EKTA TIBREWAL
RHQ-LUCKNOW, NR-3
Supply AND Installation of Exhaust Fans in Bathrooms for Colony and Guest House including Supply and Installation of a Wash Basin in each C Type Quarter at Mainpuri Substation
NR3/NT/W-CIVIL/DOM/K00/26/07976
Limited
Civil - All
Works
Mainpuri Substation
₹10,000
5 Jun 2026
5 Jun 2026
24 Jun 2026
5 Jun 2026
22 Jun 2026
5 Jun 2026
Taking out doors, windows and clerestory window shutters (steel or wood) including stacking within 50 metres lead :Of area 3 sq. metres and below
Providing and fixing panelling or panelling and glazing in panelled or panelled and glazed shutters for doors, windows and clerestory windows (Area of opening for panel inserts excluding portion inside grooves or rebates to be measured). Panelling for panelled or panelled and glazed shutters 25 mm to 40 mm thick.5.0 mm thick glass panes (weight not less than 12.50 kg/sqm).
Providing and fixing factory made uPVC glazed/wire mesh windows/ doors comprising of lead free uPVC multi-chambered frame, sash and mullion/coupler (where ever required) extruded profiles having minimum wall thickness of 1.70 mm for Series R1 and R2 profiles and 2.10 mm for Series R3 and R4 profiles conforming to EN: 12608 in any shape, colour and design duly reinforced with galvanized mild steel section made of required shape & size as per CPWD Specification, uPVC extruded glazing beads, interlocks and Inline sash adaptor (where ever required) of appropriate dimension, EPDM gasket, hardware, SS 304 grade fasteners of minimum 8 mm dia with countersunk head, comprising of matching polyamide PA6 grade sleeve for fixing frame to finished wall as per IS 1367 : Part 1 to 14, plastic packers, plastic caps and necessary stainless steel screws etc. Profile of frame, sash & mullion (if required) shall be mitred cut and fusion welded/mechanically jointed duly sealed at all corners, including drilling of holes for fixing hardware and drainage of water etc. After fixing frame the gap between frame and adjacent finished wall shall be filled with weather proof silicon sealant over backer rod of approved size and quality, all complete as per approved drawing conforming to CPWD specification & direction of Engineer-in-Charge. Section of steel reinforcement and cross sections of uPVC profiles to be as per design approved by Engineer-in-Charge. Wire mesh / Glazing of plain/ toughened/ laminated/ double glass unit with / without high performance coatings as per design requirements and conforming to IS: 3548 & IS: 16231 shall be paid separately.Fixed window / ventilator with mullion / transom. Using R1 series with frame (33mm & above ) x (35mm & above) & mullion (33mm & above) x (50mm & above). (Height upto 0.90 metre) -
Providing and fixing Chlorinated Polyvinyl Chloride (CPVC) pipes, having thermal stability for hot & cold water supply, including all CPVC plain & brass threaded fittings, i/c fixing the pipe with clamps at 1.00 m spacing. This includes jointing of pipes & fittings with one step CPVC solvent cement and the cost of cutting chases and making good the same including testing of joints complete as per direction of Engineer in Charge:Concealed work, including cutting chases and making good the walls etc. :15 mm nominal bore
Providing and fixing Chlorinated Polyvinyl Chloride (CPVC) pipes, having thermal stability for hot & cold water supply, including all CPVC plain & brass threaded fittings, i/c fixing the pipe with clamps at 1.00 m spacing. This includes jointing of pipes & fittings with one step CPVC solvent cement and the cost of cutting chases and making good the same including testing of joints complete as per direction of Engineer in Charge:Concealed work, including cutting chases and making good the walls etc. : 25 mm nominal bore
Providing and fixing soil, waste and vent pipes : 75MM PVC SWR pipe IS 13592 Type B
Making connection of G.I. distribution branch with G.I. main of following sizes by providing and fixing tee, including cutting and threading the pipe etc. complete :25 to 40 mm nominal bore
Providing and fixing wash basin with C.I. brackets, 15 mm dia CP Brass single hole basin mixer of approved quality and make, including painting of fittings and brackets, cutting and making good the walls wherever required:- :White Vitreous China Wash basin size 550x400 mm with a15 mm CP Brass single hole basin mixer
Providing and fixing C.P. brass angle valve for basin mixer and geyser points of approved quality conforming to IS:893115 mm nominal bore
Providing and fixing C.P. Brass extension nipple (size 15mmx50mm) of approved make and quality as per direction of Engineer-in-charge
Providing and fixing 600x450 mm beveled edge mirror of superior glass (of approved quality) complete with 6 mm thick hard board ground fixed to wooden cleats with C.P. brass screws and washers complete
Providing and fixing 600x120x5 mm glass shelf with edges round off, supported on anodised aluminium angle frame with C.P. brass brackets and guard rail complete fixed with 40 mm long screws, rawl plugs etc., complete.
Supplying, Installation of exhaust fan upto 450mm sweep in the exisiting opening, including making the hole to suit the size of the above fan, making good the damage, connection, testing, commisssiong etc. as required.
Providing and fixing CP Brass 32mm size Bottle Trap of approved quality & make and as per the direction of Engineer-in-charge.
Name Surmane
Title
DD-MMM-YYYY
India
Udyam Certificate No.
Dessignation:
Ref. of page, Clause & Name of Documents
Date of Retirement/ Resignation from POWERGRID
Designation:
Yes /No
Partial offloading under a Contrct and/or Facilitation beyond 10% of the Contract Price shall also be treated as Termination. For the said purpose, the Contract price means the Contract Price of the Facilities notwithstanding the Construction of the Contract
In case POWERGRID has issued a letter in this regard wherein the firm has been put on hold from award of further contract(s) for a specified period and this specified period of hold is yet to expire, the bidder shall indicate “Yes” against this event.
For the purpose of working out 50% of the Contract, following shall be taken into account suitably:
Main aspect of the QR
50% of the total supply of Conductor/ Insulator under the Contract
50% of the total Transmission Line construction under the Contract
50% of the total bays construction under the Contract
50% of the total supply of Transformer/ Reactor under the Contract
50% of the total supply of GIS bays under the Contract
Regarding Sr. No. 6, in case of ‘Yes’, following information shall be submitted additionally:
Designation:
Designation:
Designation:
Designation:
Saving Account
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html
Annexure-I Instructions to Bidders.docx
docx • 0.08 MB
Annexure-II Conditions of Contract.docx
docx • 0.09 MB
Annexure-III Indicative BOQ.xlsx
xlsx • 0.02 MB
Annexure-III Make list.pdf
pdf • 0.37 MB
Annexure-III SFQP.pdf
pdf • 2.72 MB
Annexure-III Technicap specification.pdf
pdf • 0.35 MB
Appendix-I to Conditions of Contract.docx
docx • 0.03 MB
Attachment-4.DOCX
docx • 0.03 MB
Bid Form.xlsx
xlsx • 0.05 MB
Bid Security Format.docx
docx • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .