| 1 | L1₹30.4 LAccepted-AOC MECHEDA NEAR PNB PURBA MEDINIPUR MECHEDA 721137 | MECHEDA | PURBA MEDINIPUR | WEST BENGAL | 721137 | ₹30.4 L | L1 | Accepted-AOC ACCEPTED |
| 2 | L2₹30.4 LRejected-AOC | ₹30.4 L | L2 | Rejected-AOC REJECTED |
| 3 | L3₹30.7 LRejected-Finance 285 MAHATMA GANDHI ROAD 285 PRANTIKAPAN SHOPPING COMPLEX BL 1 1ST FLOOR SHOP S 35 KOLKATA 700104 | KOLKATA | KOLKATA | WEST BENGAL | 700104 | ₹30.7 L | L3 | Rejected-Finance REJECTED |
Tender Value
₹30.4 L
EMD Value
₹60,753
Closing Date
19 Jan 2026, 4:00 pmClosed
EXECUTIVE ENGINEER KOLKATA SOUTH I DIVISION, HOUSI
84, IBRAHIMPUR ROAD, KOLKATA 700032
Renovation and Repairing work of total 89 nos. unauthorized flats with structural repairing, plastering, flooring, white wash etc. at RHE Baburam Ghosh Road.
2025_HSD_980854_1
WBHOUSING/EE/KS ID/e-NIT26/2025-26
Open Tender
CIVIL WORKS
120 days
RHE BABURAM GHOSH ROAD
Please refer Tender documents.
4 documents required · 4 mandatory
₹60,753
30 Jan 2026
29 Dec 2025
21 Jan 2026
31 Dec 2025
19 Jan 2026
31 Dec 2025
Stripping off worn out plaster and raking out joints of walls, celings etc. upto any height and in any floor including removing rubbish within a lead of 75m as directed.
Cleaning the concrete surface by removing dirt and debris, marking defective locations and removing loose concrete by careful stripping untill hard surface is exposed, cutting the concrete to regular shape, wire brushing the exposed surface and removing debris from site complete as per direction of the Engineer - in - Charge.
Reinforcement for reinforced concrete work in all sorts of structures including distribution bars, stirrups, binders etc initial straightening and removal of loose rust (if necessary), cutting to requisite length, hooking and bending to correct shape, placing in proper position and binding with 16 gauge black annealed wire at every intersection, complete as per drawing and direction. Ground Floor
First Floor
Second Floor
Third Floor
Welding in M.S. structural work with gas or electric: (a) Tack weld
Dismantling artificial stone flooring upto 50 mm. thick by carefully chiselling without damaging the base and removing rubbish as directed within a lead of 75 m. Ground Floor
First Floor
Second Floor
Third Floor
(a) Applying 2 coats of bonding agent with synthetic multi functional rubber emulsion having adhesive and water proofing properties by mixing with water in proportion (1 bonding agent : 4 water : 6 cement) as per Manufacturer's specification [Cement to be supplied by the Department]
Applying epoxy based reactive joining agent for joining the old concrete with fresh concrete to be applied within manufacturer's specified time as per manufacturers specification. (0.4 Kg / m² of concrete surface).
Cement concrete (1:1.5:3) with graded stone chips 5.6 mm size with hexagonal square mesh wire netting, I.R.C. fabric mesh or X.P. M. fitted and fixed after tying the existing reinforcement on concrete without distributing the same and with proper scarping and cleaning the reinforcement and disturbed concrete with wire brush etc. after applying a coat of cement including the cost of wire netting I.R.C or X. P. M. & cost of all handling and scaffolding complete as per direction of Engineer-in -charge. c) 87.5 mm thick
Artificial stone in floor, dado, staircase etc with cement concrete (1:2:4) with stone chips, laid in panels as directed with topping made with ordinary or white cement (as necessary) and marble dust in proportion (1:2) including smooth finishing and rounding off corners including raking out joints or roughening of concrete surface and application of cement slurry before flooring works using cement @ 1.75kg/sq.m all complete including all materials and labour. In ground floor. 3 mm. thick topping (High polishing grinding on this item is not permitted with ordinary cement). Using grey cement
First Floor
Second Floor
Third Floor
Plaster (to wall, floor, ceiling etc.) with sand and cement mortar including rounding off or chamfering corners as directed and raking out joints including throating, nosing and drip course, scaffolding/staging where necessary (Ground floor).[Excluding cost of chipping over concrete surface] (i) With 1:6 cement mortar (c) 20 mm thick plaster Ground Floor
First Floor
Second Floor
Third Floor
(i) With 1:4 cement mortar (c) 10 mm thick plaster Ground Floor
First Floor
Second Floor
Third Floor
Neat cement punning about 1.5mm thick in wall, dado, window sill, floor etc. NOTE:Cement 0.152 cu.m per100 sq.m.
White washing including cleaning and smoothening surface thoroughly. All floors : b) Two coats (to be done on specific instruction).
Dismantling Orissa pattern W.C. including taking out of base concrete, if necessary, complete.
Supplying, fitting and fixing E.W.C. in white glazed vitreous chinaware of approved make complete in position with necessary bolts, nuts etc. (a) With 'P' trap
Removal of rubbish,earth etc. from the working site and disposal of the same beyond the compound, in conformity with the Municipal / Corporation Rules for such disposal, loading into truck and cleaning the site in all respect as per direction of Engineer in charge
Please Enable Macros to View BoQ information
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.PDF
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 0.92 MB
BOQ_2391721.xls
BOQ • 0.35 MB
2911.pdf
Tender Documents • 0.56 MB
Download all tender documents and submit your bid