| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹3.8 CrAdmitted-Finance | -26.99% | ₹3.8 Cr | L1 | Admitted-Finance |
| 2 | L2₹4.0 CrAdmitted-Finance | -24.25% | ₹4.0 Cr | L2 | Admitted-Finance |
| 3 | L3₹5.6 CrAdmitted-Finance | +6.99% | ₹5.6 Cr | L3 | Admitted-Finance |
Tender Value
₹5.2 Cr
EMD Value
₹10.5 L
Closing Date
28 Jan 2026, 3:00 pmClosed
EXECUTIVE ENGINEER CD IV
CIVIL DIVISION IV IFC LM BUND OFFICE COMPLEX DELHI
Construction of damaged boundary wall (precast wall) along Both Bank of Karawal Nagar Drain between RD-0m to RD-2480m for the year 2025-26.
2026_IFC_285012_1
133/EE/CD-IV/IFC/2025-26
Open Tender
Civil Works
210 days
EAST
Please refer to Tender Documents
6 documents required · 6 mandatory
₹0
₹10.5 L
29 Jan 2026
16 Jan 2026
28 Jan 2026
16 Jan 2026
28 Jan 2026
16 Jan 2026
Deploying of Mobile crane on hire basis including driver, fuel, lubricants and hleper complete for cinducting of various work i.e. lifting of truss, pasting & demolishing work, steel work and erection of poles etc. as per direction of Engineer-In-Charge.
Demolishing brick work manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge. In cement mortar.
Demolishing stone rubble masonry manually/ by mechanical means including stacking of serviceable material and disposal of unserviceable material within 50 metres lead as per direction of Engineer-in-charge : In cement mortar
Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and disposal of excavated earth lead upto 50 m and lift upto 1.5 m, as directed by Engineer-in-charge. All kinds of soil
Boring with hydraulic piling rigs with power units, Providing and installing cast in situ single under reamed piles of specified diameter and length below pile cap in M-30 cement concrete, to carry a safe working load not less than specified, excluding the cost of steel reinforcement but including the cost of boring with bentonite solution and the length of the pile to be embedded in pile cap etc. all complete. (Length of pile for payment shall be measured upto to the bottom of pile cap)
Vertical load testing of piles in accordance with IS 2911 (Part IV) including installation of loading platform by Kentledge/Anchor piles method and preparation of pile head or construction of test cap and dismantling of test cap after test etc. complete as per specification & the direction of Engineer in-charge.Note: 1. Initial and Routine Load Test shall not be carried out by Dynamic method of testing.Note: 2. Testing agency shall submitt the design of loading platform for the approval of Engineer-in-charge.Single pile upto 50 tonne Safe capacity.Routine test (Test Load 1.5 times the Safe capacity.
Centering and shuttering including strutting, propping etc. and removal of form for all heights :Foundations, footings, bases of columns, etc. for mass concrete.
Centering and shuttering including strutting, propping etc. and removal of form for all heights :Lintels, beams, plinth beams, girders, bressumers and cantilevers.
Centering and shuttering including strutting, propping etc. and removal of form for all heights :Columns, Pillars, Piers, Abutments, Posts and Struts.
Providing and laying in position cement concrete of specified grade excluding the cost of centering and shuttering - All work up to plinth level :1:4:8 (1 Cement : 4 coarse sand (zone-III) : 8 graded stone aggregate 40 mm nominal size)
Providing and laying RMC of M-30 grade By using minimum 400kg of cement(43 grade, OPC) per cum of concrete in reinforced cement concrete work in walls (any thickness), including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. above plinth level up to floor five level, excluding cost of centering, shuttering, finishing and reinforcement manufactured in automatic RMC plant using coarse sand and graded stone aggregate of 20mm nominal size in appropriate proportion as per approved design criteria including transportation to site in transit mixer, including cost of admixture in recommended proportion as per IS9103 to accelerate/ retard setting of concrete to improve workability with out impairing strength and durability as per specification including spreading and compacting mechanically by using needle vibrators etc. complete as per direction of Engineer in-charge. Note:- Cement content considered in M-30 is @ 400 kg/cum. Excess/less cement used as per design mix is payable/ recoverable separately M-30 RMC by using minimum cement @400 kg/cum. Cement concrete manufactured in automatic batching plant (RMC plant) including transportation to site in transit mixer.
Fabrication and manufacturing of solid precast with machine batched and machine mixed design mix M-35 grade cement concrete for reinforced cement concrete element and placing the same in position with provisions of shear keys, connecting loops, dowel tubes and proper lifting accessories for walls, beams, slabs, stairs, column etc, of various thickness, shape and size of different concrete grades manufactured in controlled factory environment with approved methodology including moulds (Pallet system, Tilts form, table moulds, battery moulds, vertical moulds, beam moulds, column moulds, staircase moulds, Facade mould, etc.), mixing, transporting and placing of concrete, vibrating, curing, finishing, making necessary cutout/ holes of required sizes for services, yard handling & stacking all complete as per IS 11447:1985 and as per approved shop drawings and design mix. The rate is also to include the cost of transporting, placing, aligning, providing temporary supports and stays for pre-cast concrete members in a approved manner as per the direction of Engineer-in-Charge. (Reinforcement shall be paid separately).
Steel reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete upto plinth level.Thermo-Mechanically Treated bars of grade Fe-500D or more.
Steel work welded in built up sections/ framed work, including cutting, hoisting, fixing in position and applying a priming coat of approved steel primer using structural steel etc. as required.
Finishing walls with Premium Acrylic Smooth exterior paint with Silicone additives of required shade: New work (Two or more coats applied @ 1.43 ltr/10 sqm over and including priming coat of exterior primer applied @ 2.20 kg/10 sqm).
Please Enable Macros to View BoQ information
stage.html
html • 0.03 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.12 MB
BOQ_377034.xls
BOQ • 0.38 MB
133TENDERDOCUMENT.pdf
Tender Documents • 0.37 MB
Download all tender documents and submit your bid