Tender Value
₹96 L
EMD Value
₹96,000
Closing Date
25 Nov 2026, 3:00 pm
Eligibility, documents, scope, Go/No-Go checksEligibility, required documents, scope of work and Go/No-Go checks for this tender, in one click.
Executive Officer
116, Melasalai, Thirubuvanam Town Panchayat
Formation Of BT Road at Attrangarai vazhi nadappu sarabar nagar in Thirubuvanam Town Panchayat
2026_DTP_723274_1
350/2026
Open Tender
Civil Works
Works
120 days
Thirubuvanam Town Panchayat
Refer Tender Notice
3 documents required · 3 mandatory
₹0
₹96,000
Yes
Thirubuvanam Town Panchayat
7 Nov 2026
7 Nov 2026
25 Nov 2026
7 Nov 2026
25 Nov 2026
7 Nov 2026
19 Nov 2026
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Construction of Granular Sub-base by providing close graded material,mixing in a machanical plant at OMC,carriage of mixed material to work site,spreading in uniform layers with motor grader on prepared surface and compacting with vibratory power roller to acheive the desired density,Complete as per clause 401. | 537.6 | M3 | - | - |
| 2 | Providing and laying WMM (Wet Mix Mecadam) of 250 mm compacted thickness in two layors of 125 mm thick or else as specified on the prepared sub base with graded stone aggregate and granular material of quality size and grading pasting in layor with motor grader and compaction with vibrating rollers of 80-100 KN static weight and fine dressing for required grade and cross slope as shown on the drawing equipments equipments safety measures testing and incidents necessary to complete the work as per MORT&H406 | 358.4 | M3 | - | - |
| 3 | Providing and applying of Prime Tack coat using emulsion bitumen at the rate of 7 kg per 10m2 over the WET MIX MECADAM Surface preparatory to another bituminous construction over it etc. complete. | 3,584 | M2 | - | - |
| 4 | Providing and applying of Tack coat over WMM Surface treated with prime coat using 2.50kg bitiminous emulsion per 10m2 As per 111,112,501,503,&900 MORTH Specification | 3,584 | M2 | - | - |
| 5 | Providing and laying 50mm consolidated thick Dense Bituminous Macadam using 0.24cum of 26.50-13.20mm,0.25cum of 13.20-2.36mm and 0.23cum of 2.36mm &below and with 53.20 Kgs of VG30/VG40 bitumen for premixing per 10sqm including cost and conveyance of all materials to CMPsite,heating the bitumen and aggregate to required temperature and mixing the min required temperature in central hot mix plant 20-30 ton capacity, conveying the mix by tipper trucks to work site, spreading the mix to uniform thickness of 50mm with paver to the specified grades and cross sections and compacted by Vibratory/Pneumatic Roller to the required density etc.,including labou for attending to paver at site etc.,including hire charges and fuel charges for 20-30t CMP with bitumen boiler, tipper trucks, Paver Finisher / 9m paver finisher, Vibratory/Pneumatic rollers and all other tools and plant required, including fuel and all other incidental charges etc.,complete a sper specification using CMP as per clause 505 MORTH Rev-5 | 179.2 | M3 | - | - |
| 6 | Providing and laying Bituminous Concrete to 30 mm thick using 0.13 cum of 19.00-9.50mm 0.17 cum 9.50-2.36mm and 0.26 cum of 2.36 and below with 46.28kgs of VG30/VG40 and plastic waste added 4.02kgs bitumen for premixing per 10sqm including cost and conveyance of all marerials to CMP site, heating the bitumen and aggregate to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity,conveying the mix by tipper trucks to paver site spreading the mix to uniform thickness of 40mm with mechanical paver tothe specified grades and cross sections and consolidated by 8-10 tonne Vibratory /Pneumatic Roller to the required density etc., including labour for attending to paver to site etc.,including hire charges and fuel charges for 20-30 t CMP with bitumen boiler,tippertrucks,paver Finisher /9m paver finisher,Vibratory / Pneumatic roller and all other tools and plant required, including fuel and all other incidental charges etc.,complete as per specification using CMP as per clause 507 of MORTH Rev-5. | 107.52 | M3 | - | - |
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.66 MB
Tendernotice_2.pdf
PDF • 0.78 MB
BOQ_868402.xls
BOQ • 0.23 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .