| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | 1ST₹9.9 LAccepted-Finance | ₹9.9 L | 1ST | Accepted-Finance 1ST LOWEST |
| 2 | 2ND₹10.4 LRejected-Finance | ₹10.4 L | 2ND | Rejected-Finance 2ND LOWEST |
| 3 | 3RD₹10.6 LRejected-Finance | ₹10.6 L | 3RD | Rejected-Finance 3RD LOWEST |
Tender Value
₹9.9 L
EMD Value
₹20,000
Closing Date
17 Feb 2026, 4:00 pmClosed
EE(C)/BR-IV
213-B, C. R. AVENUE KOLKATA 700 006
Renovation of sewer line at Ramananda Chatterjee Street from 12A and 33A to 39, Ramananda Chatterjee Street in Ward No.-27.
2026_KMC_1002044_1
KMC/EEC/BR-IV/25-26/APAS27/25
Open Tender
CIVIL WORKS
25 days
BOROUGH IV
Please refer Tender documents.
4 documents required · 4 mandatory
₹0
₹20,000
18 Apr 2026
9 Feb 2026
19 Feb 2026
9 Feb 2026
17 Feb 2026
9 Feb 2026
8.a) Supplying, fitting and fixing with cement jointing (3:1) salt glazed stoneware pipe including excavation of earth upto 1.5 metre depth in all sorts of soil both mixed or unmixed and refilling (but excluding cementing at bottom and sides) d) 300 mm dia
BUILDING WORKS (A) EARTH WORK,ANTITERMITE TREATMENT 2. Earth work in excavation of foundation trenches or drains, in all sorts of soil (including mixed soil but excluding laterite or sandstone) including removing, spreading or stacking the spoils within a lead of 75 m. as directed. The item includes necessary trimming the sides of trenches levelling, dressing and ramming the bottom, bailing out water as required complete (b) Depth of excavation for additional depth beyond 1,500 mm. and upto 3,000 mm. but not requiring shoring
SECTION(B) - SANITARY AND DRAINAGE WORKS.(B)-(II) SOIL PIPE AND FITTINGS.(a) Original Works.(16.)Supplying, fitting and fixing with cement jointing (3:1) salt glazed stoneware pipe including excavation of earth upto 1.50 metre depth in all sorts of soil both mixed or unmixed and refilling (but excluding concreting at bottom and sides).(iii) 150 mm
BUILDING WORKS ( C ) BRICKWORKS, CONCRETE WORKS Etc. A. BRICK WORKS 1. Single Brick Flat Soling of picked jhama bricks including ramming and dressing bed to proper level and filling joints with local sand.
Cement concrete with graded jhama khoa (30 mm size) excluding shuttering In ground floor and foundation. (a) 1:3:6 proportion
23.Construction of Catch pit 600mmX525mm. (inside measurement) and depth of invert 1000mm. below G.L. with 250mm. thick cement brick work (1:4) over 100mm. thick jhama cement concrete (1:4:8) bed over a layer of brick flat soling including providing 100mm. thick R.C.C. slab with ordinary cement concrete (mix 1:1.5:3) with reinforcement as per standard drawing, brickon- edge flooring with 20 mm. thick cement plaster (1:4) finished fine with 1.5 mm. thick neat cement in the inside walls and invert including supplying and fixing R.C.P.C. gully grid (5 M.T.load bearing capacity) and 150 mm. dia. C.I. Syphone including cutting hard crust, excavation, dewatering, back filling and removal of spoils as per standard drawing
(19)Construction of special inspection pit with chamber of size 900mm. X 600mm. x 1500 mm (inside measurement) and 450mm X 450mm. square shaft (inside measurement) with 250mm. thick cement brick work (1:4) over 150mm. thick jhama cement conc. (1:4:8) bed over a layer of brick flat soling including providing 150mm. thick R.C.C. slab with ordinary cement concrete (mix 1:1.5:3) with 1% reinforcement over the chamber, brick on edge flooring with ordinary cement concrete(mix 1:2:4) in the invert with 20mm. thick cement plaster (1:4) finished fine with 1.5 mm. thick neat cement in the inside walls and invert including supplying, fitting and fixing R.C.P.C. cover and frame (15 m.T. load bearing capacity) with ordinary cement concrete (mix :1:2:4) and C.I. steps( 4 Kg. each) including cutting hard crust, excavation, dewatering, backfilling and removal of spoils but excluding shoring as per standard drawing of K.m.C. (depth of invert should not be less than 1.80m below G.L.) i) Average depth of invert 2.00 m. below G.L.
21.Construction of special inspection pit with chamber of size 900mm. X 600mm. x 1500 mm (inside measurement) and 450mm X 450mm. square shaft (inside measurement) with 250mm. thick cement brick work (1:4) over 150mm. thick jhama cement conc. (1:4:8) bed over a layer of brick flat soling including providing 150mm. thick R.C.C. slab with ordinary cement concrete (mix 1:1.5:3) with reinforcement as per standard drawing over the chamber, brick on edge flooring with ordinary cement concrete(mix 1:2:4) in the invert with 20mm. thick cement plaster (1:4) finished fine with 1.5 mm. thick neat cement in the inside walls and invert including supplying, fitting and fixing R.C.P.C. cover and frame (15 M.T. load bearing capacity) with ordinary cement concrete (mix :1:2:4) and C.I. steps( 4 Kg. each) including cutting hard crust, excavation, dewatering, backfilling and removal of spoils but excluding shoring as per standard drawing .(depth of invert should not be less than 1.80m below G.L.)
(18)Construction of special inspection chamber pit of size 900mm. X 600mm. (inside measurement) without shaft with 250mm. thick cement brick work (1:4) over 150mm. thick jhama cement conc. (1:4:8) bed over a layer of brick flat soling including providing 150mm. thick R.C.C. slab with ordinary cement concrete (mix 1:1.5:3) with 1% reinforcement over the chamber, brick on edge flooring with ordinary cement concrete (mix 1:2:4) in the invert with 20mm. thick cement plaster (1:4) finished fine with 1.5 mm. thick neat cement in the inside walls and invert including supplying, fitting and fixing 450mm. dia. (15 m.T.) heavy duty R.C.P.C. cover and frame (15 m.T. load bearing capacity) with ordinary cement concrete (mix 1:2:4) and C.I. steps (4 kg. each) including cutting hard crust, excavation, dewatering, back filling and removal of spoils but excluding shoring as per standard drawing of K.m.C. (depth of invert between 1.15m. to 1.80m. below G.L.) i) Average depth of invert 1.15 m. below G.L.
Construction of special inspection chamber pit of size 900mm. X 600mm. (inside measurement) without shaft with 250mm. thick cement brick work (1:4) over150mm. thick jhama cement conc. (1:4:8) bed over a layer of brick flat soling including providing 150mm. thick R.C.C. slab with ordinary cement concrete (mix 1:1.5:3) with reinforcement as per standard drawing over the chamber, brick on edge flooring with ordinary cement concrete (mix 1:2:4) in the invert with 20mm. thick cement plaster (1:4) finished fine with 1.5 mm. thick neat cement in the inside walls and invert including supplying, fitting and fixing 450mm. dia. (15 M.T.) heavy duty R.C.P.C. cover and frame (15 M.T. load bearing capacity) with ordinary cement concrete (mix 1:2:4) and C.I. steps (4 kg. each) including cutting hard crust, excavation, dewatering, back filling an removal of spoils but excluding shoring as per standard drawing .(depth of invert between 1.15m. to 1.80m. below G.L.) ii) Addition and deduction of rate of special inspection chamber pit as per above item for each addition or reduction in depth of 150 mm. or part thereof.
BUILDING WORKS (B) DISMANTLING, CUTTING CHASE, HOLES ETC. 1. Dismantling all types of masonry excepting cement concrete plain or reinforced, stacking serviceable materials at site and removing rubbish as directed within a lead of 75 m. (a) In ground floor including roof.
BUILDING WORKS ( C ) Brickworks,Concrete Works etc A. BRICK WORKS 7. Brick work with 1st class bricks in cement mortar (1:4) (a) In foundation and plinth
SECTION 1. ------------BUILDING WORKS (I) PLASTERING, POINTING ETC. A. ORIGINAL WORKS 1.Plaster (to wall, floor, ceiling etc.) with sand and cement mortar including rounding off or chamfering corners as directed and raking out joints including throating, nosing and drip course, scaffolding/staging where necessary (Ground floor).[Excluding cost of chipping over concrete surface](ii) With 1:4 cement mortar (a) 20 mm thick plaster
SECTION 1. ------------BUILDING WORKS (I) PLASTERING, POINTING ETC. A. ORIGINAL WORKS 15 Neat cement punning about 1.5mm thick in wall, dado, window sill, floor etc. NOTE:Cement 0.152 cu.m per100 sq.m.
Hire and labour charges for 3.75cm. thick close timbering with planks, battens,runners,struts etc. complete removing them incl. penetration of shoring as per direction of the Engineer-in-Charge upto 1 M. trench width. (Vertical surface of contact area with supporting earth to be measured, payment for penetration will not be allowed) a) Depth upto 3.00 M below G.L.
BUILDING WORKS (A) EARTH WORK,ANTITERMITE TREATMENT 4. (A) Filling in foundation or plinth by silver sand in layers not exceeding 150 mm as directed and consolidating the same by thorough saturation with water, ramming complete including the cost of supply of sand. (payment to be made on measurement of finished quantity)
Earthwork in cutting to form road section in correct profile including removal of spoils not exceeding initial lead of 50m and initial lift of 1.5m (Mode of measurement: pre works and post works) (i) In ordinary soil
Water Bound Macadam Sub Base by consolidating Jhama metal / Laterite chelly or stone metal / shingles of specific size in hard crust to requisite thickness (measured after compaction) in layers including screening of metals etc. as necessary, hand packing, sweeping, watering and rolling in stages with power roller to proper line, grade and camber, lighting, guarding & barricading and making necessary earthen bundh of one metre width on each side where necessary to protect edges and preparing the bed by necessary cutting or filling and rolling all complete including the cost of all materials and hire and labour charges of all men and machineries and compacting to the required density, as per Clause 404 of Specifications for Road & Bridge Works of MoRT&H (5th Revision). (i) For Construction of Sub Base by consolidating Jhama metal / Laterite (63 mm to 45 mm) (Moorum replaced with course sand) (For compacted thickness 75mm)
CHAPTER - VIII SUPPLYING OF MATERIALS HIRE CHARGES OF MACHINERIES 8.29Hire charges for engaging Air Compressor machine with minimum pressure capacity of 5.0 Kg/sq.cm arrangement including all necessary equipments and operating staff, carriage, fuel, Tools and plants all complete for cutting Road / hard crust cutting with pneumatic hammer at desired point in water supply works as per direction of EIC . a) With Pneumatic hammers For minimum engagement of 8 hrs. In a day
NEW PANEL AND RATE FOR SUPPLY OF PORTABLE PUMPING UNIT (DISEL DRIVEN) OF SIZE 3" DIA ON HIRE BASIS FOR REMOVAL OF STAGNANT WATER FROM SEWER, WATER LOGGING & FLOOD WATER INCLUDING INSTALLATION AND OPERATION TO BE USED IN DIFFERENT BOROUGHS UNDER CME(C) DEPARTMENT AS AND WHEN REQUIRED.
Sub Total
Please Enable Macros to View BoQ information
stage.html
html • 0.04 MB
technical_2455661.pdf
techsummary_2455661.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 1.49 MB
BOQ_2455661.xls
BOQ • 0.26 MB
T1.pdf
Tender Documents • 0.57 MB
Download all tender documents and submit your bid