| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.1 CrAccepted-AOC | ₹1.1 Cr | L1 | Accepted-AOC L1 |
| 2 | Not Admitted-Finance 208 L MODEL TOWN LUDHIANA | LUDHIANA | PUNJAB | 141001 | - | - | Not Admitted-Finance Not qualified for AOC |
| 3 | Not Admitted-Fee/PreQual/Technical | - | - | Not Admitted-Fee/PreQual/Technical Not Complied with technical specification |
| Sl No | Description | Qty | Unit | M/S SHREE ANSH CONSTRUCTION L1 |
|---|---|---|---|---|
| 1.00 | Earth work in Filling for slope & bed of canal including all lead & lift with all cost of material,labour,T & P etc. required for proper completion of work. | 1,277.26 | Cum. | 150 ₹1,91,588.85 |
| 2.00 | Laying C.C. M-15 (1:2:4) mix in foundation with Kabrai crushed gritt 10 to 20 mm size coarse sand of F.M. not less than 2.0, including all cost of material, labour, T & P etc. required for proper completion of work. | 36.39 | Cum. | 12,000 ₹4,36,644 |
| 3.00 | Filling Local Sand including carriage with all cost of labour and T&P charges etc. | 84 | Cum. | 300 ₹25,200 |
| 4.00 | Supplying and laying Geo Textile sheet made of 200 gsm woven multifilament polypropylene yarn including all cost of labour, T&P and material charges etc. | 840 | Sqm | 120 ₹1,00,800 |
| 5.00 | Boulder masonary in 1:4 C:M with coarse sand,of F.M. not less than 2.0, including all cost of material,labour, T & P etc. required for proper completion of work. | 192.6 | Cum. | 9,700 ₹18,68,220 |
| 6.00 | Stone grit (4.75 to 10mm) in side slope 75 mm thick including all cost of material,labour, T & P etc. required for proper completion of work. | 54 | Cum. | 6,100 ₹3,29,400 |
| 7.00 | Stone grit (10 to 20mm) in side slope 75 mm Thick including all cost of material,labour, T & P etc. required for proper completion of work. | 54 | Cum. | 7,200 ₹3,88,800 |
| 8.00 | Supplying and laying Mirzapur hard stone Boulder in G.I. wire crate ( 1.0 x 1.0 x 1.0 ) mtr. With mesh size 20x20 cm including all cost of material with loading, unloading and carriage , labour, T & P etc required for proper completion of work. | 835.2 | Cum. | 6,150 ₹51,36,480 |
| 9.00 | Supplying & laying of Mirzapur hard stone Boulder for slope including all cost of material with loading, unloading and Carriage , labour, T & P etc. required for proper completion of work. | 210 | Cum. | 5,100 ₹10,71,000 |
| 10.00 | Centering and shuttering for R.C.C.work; including all cost of material, labour, T & P etc complete work. | 339.92 | Sqm | 840 ₹2,85,532.8 |
Updated dates
Tender Value
₹1.2 Cr
EMD Value
₹2.4 L
Closing Date
9 Jan 2026, 3:00 pmClosed
Superintending Engineer
Office of the Superintending Engineer Drainage Circle Gonda
Protection work in down stream at Km 10.960 PRB Cum Fall of Basti Branch.
2025_UPIDC_1099050_5
01/SE/2025-26
Open Tender
Civil Works - Canal
SHRAVASTI
Please refer Tender documents.
3 documents required · 3 mandatory
₹2,354
₹2.4 L
26 Mar 2026
15 Dec 2025
9 Jan 2026
15 Dec 2025
9 Jan 2026
15 Dec 2025
Earth work in Filling for slope & bed of canal including all lead & lift with all cost of material,labour,T & P etc. required for proper completion of work.
Laying C.C. M-15 (1:2:4) mix in foundation with Kabrai crushed gritt 10 to 20 mm size coarse sand of F.M. not less than 2.0, including all cost of material, labour, T & P etc. required for proper completion of work.
Filling Local Sand including carriage with all cost of labour and T&P charges etc.
Supplying and laying Geo Textile sheet made of 200 gsm woven multifilament polypropylene yarn including all cost of labour, T&P and material charges etc.
Boulder masonary in 1:4 C:M with coarse sand,of F.M. not less than 2.0, including all cost of material,labour, T & P etc. required for proper completion of work.
Stone grit (4.75 to 10mm) in side slope 75 mm thick including all cost of material,labour, T & P etc. required for proper completion of work.
Stone grit (10 to 20mm) in side slope 75 mm Thick including all cost of material,labour, T & P etc. required for proper completion of work.
Supplying and laying Mirzapur hard stone Boulder in G.I. wire crate ( 1.0 x 1.0 x 1.0 ) mtr. With mesh size 20x20 cm including all cost of material with loading, unloading and carriage , labour, T & P etc required for proper completion of work.
Supplying & laying of Mirzapur hard stone Boulder for slope including all cost of material with loading, unloading and Carriage , labour, T & P etc. required for proper completion of work.
Centering and shuttering for R.C.C.work; including all cost of material, labour, T & P etc complete work.
Cutting, bending, binding and placing of steel reinforcement in R.C.C. work; including all, cost of steel, binding wire,labour, T & P etc. complete work.
Drilling suitable holes in reinforced or plain cement concrete with power driven drill machine to a minimum depth of 100mm upto 200mm in RCC beams, lintels, columns and slabs to introduce steel bars for sunshades/balconies including fixing the steel bars in position using epoxy resin anchor grout of approved make but excluding the cost of reinforcement, all complete as per direction of Engineer-In-Charge.
Laying R.C.C. M-20 (1:1½:3) mix with Kabrai crushed stone grit graded 4.75 to 20mm size with coarse sand of F.M. not less then 2.0; including all cost of material, labour T & P etc required for proper completion of work.
Supply & fixing sign board ISA40x40x05mm size 1.20x2.10m. and 1.50mm thick M.S. plate, painting caution letter, including all cost of material, labour, T & P etc complete work.
Dewatering with all cost of power & P.O.L . machine, pump, well point systm and operator etc with assembling and dismentling of machine etc required for proper completion of work.
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 5.63 MB
LT5.pdf
Tender Documents • 15.77 MB
BOQ_2024510.xls
BOQ • 0.26 MB
Download all tender documents and submit your bid