Loading…
Loading…
Tender Value
₹7.5 Cr
EMD Value
₹3.8 L
Closing Date
17 Sept 2026, 5:00 pm5d left
SE PMGSY Konkan Region Thane, 9th Floor, TMC Parki
SE PMGSY Konkan RegionThane, 9th Floor, TMC ParkingPlaza Building, Near JupiterHospital, Ghodbandar Road,Thane 400606
Construction and Maintenance of Bridge 1.NH66 to Salgaon Mala Sawantwadi Road at CH 0/860 KM 2.NH66 to Salgaon Mala Sawantwada Road at CH 0/500 KM3.Ghawanale Naneli Mangaon Road at CH.4/640 KM
2026_CEMAH_149390_1
MH2887
Open Tender
Civil Works - Bridge Construction
Percentage
365 days
KUDAL
Please refer Tender documents.
7 documents required · 7 mandatory
₹17,700
₹3.8 L
SE,PMGSY,Konkan Region Thane
2 Sept 2026
2 Sept 2026
18 Sept 2026
2 Sept 2026
17 Sept 2026
9 Sept 2026
8 Sept 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1.01 | Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of stone masonry, including disposal of unserviceable material and stacking the serviceable material with all lift and lead of 1000 m as per Technical Specification Clause 202.Rubble stone masonry in cement mortar | - | Cubic Metre | 1,119.17 | - |
| 1.02 | Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of stone masonry, including disposal of unserviceable material and stacking the serviceable material with all lift and lead of 1000 m as per Technical Specification Clause 202.Rubble stone masonry in cement mortar | - | Running Meter | 620.49 | - |
| 1.03 | Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of stone masonry, including disposal of unserviceable material and stacking the serviceable material with all lift and lead of 1000 m as per Technical Specification Clause 202.Rubble stone masonry in cement mortar | 1 | Cubic Metre | 706.95 | ₹706.24 |
| 1.04 | Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of stone masonry, including disposal of unserviceable material and stacking the serviceable material with all lift and lead of 1000 m as per Technical Specification Clause 202.Rubble stone masonry in cement mortar | 1 | Cubic Metre | 883.69 | ₹882.81 |
| 1.05 | Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of stone masonry, including disposal of unserviceable material and stacking the serviceable material with all lift and lead of 1000 m as per Technical Specification Clause 202.Rubble stone masonry in cement mortar | 1 | Cubic Metre | 1,436.06 | ₹1,434.62 |
| 1.06 | Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of stone masonry, including disposal of unserviceable material and stacking the serviceable material with all lift and lead of 1000 m as per Technical Specification Clause 202.Rubble stone masonry in cement mortar | - | Hour | 201 | - |
| 1.07 | Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of stone masonry, including disposal of unserviceable material and stacking the serviceable material with all lift and lead of 1000 m as per Technical Specification Clause 202.Rubble stone masonry in cement mortar | 1 | Cubic Metre | 7,514.46 | ₹7,506.95 |
| 1.08 | Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of stone masonry, including disposal of unserviceable material and stacking the serviceable material with all lift and lead of 1000 m as per Technical Specification Clause 202.Rubble stone masonry in cement mortar | - | Running Meter | 1,674 | - |
| 1.09 | Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of stone masonry, including disposal of unserviceable material and stacking the serviceable material with all lift and lead of 1000 m as per Technical Specification Clause 202.Rubble stone masonry in cement mortar | - | Cubic Metre | 7,546.5 | - |
| 1.1 | Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of stone masonry, including disposal of unserviceable material and stacking the serviceable material with all lift and lead of 1000 m as per Technical Specification Clause 202.Rubble stone masonry in cement mortar | - | Cubic Metre | 9,129.96 | - |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 3.48 MB
BOQ_235451.xls
BOQ • 0.50 MB
MH2887.pdf
Tender Documents • 3.46 MB
87-DR.pdf
Additional Documents • 14.95 MB
corri2.pdf
PDF • 1.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .