| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹12.3 CrAccepted-AOC | L1 | Accepted-AOC TENDER AWARDED |
| Sl No | Description | Qty | Unit | AJAY SAUHTA L1 |
|---|---|---|---|---|
| 1.00 | Excavation in hilly area in all heights and depths and in all kind of soil by manual/mechanical means including saturated soil comprising of ordinary soil, soft rocks, hard rocks, chiseling/wedging out of rock (where blasting is prohibited) and their intermediate classification of soil, setting out true to the required lines, grades, cutting and trimming of side slopes to level as shown in the drawing and as directed by engineer-in-charge at site according to the MORD technical specification section 300 and 1600 and sorting out useful materials and stacking the same in all leads, lifts in acquired width of road and transportation of un-useful material for filling in road ways, camber, embankments for grade improvements and disposal of all surplus material to the approved dumping sites through all modes of transportation including head load or animal transport or mechanical means along with its leveling, fine dressing and carriage of machineries, materials, tools, equipments and safety measures and incidentals necessary to complete the work by mechanical means and labour if required. Recovery of stones that tune of 2168.11 Cum quantity ( Nine hundred twenty one point twenty eight) cubic metres at the rate of 300/- (Rupees three hundred ) per cubic metre shall be effected from the contractor's running bills on pro-rate basis as per actual quantity executed. Any loss to the public, private property during the course of execution shall be the absolute responsibility of the contractor, which shall have to be duly compensated by him in all cases. The rate is including octroi, royality, Malkana, toll tax, and any other taxes imposed by the Government including GST. | 78,028.08 | Per cubic metre | 300 ₹2,34,08,424 Lowest |
| 2.00Earth work in excavation for all type of road structure such as retaining walls,Breast walls,culverts,drainds and parapets etcetra. in all types of classification of soil comprising of ordinary soil ,ordinary rock and hard rocks, chiselling/wedging out of rock (where blasting is prohibited) as per drawing and MORD.Technical specifications Clause 305.1 and as per direction of Engineer in Charge including setting out, shoring and bracing, removal of stumps and other deleterious material and disposal of material up to any lead and upto any lift, including dressing of sides and bottom and back filling in trenches with excavated suitable material to the orignal surface in layers not exceeding 150 mm (one hundred (fifty milimeters) compected thickness including sorting and sturting and pumping and bailing out water (surface and sub soil water) up to all depth or any quantum of water including cleaning of slush which may arise out during dewatering as per the direction of Engineer-In-Charge and including of carriage of material with in all leads and lifts and other incidentals. The rate including octroi, royality, Malkana, toll tax, GST or other taxes imposed by the Government. | ||||
| 2.10 | R/Wall & B/Wall | 882.05 | Per cubic metre | 507 ₹4,47,199.35 Lowest |
| 2.20 | Hume Pipe Culvert | 1,616.71 | Per cubic metre | 507 ₹8,19,671.97 Lowest |
| 2.30 | Drain | 821.11 | Per cubic metre | 507 ₹4,16,302.77 Lowest |
| 2.40 | PCC Parapets | 186.38 | Per cubic metre | 507 ₹94,494.66 Lowest |
| 2.50 | Dumping Structure | 50.63 | Per cubic metre | 507 ₹25,669.41 Lowest |
| 3.00Providing and laying cement concrete grade M 10 (Ten) nominal mix 1:3:6 (one cement:three sand:six graded stone graded stone aggregate 20 mm (twenty milimeter) nominal size)concrete for plain/reinforced concrete in open foundations complete including form work as per drawings and technical specifications Clause 802, 803, 1202 & 1203 .including carriage of material with in all leads and lifts as per direction by the Engineer-In-Charge. The rate including octroi, royality, Malkana, toll tax, GST or other taxes imposed by the Government. | ||||
| 3.10 | Hume Pipe Culvert | 1,101.67 | Per cubic metre | 6,300 ₹69,40,521 Lowest |
| 3.20 | Drain | 815.67 | Per cubic metre | 6,300 ₹51,38,721 Lowest |
Tender Value
₹11.9 Cr
EMD Value
₹23.8 L
Closing Date
12 Jun 2023, 6:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
SUPERINTENDING ENGINEER 14TH CIRCLE HPPWD ROHRU
SUPERINTENDING ENGINEER 14TH CIRCLE HPPWD ROHRU
(SH- F/C 5/7mtr wide road cross drainage, protection work, metalling and tarring, side drain, parapet km 0/0 to 9/950)
2023_PWD_74524_1
PW-SE-XIV-1685-1784DT-27.5.23
Open Tender
Civil Works - Roads
Item Rate
510 days
ROHRU
Please refer Tender documents.
11 documents required · 11 mandatory
₹5,000
₹23.8 L
ROHRU
1 Mar 2024
5 Jun 2023
13 Jun 2023
5 Jun 2023
12 Jun 2023
5 Jun 2023
5 Jun 2023
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Excavation in hilly area in all heights and depths and in all kind of soil by manual/mechanical means including saturated soil comprising of ordinary soil, soft rocks, hard rocks, chiseling/wedging out of rock (where blasting is prohibited) and their intermediate classification of soil, setting out true to the required lines, grades, cutting and trimming of side slopes to level as shown in the drawing and as directed by engineer-in-charge at site according to the MORD technical specification section 300 and 1600 and sorting out useful materials and stacking the same in all leads, lifts in acquired width of road and transportation of un-useful material for filling in road ways, camber, embankments for grade improvements and disposal of all surplus material to the approved dumping sites through all modes of transportation including head load or animal transport or mechanical means along with its leveling, fine dressing and carriage of machineries, materials, tools, equipments and safety measures and incidentals necessary to complete the work by mechanical means and labour if required. Recovery of stones that tune of 2168.11 Cum quantity ( Nine hundred twenty one point twenty eight) cubic metres at the rate of 300/- (Rupees three hundred ) per cubic metre shall be effected from the contractor's running bills on pro-rate basis as per actual quantity executed. Any loss to the public, private property during the course of execution shall be the absolute responsibility of the contractor, which shall have to be duly compensated by him in all cases. The rate is including octroi, royality, Malkana, toll tax, and any other taxes imposed by the Government including GST. | 78,028.08 | Per cubic metre | - | - |
| 2Earth work in excavation for all type of road structure such as retaining walls,Breast walls,culverts,drainds and parapets etcetra. in all types of classification of soil comprising of ordinary soil ,ordinary rock and hard rocks, chiselling/wedging out of rock (where blasting is prohibited) as per drawing and MORD.Technical specifications Clause 305.1 and as per direction of Engineer in Charge including setting out, shoring and bracing, removal of stumps and other deleterious material and disposal of material up to any lead and upto any lift, including dressing of sides and bottom and back filling in trenches with excavated suitable material to the orignal surface in layers not exceeding 150 mm (one hundred (fifty milimeters) compected thickness including sorting and sturting and pumping and bailing out water (surface and sub soil water) up to all depth or any quantum of water including cleaning of slush which may arise out during dewatering as per the direction of Engineer-In-Charge and including of carriage of material with in all leads and lifts and other incidentals. The rate including octroi, royality, Malkana, toll tax, GST or other taxes imposed by the Government. | |||||
| 2.1 | R/Wall & B/Wall | 882.05 | Per cubic metre | - | - |
| 2.2 | Hume Pipe Culvert | 1,616.71 | Per cubic metre | - | - |
| 2.3 | Drain | 821.11 | Per cubic metre | - | - |
| 2.4 | PCC Parapets | 186.38 | Per cubic metre | - | - |
| 2.5 | Dumping Structure | 50.63 | Per cubic metre | - | - |
| 3Providing and laying cement concrete grade M 10 (Ten) nominal mix 1:3:6 (one cement:three sand:six graded stone graded stone aggregate 20 mm (twenty milimeter) nominal size)concrete for plain/reinforced concrete in open foundations complete including form work as per drawings and technical specifications Clause 802, 803, 1202 & 1203 .including carriage of material with in all leads and lifts as per direction by the Engineer-In-Charge. The rate including octroi, royality, Malkana, toll tax, GST or other taxes imposed by the Government. | |||||
| 3.1 | Hume Pipe Culvert | 1,101.67 | Per cubic metre | - | - |
| 3.2 | Drain | 815.67 | Per cubic metre | - | - |
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
BOQ_111738.xls
BOQ Document • 0.27 MB
122317158.pdf
Tender Document • 1.48 MB
J-3NasariDagaon.pdf
Tender Document • 0.67 MB
122317163.html
Tender Document • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .