Loading…
Loading…
| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹12.5 LAccepted-Finance 50 PAJANI MADAM KURUN THERU KOTTAR NAGERCOIL | ₹12.5 L | L1 | Accepted-Finance Lowest amount Quated |
| 2 | L2₹12.8 LRejected-Finance | ₹12.8 L | L2 | Rejected-Finance Amount Exceed |
| 3 | Rejected-Technical 648 GANDHI NAGER ERACHAKULAM | - | - | Rejected-Technical L2 |
| Sl No | Description | Qty | Unit | G. Sahayarajan L1 | C.SUGANTHAN WORKS CONTRACTOR L3 | SPSM ENGINEERING CONSTRUCTION L2 |
|---|---|---|---|---|---|---|
| 1.00Construction of Retaining wall (90m) for Preventing the seepage water of Thovalai channel and Providing cement concrete pavement (135m ) at Chembainager road in madavalayam Village panchayat. | ||||||
| 2.00 | Earth work excavation for foundation in all soils and subsoils to full depth as may be directed except in hard rock requiring blasting but inclusive of shoring strutting and bailing out water wherever necessary and refilling the sides of foundation with excavated earth in layersw of not more than 15cm thick well rammed and consolidated and depositing the surplus earth in all places shown by departmental officers with initial leae and lift etc, complete complying with standard specifiacfion and as directed. | 64.8 | cum | 230.81 ₹14,956.49 | 263.25 ₹17,058.60 | 235 ₹15,228 |
| 3.00 | Cement concrete 1:4:8 mix using 40mm gauge hand broken granite stone jelly for foundation including watering wherever necessary and laid in layers not more than 15cm thick completed etc, complete complying with standard specification and as directed. | 63.99 | Cum | 4,634.94 ₹3.0 L | 5,286.48 ₹3.4 L | 4,714 ₹3.0 L |
| 4.00 | Supplying and erecting for sides and soffits including supports and strutting for plane surfaces in all cross bracing using mild steel sheets of size 90x60cm and 10 gauge stiffered welded with mild angles of size 25x25x3mm for boarding laid over silver oak joists of size 10cmx65cm dia spaced at 75cm centre to centre etc, complete complying with standard specification and as directed for the following items, Core wall | 128.25 | sqm | 131.25 ₹16,832.81 | 149.7 ₹19,199.03 | 134 ₹17,185.50 |
| 5.00 | Supplying and erecting for sides and soffits including supports and strutting for plane surfaces in all cross bracing using mild steel sheets of size 90x60cm and 10 gauge stiffered welded with mild angles of size 25x25x3mm for boarding laid over silver oak joists of size 10cmx65cm dia spaced at 75cm centre to centre etc, complete complying with standard specification and as directed for the following items, Retaining wall | 225 | sqm | 479.06 ₹1.1 L | 546.41 ₹1.2 L | 488 ₹1.1 L |
| 6.00 | Cement concrete 1:3:6 mix using 40mm gauge hand broken granite stone jelly for foundation including watering wherever necessary and laid in layers not more than 15cm thick completed etc, complete complying with standard specification and as directed. | 68.18 | cum | 4,871.19 ₹3.3 L | 5,555.94 ₹3.8 L | 4,955 ₹3.4 L |
| 7.00 | Cement concrete 1:3:6 mix using 20mm gauge hand broken granite stone jelly for foundation including watering wherever necessary and laid in layers not more than 15cm thick completed etc, complete complying with standard specification and as directed. | 12.42 | cum | 5,292.11 ₹65,728.01 | 6,036.02 ₹74,967.37 | 5,383 ₹66,856.86 |
| 8.00 | Cement concrete 1:2:4 mix using 20mm gauge hand broken granite stone jelly for foundation including watering wherever necessary and laid in layers not more than 15cm thick completed etc, complete complying with standard specification and as directed. | 37.46 | Cum | 5,764.61 ₹2.2 L | 6,574.94 ₹2.5 L | 5,864 ₹2.2 L |
| 9.00 | Plastering with Cement Mortar 1:5 (One cement and Five P.Sand), 12mm thick in all floors including curing etc. complete complying with standard specification and as directed by the departmental officers. | 40.5 | sqm | 246.69 ₹9,990.95 | 281.37 ₹11,395.49 | 251 ₹10,165.50 |
| 10.00 | Provision for tar pad arrangement | 13.5 | sqm | 205.01 ₹2,767.64 | 233.83 ₹3,156.71 | 209 ₹2,821.50 |
Tender Value
₹14.5 L
EMD Value
₹14,500
Closing Date
20 Feb 2026, 3:00 pmClosed
Block Development Officer(B.Pt)
Block Development Officer(B.Pt) Thovalai Panchayat Union @ Bhoothapandy
Construction of Retaining wall (90m) for Preventing the seepage water of Thovalai channel and Providing cement concrete pavement (135m ) at Chembainager road in madavalayam Village panchayat
2026_RDTN_657023_1
A2/323/2026
Open Tender
Civil Works
Construction of Retaining wall (90m) for Preven
Please refer Tender documents.
3 documents required · 3 mandatory
₹0
₹14,500
Yes
17 Apr 2026
13 Feb 2026
20 Feb 2026
13 Feb 2026
20 Feb 2026
13 Feb 2026
Construction of Retaining wall (90m) for Preventing the seepage water of Thovalai channel and Providing cement concrete pavement (135m ) at Chembainager road in madavalayam Village panchayat.
Earth work excavation for foundation in all soils and subsoils to full depth as may be directed except in hard rock requiring blasting but inclusive of shoring strutting and bailing out water wherever necessary and refilling the sides of foundation with excavated earth in layersw of not more than 15cm thick well rammed and consolidated and depositing the surplus earth in all places shown by departmental officers with initial leae and lift etc, complete complying with standard specifiacfion and as directed.
Cement concrete 1:4:8 mix using 40mm gauge hand broken granite stone jelly for foundation including watering wherever necessary and laid in layers not more than 15cm thick completed etc, complete complying with standard specification and as directed.
Supplying and erecting for sides and soffits including supports and strutting for plane surfaces in all cross bracing using mild steel sheets of size 90x60cm and 10 gauge stiffered welded with mild angles of size 25x25x3mm for boarding laid over silver oak joists of size 10cmx65cm dia spaced at 75cm centre to centre etc, complete complying with standard specification and as directed for the following items, Core wall
Supplying and erecting for sides and soffits including supports and strutting for plane surfaces in all cross bracing using mild steel sheets of size 90x60cm and 10 gauge stiffered welded with mild angles of size 25x25x3mm for boarding laid over silver oak joists of size 10cmx65cm dia spaced at 75cm centre to centre etc, complete complying with standard specification and as directed for the following items, Retaining wall
Cement concrete 1:3:6 mix using 40mm gauge hand broken granite stone jelly for foundation including watering wherever necessary and laid in layers not more than 15cm thick completed etc, complete complying with standard specification and as directed.
Cement concrete 1:3:6 mix using 20mm gauge hand broken granite stone jelly for foundation including watering wherever necessary and laid in layers not more than 15cm thick completed etc, complete complying with standard specification and as directed.
Cement concrete 1:2:4 mix using 20mm gauge hand broken granite stone jelly for foundation including watering wherever necessary and laid in layers not more than 15cm thick completed etc, complete complying with standard specification and as directed.
Plastering with Cement Mortar 1:5 (One cement and Five P.Sand), 12mm thick in all floors including curing etc. complete complying with standard specification and as directed by the departmental officers.
Provision for tar pad arrangement
GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column "BB" for all works in this package}
Please Enable Macros to View BoQ information
stage.html
html • 0.03 MB
tech_eval.pdf
fin_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.37 MB
Tendernotice_2.pdf
PDF • 0.23 MB
BOQ_787921.xls
BOQ • 0.32 MB
Download all tender documents and submit your bid