| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹54.8 LAccepted-AOC | ₹54.8 L | L1 | Accepted-AOC Bid Accepted. Hence, Lowest Bidder L1 |
| 2 | L2₹55.9 LRejected-AOC | ₹55.9 L | L2 | Rejected-AOC Bid Rejected. Hence, Highest Bidder L2. |
| 3 | Rejected-Technical | - | - | Rejected-Technical Bidder Withdrawn his Bid |
| Sl No | Description | Qty | Unit | Arputham infrastructures L1 | MARUTHI AND CO L2 |
|---|---|---|---|---|---|
| 1.00 | Upgradation of road from Thungavi UDT to Dharapuram Road Kottamangalan Road Via Kumaramangalam 0/0-1/0 R-238
Construction Work
Clearing the light/scrub jungle by uprooting including all cutting charges and disposing of the products and clearing as directed by departmental officers including all incidental charges etc. complete.
MORD Specification 111, 112, 201 | 1,200 | Sqm | 6.3 ₹7,560 Lowest | 7.5 ₹9,000 |
| 2.00 | Earth work excavation and depositing on back with an initial of 10m and lift 2m in sand, silt or other loose soil, wet sand or silt not under water, light black cotton soil, sandy loam and ordinary soil including excavated earth etc., as per SS 20 B including laying and spreading in layers of 250 mm loose thick each, sectioning , watering and compacting by Power roller to achieve the required Proctor density at 100% compaction at optimum moisture content as determined in occurrence with complete as per MoRD 111, 112, 202, 900, 301, 304 | 540 | Cum | 140.3 ₹75,762 Lowest | 145 ₹78,300 |
| 3.00 | Providing and laying Gravel including cost and conveyance of gravel from approved sources to work site including labour for spreading , watering and compacting by power roller to achieve the required protect density at 100% compaction at optimum moisture content and hire & fuel charges for power roller, water sprinkler and all other incidental charges such as traffic barricading and providing danger lights etc., complete. MORD Specification 111, 112, 401, 900 Km 0/0 - 1/0 | 299.13 | Cum | 741.65 ₹2,21,849.76 Lowest | 770 ₹2,30,330.1 |
| 4.00 | Wet Mix Macadam
Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the material with water at OMC in mechanical mixer (Pug Mill), carriage of mixed material by tipper to site, laying in uniform layers in subbase/base course on a well prepared sub-base and compacting with smooth wheel roller of 80 to 100kN weight to achieve the desired density including lighting, barricading and maintenance of diversion, etc as per Tables 400.11 & 400.12 and Technical Specification Clause 406. | 579.34 | Cum | 2,602.7 ₹15,07,848.22 Lowest | 2,650 ₹15,35,251 |
| 5.00 | Providing and applying Primer coat with bitumen emulsion (SS-1) on prepared surface of granular base including cleaning of road surface and spraying primer at the rate of 0.70 kg/sqm using mechanical means as per Technical Specification Clause 502 | 3,862.25 | Sqm | 89.5 ₹3,45,671.38 Lowest | 91 ₹3,51,464.75 |
| 6.00 | Providing and applying Tack coat with Bitumen emulsion (RS-1) using emulsion pressure distributor at the rate of 0.25 kg per sqm on the prepared granular surface treated with Primer cleaned with Hydraulic broom as per Technical Specification Clause 503.4 | 3,873.13 | Sqm | 21.12 ₹81,800.51 Lowest | 22 ₹85,208.86 |
| 7.00 | Bituminous Concrete (BC)
Providing BC 30 mm Thick (GradeII) Using VG30 Bitumen Providing and laying Bituminous Concrete to 25 mm thick using 0.13 cum of 19.00- 9.50mm, 0.17 cum of 9.50-2.36mm and 0.26 cum of 2.36 and below with 47.28kgs of VG30 bitumen and 3.02Kgs of Waste Plastic for premixing per 10sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 30mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonne Vibratory to the required density etc., including labour for attending to paver to site etc., including hire charges and fuel charges for 20-30 t CMP with bitumen boiler, tipper trucks, Paver Finisher, Vibratory roller and all other tools and plant required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clause 507 of MORTH Rev-5 | 96.83 | Cum | 11,829.66 ₹11,45,465.98 Lowest | 12,000 ₹11,61,960 |
| 8.00 | Construction of 1.50m Span RCC slab culvert
Earth work excavation for foundation of structures up to 3m depth as per drawing and technical specification Clause 1104 including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and back filling with approved material. | 79.8 | Cum | 263.78 ₹21,049.64 Lowest | 280 ₹22,344 |
| 9.00 | Cement concrete 1:4:8 mix using HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed. | 10.29 | Cum | 5,839.05 ₹60,083.82 Lowest | 6,000 ₹61,740 |
| 10.00 | Cement concrete 1:3:6 mix using HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed. | 86.93 | Cum | 6,629.59 ₹5,76,310.26 Lowest | 6,800 ₹5,91,124 |
Tender Value
₹51.0 L
EMD Value
₹51,000
Closing Date
19 Feb 2026, 3:00 pmClosed
The Project Director, DRDA, Tiruppur
DRDA, Tiruppur
Strengthening/Upgradation BT to the Roads in Madathukulam Block of Tiruppur District 10/NABARD-RIDF/2026-27.
2026_RDTN_657452_8
DIPR.1031/Tender/2026, dated . 13.02.2026
Open Tender
Civil Works - Roads
Item Wise
180 days
Tiruppur
Please Refer Tender Documents
6 documents required · 6 mandatory
₹0
₹51,000
DRDA, Tiruppur
18 Mar 2026
14 Feb 2026
19 Feb 2026
14 Feb 2026
19 Feb 2026
14 Feb 2026
16 Feb 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Upgradation of road from Thungavi UDT to Dharapuram Road Kottamangalan Road Via Kumaramangalam 0/0-1/0 R-238
Construction Work
Clearing the light/scrub jungle by uprooting including all cutting charges and disposing of the products and clearing as directed by departmental officers including all incidental charges etc. complete.
MORD Specification 111, 112, 201 | 1,200 | Sqm | - | - |
| 2 | Earth work excavation and depositing on back with an initial of 10m and lift 2m in sand, silt or other loose soil, wet sand or silt not under water, light black cotton soil, sandy loam and ordinary soil including excavated earth etc., as per SS 20 B including laying and spreading in layers of 250 mm loose thick each, sectioning , watering and compacting by Power roller to achieve the required Proctor density at 100% compaction at optimum moisture content as determined in occurrence with complete as per MoRD 111, 112, 202, 900, 301, 304 | 540 | Cum | - | - |
| 3 | Providing and laying Gravel including cost and conveyance of gravel from approved sources to work site including labour for spreading , watering and compacting by power roller to achieve the required protect density at 100% compaction at optimum moisture content and hire & fuel charges for power roller, water sprinkler and all other incidental charges such as traffic barricading and providing danger lights etc., complete. MORD Specification 111, 112, 401, 900 Km 0/0 - 1/0 | 299.13 | Cum | - | - |
| 4 | Wet Mix Macadam
Providing, laying, spreading and compacting graded stone aggregate to wet mix macadam specification including premixing the material with water at OMC in mechanical mixer (Pug Mill), carriage of mixed material by tipper to site, laying in uniform layers in subbase/base course on a well prepared sub-base and compacting with smooth wheel roller of 80 to 100kN weight to achieve the desired density including lighting, barricading and maintenance of diversion, etc as per Tables 400.11 & 400.12 and Technical Specification Clause 406. | 579.34 | Cum | - | - |
| 5 | Providing and applying Primer coat with bitumen emulsion (SS-1) on prepared surface of granular base including cleaning of road surface and spraying primer at the rate of 0.70 kg/sqm using mechanical means as per Technical Specification Clause 502 | 3,862.25 | Sqm | - | - |
| 6 | Providing and applying Tack coat with Bitumen emulsion (RS-1) using emulsion pressure distributor at the rate of 0.25 kg per sqm on the prepared granular surface treated with Primer cleaned with Hydraulic broom as per Technical Specification Clause 503.4 | 3,873.13 | Sqm | - | - |
| 7 | Bituminous Concrete (BC)
Providing BC 30 mm Thick (GradeII) Using VG30 Bitumen Providing and laying Bituminous Concrete to 25 mm thick using 0.13 cum of 19.00- 9.50mm, 0.17 cum of 9.50-2.36mm and 0.26 cum of 2.36 and below with 47.28kgs of VG30 bitumen and 3.02Kgs of Waste Plastic for premixing per 10sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 30mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonne Vibratory to the required density etc., including labour for attending to paver to site etc., including hire charges and fuel charges for 20-30 t CMP with bitumen boiler, tipper trucks, Paver Finisher, Vibratory roller and all other tools and plant required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clause 507 of MORTH Rev-5 | 96.83 | Cum | - | - |
| 8 | Construction of 1.50m Span RCC slab culvert
Earth work excavation for foundation of structures up to 3m depth as per drawing and technical specification Clause 1104 including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and back filling with approved material. | 79.8 | Cum | - | - |
| 9 | Cement concrete 1:4:8 mix using HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed. | 10.29 | Cum | - | - |
| 10 | Cement concrete 1:3:6 mix using HBG metal for foundation including watering wherever necessary and laid in layers of not more than 15cm thick., compacting etc., complete complying with standard specifications and as directed. | 86.93 | Cum | - | - |
stage.html
html • 0.04 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 0.24 MB
BOQ_788555.xls
BOQ • 0.34 MB
TB10.pdf
Tender Documents • 1.25 MB
PB10.pdf
Tender Documents • 0.82 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at [email protected].