drawings and MORD technical specification Clauses 800, 1205.4 & 1205.5 (RCC M25)
Providing weepholes in abutment, wing wall, return wall with 100mm dia AC pipe extending through the full widht of strucures with slope of 1(V) : 2(H) towards drawing face complete as per drawing and techinical specification
Providing and fixing 20mm thick compressible fibre board in expansion joint complete as per dreeing and technical specifications
Providing and fixing tar paper for bearing
Backfilling behaind abutment, wing wall and return wall complete as per drawing & MORD
1.C) Construction of 1.50m span RCC Slab Culvert at Ch 4220
Earth work Excavation for Foundation of structres upto 3m depth as per drawing and techincal specification Clause 1104 including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and back filling with approved material.
Providing and laying concrete for plain/ Reinforeced concrete in open foundations complete as per drawings and MORD technical specification Cuauses 802,803,1202 & 1203 M20 M20
Providing and laying concrete for plain /Rainforced Concrete in open foundations complte as per drawings and MORD technical specification clauses 802,803,1202, & 1203 M20
Below Sill
Above Sill
Supplying, fitting and placing HYSD bar reinforcement in superstructure complete as per drawing and MORD technical specification Clauses 1002, 1010 and 1202
Providing and laying concrete for Reinforced concrete in super structure complete as per drawings and MORD technical specification Clauses 800, 1205.4 & 1205.5 (RCC M25)
Providing weepholes in abutment, wing wall, return wall with 100mm dia AC pipe extending through the full widht of strucures with slope of 1(V) : 2(H) towards drawing face complete as per drawing and techinical specification
Providing and fixing 20mm thick compressible fibre board in expansion joint complete as per dreeing and technical specifications
Providing and fixing tar paper for bearing
Backfilling behaind abutment, wing wall and return wall complete as per drawing & MORD
1.D) Construction of 1.50m span RCC Slab Culvert at Ch 4300
Earth work Excavation for Foundation of structres upto 3m depth as per drawing and techincal specification Clause 1104 including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and back filling with approved material.
Providing and laying concrete for plain/ Reinforeced concrete in open foundations complete as per drawings and MORD technical specification Cuauses 802,803,1202 & 1203 M20 M20
Providing and laying concrete for plain /Rainforced Concrete in open foundations complte as per drawings and MORD technical specification clauses 802,803,1202, & 1203 M20
Below Sill
Above Sill
Supplying, fitting and placing HYSD bar reinforcement in superstructure complete as per drawing and MORD technical specification Clauses 1002, 1010 and 1202
Providing and laying concrete for Reinforced concrete in super structure complete as per drawings and MORD technical specification Clauses 800, 1205.4 & 1205.5 (RCC M25)
Providing weepholes in abutment, wing wall, return wall with 100mm dia AC pipe extending through the full widht of strucures with slope of 1(V) : 2(H) towards drawing face complete as per drawing and techinical specification
Providing and fixing 20mm thick compressible fibre board in expansion joint complete as per dreeing and technical specifications
Providing and fixing tar paper for bearing
Backfilling behaind abutment, wing wall and return wall complete as per drawing & MORD
1.E) Construction of 1.50m span RCC Slab Culvert at Ch 4590
Earth work Excavation for Foundation of structres upto 3m depth as per drawing and techincal specification Clause 1104 including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and back filling with approved material.
Providing and laying concrete for plain/ Reinforeced concrete in open foundations complete as per drawings and MORD technical specification Cuauses 802,803,1202 & 1203 M20 M20
Providing and laying concrete for plain /Rainforced Concrete in open foundations complte as per drawings and MORD technical specification clauses 802,803,1202, & 1203 M20
Below Sill
Above Sill
Supplying, fitting and placing HYSD bar reinforcement in superstructure complete as per drawing and MORD technical specification Clauses 1002, 1010 and 1202
Providing and laying concrete for Reinforced concrete in super structure complete as per drawings and MORD technical specification Clauses 800, 1205.4 & 1205.5 (RCC M25)
Providing weepholes in abutment, wing wall, return wall with 100mm dia AC pipe extending through the full widht of strucures with slope of 1(V) : 2(H) towards drawing face complete as per drawing and techinical specification
Providing and fixing 20mm thick compressible fibre board in expansion joint complete as per dreeing and technical specifications
Providing and fixing tar paper for bearing
Backfilling behaind abutment, wing wall and return wall complete as per drawing & MORD
1.F) Construction of 1.50m span RCC Slab Culvert at Ch 4760
Earth work Excavation for Foundation of structres upto 3m depth as per drawing and techincal specification Clause 1104 including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and back filling with approved material.
Providing and laying concrete for plain/ Reinforeced concrete in open foundations complete as per drawings and MORD technical specification Cuauses 802,803,1202 & 1203 M20 M20
Providing and laying concrete for plain /Rainforced Concrete in open foundations complte as per drawings and MORD technical specification clauses 802,803,1202, & 1203 M20
Below Sill
Above Sill
Supplying, fitting and placing HYSD bar reinforcement in superstructure complete as per drawing and MORD technical specification Clauses 1002, 1010 and 1202
Providing and laying concrete for Reinforced concrete in super structure complete as per drawings and MORD technical specification Clauses 800, 1205.4 & 1205.5 (RCC M25)
Providing weepholes in abutment, wing wall, return wall with 100mm dia AC pipe extending through the full widht of strucures with slope of 1(V) : 2(H) towards drawing face complete as per drawing and techinical specification
Providing and fixing 20mm thick compressible fibre board in expansion joint complete as per dreeing and technical specifications
Providing and fixing tar paper for bearing
Backfilling behaind abutment, wing wall and return wall complete as per drawing & MORD
1.G) Construction of 1.50m span RCC Slab Culvert at Ch 5025
Earth work Excavation for Foundation of structres upto 3m depth as per drawing and techincal specification Clause 1104 including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and back filling with approved material.
Providing and laying concrete for plain/ Reinforeced concrete in open foundations complete as per drawings and MORD technical specification Cuauses 802,803,1202 & 1203 M20 M20
Providing and laying concrete for plain /Rainforced Concrete in open foundations complte as per drawings and MORD technical specification clauses 802,803,1202, & 1203 M20
Below Sill
Above Sill
Supplying, fitting and placing HYSD bar reinforcement in superstructure complete as per drawing and MORD technical specification Clauses 1002, 1010 and 1202
Providing and laying concrete for Reinforced concrete in super structure complete as per drawings and MORD technical specification Clauses 800, 1205.4 & 1205.5 (RCC M25)
Providing weepholes in abutment, wing wall, return wall with 100mm dia AC pipe extending through the full widht of strucures with slope of 1(V) : 2(H) towards drawing face complete as per drawing and techinical specification
Providing and fixing 20mm thick compressible fibre board in expansion joint complete as per dreeing and technical specifications
Providing and fixing tar paper for bearing
Backfilling behaind abutment, wing wall and return wall complete as per drawing & MORD
1.H) Construction of 1.50m span RCC Slab Culvert at Ch 5140
Earth work Excavation for Foundation of structres upto 3m depth as per drawing and techincal specification Clause 1104 including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and back filling with approved material.
Providing and laying concrete for plain/ Reinforeced concrete in open foundations complete as per drawings and MORD technical specification Cuauses 802,803,1202 & 1203 M20 M20
Providing and laying concrete for plain /Rainforced Concrete in open foundations complte as per drawings and MORD technical specification clauses 802,803,1202, & 1203 M20
Below Sill
Above Sill
Supplying, fitting and placing HYSD bar reinforcement in superstructure complete as per drawing and MORD technical specification Clauses 1002, 1010 and 1202
Providing and laying concrete for Reinforced concrete in super structure complete as per drawings and MORD technical specification Clauses 800, 1205.4 & 1205.5 (RCC M25)
Providing weepholes in abutment, wing wall, return wall with 100mm dia AC pipe extending through the full widht of strucures with slope of 1(V) : 2(H) towards drawing face complete as per drawing and techinical specification
Providing and fixing 20mm thick compressible fibre board in expansion joint complete as per dreeing and technical specifications
Providing and fixing tar paper for bearing
Backfilling behaind abutment, wing wall and return wall complete as per drawing & MORD
1.I) Construction of 1.50m span RCC Slab Culvert at Ch 5710
Earth work Excavation for Foundation of structres upto 3m depth as per drawing and techincal specification Clause 1104 including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and back filling with approved material.
Providing and laying concrete for plain/ Reinforeced concrete in open foundations complete as per drawings and MORD technical specification Cuauses 802,803,1202 & 1203 M20 M20
Providing and laying concrete for plain /Rainforced Concrete in open foundations complte as per drawings and MORD technical specification clauses 802,803,1202, & 1203 M20
Below Sill
Above Sill
Supplying, fitting and placing HYSD bar reinforcement in superstructure complete as per drawing and MORD technical specification Clauses 1002, 1010 and 1202
Providing and laying concrete for Reinforced concrete in super structure complete as per drawings and MORD technical specification Clauses 800, 1205.4 & 1205.5 (RCC M25)
Providing weepholes in abutment, wing wall, return wall with 100mm dia AC pipe extending through the full widht of strucures with slope of 1(V) : 2(H) towards drawing face complete as per drawing and techinical specification
Providing and fixing 20mm thick compressible fibre board in expansion joint complete as per dreeing and technical specifications
Providing and fixing tar paper for bearing
Backfilling behaind abutment, wing wall and return wall complete as per drawing & MORD
1.J) Construction of 1.50m span RCC Slab Culvert at Ch 6120
Earth work Excavation for Foundation of structres upto 3m depth as per drawing and techincal specification Clause 1104 including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and back filling with approved material.
Providing and laying concrete for plain/ Reinforeced concrete in open foundations complete as per drawings and MORD technical specification Cuauses 802,803,1202 & 1203 M20 M20
Providing and laying concrete for plain /Rainforced Concrete in open foundations complte as per drawings and MORD technical specification clauses 802,803,1202, & 1203 M20
Below Sill
Above Sill
Supplying, fitting and placing HYSD bar reinforcement in superstructure complete as per drawing and MORD technical specification Clauses 1002, 1010 and 1202
Providing and laying concrete for Reinforced concrete in super structure complete as per drawings and MORD technical specification Clauses 800, 1205.4 & 1205.5 (RCC M25)
Providing weepholes in abutment, wing wall, return wall with 100mm dia AC pipe extending through the full widht of strucures with slope of 1(V) : 2(H) towards drawing face complete as per drawing and techinical specification
Providing and fixing 20mm thick compressible fibre board in expansion joint complete as per dreeing and technical specifications
Providing and fixing tar paper for bearing
Backfilling behaind abutment, wing wall and return wall complete as per drawing & MORD
1.K) Construction of 1.50m span RCC Slab Culvert at Ch 6610
Earth work Excavation for Foundation of structres upto 3m depth as per drawing and techincal specification Clause 1104 including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and back filling with approved material.
Providing and laying concrete for plain/ Reinforeced concrete in open foundations complete as per drawings and MORD technical specification Cuauses 802,803,1202 & 1203 M20 M20
Providing and laying concrete for plain /Rainforced Concrete in open foundations complte as per drawings and MORD technical specification clauses 802,803,1202, & 1203 M20
Below Sill
Above Sill
Supplying, fitting and placing HYSD bar reinforcement in superstructure complete as per drawing and MORD technical specification Clauses 1002, 1010 and 1202
Providing and laying concrete for Reinforced concrete in super structure complete as per drawings and MORD technical specification Clauses 800, 1205.4 & 1205.5 (RCC M25)
Providing weepholes in abutment, wing wall, return wall with 100mm dia AC pipe extending through the full widht of strucures with slope of 1(V) : 2(H) towards drawing face complete as per drawing and techinical specification
Providing and fixing 20mm thick compressible fibre board in expansion joint complete as per dreeing and technical specifications
Providing and fixing tar paper for bearing
Backfilling behaind abutment, wing wall and return wall complete as per drawing & MORD
1.L) Construction of 1.50m span RCC Slab Culvert at Ch 6700
Earth work Excavation for Foundation of structres upto 3m depth as per drawing and techincal specification Clause 1104 including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and back filling with approved material.
Providing and laying concrete for plain/ Reinforeced concrete in open foundations complete as per drawings and MORD technical specification Cuauses 802,803,1202 & 1203 M20 M20
Providing and laying concrete for plain /Rainforced Concrete in open foundations complte as per drawings and MORD technical specification clauses 802,803,1202, & 1203 M20
Below Sill
Above Sill
Supplying, fitting and placing HYSD bar reinforcement in superstructure complete as per drawing and MORD technical specification Clauses 1002, 1010 and 1202
Providing and laying concrete for Reinforced concrete in super structure complete as per drawings and MORD technical specification Clauses 800, 1205.4 & 1205.5 (RCC M25)
Providing weepholes in abutment, wing wall, return wall with 100mm dia AC pipe extending through the full widht of strucures with slope of 1(V) : 2(H) towards drawing face complete as per drawing and techinical specification
Providing and fixing 20mm thick compressible fibre board in expansion joint complete as per dreeing and technical specifications
Providing and fixing tar paper for bearing
Backfilling behaind abutment, wing wall and return wall complete as per drawing & MORD
1.M) Construction of 1.50m span RCC Slab Culvert at Ch 6825
Earth work Excavation for Foundation of structres upto 3m depth as per drawing and techincal specification Clause 1104 including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and back filling with approved material.
Providing and laying concrete for plain/ Reinforeced concrete in open foundations complete as per drawings and MORD technical specification Cuauses 802,803,1202 & 1203 M20 M20
Providing and laying concrete for plain /Rainforced Concrete in open foundations complte as per drawings and MORD technical specification clauses 802,803,1202, & 1203 M20
Below Sill
Above Sill
Supplying, fitting and placing HYSD bar reinforcement in superstructure complete as per drawing and MORD technical specification Clauses 1002, 1010 and 1202
Providing and laying concrete for Reinforced concrete in super structure complete as per drawings and MORD technical specification Clauses 800, 1205.4 & 1205.5 (RCC M25)
Providing weepholes in abutment, wing wall, return wall with 100mm dia AC pipe extending through the full widht of strucures with slope of 1(V) : 2(H) towards drawing face complete as per drawing and techinical specification
Providing and fixing 20mm thick compressible fibre board in expansion joint complete as per dreeing and technical specifications
Providing and fixing tar paper for bearing
Backfilling behaind abutment, wing wall and return wall complete as per drawing & MORD
1.N) Construction of 1.50m span RCC Slab Culvert at Ch 5810
Earth work Excavation for Foundation of structres upto 3m depth as per drawing and techincal specification Clause 1104 including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and back filling with approved material.
Providing and laying concrete for plain/ Reinforeced concrete in open foundations complete as per drawings and MORD technical specification Cuauses 802,803,1202 & 1203 M20 M20
Providing and laying concrete for plain /Rainforced Concrete in open foundations complte as per drawings and MORD technical specification clauses 802,803,1202, & 1203 M20
Below Sill
Above Sill
Supplying, fitting and placing HYSD bar reinforcement in superstructure complete as per drawing and MORD technical specification Clauses 1002, 1010 and 1202
Providing and laying concrete for Reinforced concrete in super structure complete as per drawings and MORD technical specification Clauses 800, 1205.4 & 1205.5 (RCC M25)
Providing weepholes in abutment, wing wall, return wall with 100mm dia AC pipe extending through the full widht of strucures with slope of 1(V) : 2(H) towards drawing face complete as per drawing and techinical specification
Providing and fixing 20mm thick compressible fibre board in expansion joint complete as per dreeing and technical specifications
Providing and fixing tar paper for bearing
Backfilling behaind abutment, wing wall and return wall complete as per drawing & MORD
1.O) Construction of CC Pavement @ Ch 5440 - 5500
Providing and laying concrete for plain/ Reinforeced concrete in open foundations complete as per drawings and MORD technical specification Cuauses 802,803,1202 & 1203 M20 M20
Construction of un-reinforced, dowel jointed at expansion and construction joint only, plain cement concrete pavement, thickness as per design, over a prepared sub base, with 43 grade cement or any other type as per Clause 1501.2.2 M30 (Grade), coarse and fine aggregates conforming to IS:383, maximum size of coarse aggregate not exceeding 25 mm, mixed in a concrete mixer of not less than 0.2 cum capacity and appropriate weigh batcher using approved mix design, laid in approved fixed side formwork (steel channel, laying and fixing of 125 micron thick polythene film, wedges, steel plates including levelling the formwork as per drawing), spreading the concrete with shovels, rakes, compacted using needle, screed and plate vibrators and finished in continuous operation including provision of contraction and expansion, construction joints, applying debonding strips, primer, sealant, dowel bars, near approaches to bridge/culvert and construction joints, admixtures as approved, curing of concrete slabs for 14-days,using curing compound (where specified ) and water finishing to lines and grade as per drawing and Technical Specification Clause 1501
Providing and fixing 20mm thick compressible fibre board in expansion joint complete as per dreeing and technical specifications
1.P) Construction of Protection Wall Km 3/840 - 4/0
Earthwork in excavation for structures as per drawing and technical specifications Clause 305.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious material and disposal upto a lead of 50 m, dressing of sides and bottom and backfilling in trenches with excavated suitable material.
Providing and laying concrete for plain/ Reinforeced concrete in open foundations complete as per drawings and MORD technical specification Cuauses 802,803,1202 & 1203 M15
Srone Masonry Work in Cement Mortar in Foundation of Head Walls Complete as per drawing and MORD Technical Specification Clause 1109 in Cement Mortar 1:5
Dry Stone Masonry for Retaining Wall -10 cum including Cost and Conveyance of all Materials and all labour Charges etc complete.
Plastering With Cement Mortar (1:4) , 15 mm Thick on brick work in substructure as per Technical Specification Clauses613.4 & 1204
1.P) Construction of Protection Wall Km 4/0 - 5/0
Earthwork in excavation for structures as per drawing and technical specifications Clause 305.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious material and disposal upto a lead of 50 m, dressing of sides and bottom and backfilling in trenches with excavated suitable material.
Providing and laying concrete for plain/ Reinforeced concrete in open foundations complete as per drawings and MORD technical specification Cuauses 802,803,1202 & 1203 M15
Srone Masonry Work in Cement Mortar in Foundation of Head Walls Complete as per drawing and MORD Technical Specification Clause 1109 in Cement Mortar 1:5
Dry Stone Masonry for Retaining Wall -10 cum including Cost and Conveyance of all Materials and all labour Charges etc complete.
Plastering With Cement Mortar (1:4) , 15 mm Thick on brick work in substructure as per Technical Specification Clauses613.4 & 1204
1.Q) Construction of Protection Wall Km 5/0 - 6/0
Earthwork in excavation for structures as per drawing and technical specifications Clause 305.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious material and disposal upto a lead of 50 m, dressing of sides and bottom and backfilling in trenches with excavated suitable material.
Providing and laying concrete for plain/ Reinforeced concrete in open foundations complete as per drawings and MORD technical specification Cuauses 802,803,1202 & 1203 M15
Srone Masonry Work in Cement Mortar in Foundation of Head Walls Complete as per drawing and MORD Technical Specification Clause 1109 in Cement Mortar 1:5
Dry Stone Masonry for Retaining Wall -10 cum including Cost and Conveyance of all Materials and all labour Charges etc complete.
Plastering With Cement Mortar (1:4) , 15 mm Thick on brick work in substructure as per Technical Specification Clauses613.4 & 1204
1.R) Construction of Protection Wall Km 6/0 - 7/0
Earthwork in excavation for structures as per drawing and technical specifications Clause 305.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious material and disposal upto a lead of 50 m, dressing of sides and bottom and backfilling in trenches with excavated suitable material.
Providing and laying concrete for plain/ Reinforeced concrete in open foundations complete as per drawings and MORD technical specification Cuauses 802,803,1202 & 1203 M15
Srone Masonry Work in Cement Mortar in Foundation of Head Walls Complete as per drawing and MORD Technical Specification Clause 1109 in Cement Mortar 1:5
Dry Stone Masonry for Retaining Wall -10 cum including Cost and Conveyance of all Materials and all labour Charges etc complete.
Plastering With Cement Mortar (1:4) , 15 mm Thick on brick work in substructure as per Technical Specification Clauses613.4 & 1204
1.S) Construction of Protection Wall Km 7/0 - 7/335
Earthwork in excavation for structures as per drawing and technical specifications Clause 305.1 including setting out, construction of shoring and bracing, removal of stumps and other deleterious material and disposal upto a lead of 50 m, dressing of sides and bottom and backfilling in trenches with excavated suitable material.
Providing and laying concrete for plain/ Reinforeced concrete in open foundations complete as per drawings and MORD technical specification Cuauses 802,803,1202 & 1203 M15
Srone Masonry Work in Cement Mortar in Foundation of Head Walls Complete as per drawing and MORD Technical Specification Clause 1109 in Cement Mortar 1:5
Dry Stone Masonry for Retaining Wall -10 cum including Cost and Conveyance of all Materials and all labour Charges etc complete.
Plastering With Cement Mortar (1:4) , 15 mm Thick on brick work in substructure as per Technical Specification Clauses613.4 & 1204
Routine Maintenance after completion of work the road sufrace and shoulder to be maintained in proper condition to make them free from excessive edge drop offs, roughness, scouring and pot holes and cleaning of surface drain including culverts for frre flow of water. Relettering name boards and K.M & H.M stone and other maintenance operation required to keep the road traffic worthly at all the time for the maintenance period for the following years. As per General condition of contract para 32.2.2
For 1st Year
For 2nd Year
For 3rd Year
For 4th Year
For 5th Year
GST Amount for providing Service to Government Contract Works for the above Construction & Maintenance Works. { GST Amount is the Total GST Amount for overall quoted amount (Both Construction and Maintenance) above this row in column "BB" for all works in this package} (Refer Clause 13.2 & 13.3 of Section 2 of Instruction to Bidders (ITB) of SBD)
SR INFRAA
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .