| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | 1₹14.6 LAccepted-AOC | ₹14.6 L | 1 | Accepted-AOC L1 |
| 2 | 2₹14.9 LRejected-Finance | ₹14.9 L | 2 | Rejected-Finance L2 |
| Sl No | Description | Qty | Unit | D RAJKUMAR L2 | R.SURESH KUMAR CONTRACTOR L1 |
|---|---|---|---|---|---|
| 1.00Name of the Work :1.Construction of Compound Wallin PU Ele School at Chinnajambukandi H/O 24.Veerapandi Panchayat in Periyanaickenpalayam Block in Coimbatore Dist under Fund 2025-26 | |||||
| 2.00 | Earth work excavation and depositing on bank with in initial lead of 10m and lift of 2m in hard gravelly soil as per SS 20 B for foundation | 61.5 | Cum | 250 ₹15,375 | 263.5 ₹16,205.25 |
| 3.00 | Cement concrete 1:4:8 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for foundation etc complete | 7.71 | Cum | 5,600 ₹43,176 | 5,598.5 ₹43,164.44 |
| 4.00 | Supply and erecting shuttering for sides and soffits for side walls including cost and conveyance of al materials and labour charges etc complete | 91.32 | Sqm | 550 ₹50,226 | 547.5 ₹49,997.70 |
| 5.00 | Supply and erecting shuttering for sides and soffits for side walls including cost and conveyance of al materials and labour charges etc complete | 69.55 | Sqm | 1,100 ₹76,505 | 1,095 ₹76,157.25 |
| 6.00 | FLY Ash Brick work in cement mortar 1:5 (One of cement and five of sand) using Fly Ash Brick in including scaffolding, proper setting, curing, etc., complete in all respects. | 57.3 | Cum | 7,500 ₹4.3 L | 7,446 ₹4.3 L |
| 7.00 | Fabricating and placing the steel grills for reinforcement for all reinforced cement concrete works such as plinth beam, lintels, beams, sunshade, roof and floor slabs etc., including cost of steel and fabricating the reinforcement grills in position etc., complete in all floors (The rate to include the cost of binding wire steel also) | 1.88 | mt | 92,000 ₹1.7 L | 91,988.5 ₹1.7 L |
| 8.00 | Reinforced Cement concrete 1:1½:3 (One of cement, one and a half of sand and three of hard broken granite stones ) using 20mm gauge hard broken granite stones for all reinforced cement concrete works excluding the cost and fabrication of reinforcement grills in position, shuttering, centering but including laying, vibrating, curing, finishing and providing Mild steel fan hooks in the RCC slab wherever necessary as directed by the departmental officers etc., complete in all respects | 21.1 | Cum | 9,400 ₹2.0 L | 9,355.5 ₹2.0 L |
| 9.00 | Plastering the walls with cement mortar 1:5 (One of cement and five of sand) 12mm thick including finishing smooth, scaffolding, setting, curing etc., complete as directed by the departmental officers. | 78.6 | Sqm | 300 ₹1.4 L | 284.22 ₹1.3 L |
| 10.00 | Painting the walls and ceiling two coats with approved exterior emulsion paint over one coat of priming coat of emulsion including cost and conveyance of all materials to site, through scrapping of old plastered surface, preparing the surface, curing etc., complete in all respects (S.I. No. 359B) | 459.6 | Sqm | 300 ₹1.4 L | 262.48 ₹1.2 L |
Tender Value
₹14.8 L
EMD Value
₹14,850
Closing Date
9 Feb 2026, 3:00 pmClosed
Commissioner, Panchayat Union, P.N.Palayam
Panchayat Union Office, Periyanaickenpalayam, Coimbatore
Construction of Compound Wall in PU Ele School at Chinnajambukandi Ho 24.Veerapandi Panchayat under UGF 2025-26
2026_RDTN_650902_1
Roc No.626/2025/A2 Dt.03.02.2026
Open Tender
Civil Works - Others
Panchayat Union Office, Periyanaickenpalayam, Cbe
Please refer Tender documents.
5 documents required · 5 mandatory
₹0
₹14,850
31 Mar 2026
4 Feb 2026
9 Feb 2026
4 Feb 2026
9 Feb 2026
4 Feb 2026
Name of the Work :1.Construction of Compound Wallin PU Ele School at Chinnajambukandi H/O 24.Veerapandi Panchayat in Periyanaickenpalayam Block in Coimbatore Dist under Fund 2025-26
Earth work excavation and depositing on bank with in initial lead of 10m and lift of 2m in hard gravelly soil as per SS 20 B for foundation
Cement concrete 1:4:8 mix using 40mm ISS metal including cost and conveyance of all materials to site and all labour charges for mixing, laying and curing etc complete for foundation etc complete
Supply and erecting shuttering for sides and soffits for side walls including cost and conveyance of al materials and labour charges etc complete
Supply and erecting shuttering for sides and soffits for side walls including cost and conveyance of al materials and labour charges etc complete
FLY Ash Brick work in cement mortar 1:5 (One of cement and five of sand) using Fly Ash Brick in including scaffolding, proper setting, curing, etc., complete in all respects.
Fabricating and placing the steel grills for reinforcement for all reinforced cement concrete works such as plinth beam, lintels, beams, sunshade, roof and floor slabs etc., including cost of steel and fabricating the reinforcement grills in position etc., complete in all floors (The rate to include the cost of binding wire steel also)
Reinforced Cement concrete 1:1½:3 (One of cement, one and a half of sand and three of hard broken granite stones ) using 20mm gauge hard broken granite stones for all reinforced cement concrete works excluding the cost and fabrication of reinforcement grills in position, shuttering, centering but including laying, vibrating, curing, finishing and providing Mild steel fan hooks in the RCC slab wherever necessary as directed by the departmental officers etc., complete in all respects
Plastering the walls with cement mortar 1:5 (One of cement and five of sand) 12mm thick including finishing smooth, scaffolding, setting, curing etc., complete as directed by the departmental officers.
Painting the walls and ceiling two coats with approved exterior emulsion paint over one coat of priming coat of emulsion including cost and conveyance of all materials to site, through scrapping of old plastered surface, preparing the surface, curing etc., complete in all respects (S.I. No. 359B)
GST Amount for providing Service to Government Contract Works for the above Construction Works. { GST Amount is the Total GST Amount for total overall quoted amount above this row in column "BB" for all works in this package}
Please Enable Macros to View BoQ information
stage.html
html • 0.04 MB
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 0.14 MB
BHCitech.pdf
Tender Documents • 0.54 MB
BHCprice.pdf
Tender Documents • 0.92 MB
BOQ_780480.xls
BOQ • 0.28 MB
Download all tender documents and submit your bid