| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹8.4 LAccepted-AOC | ₹8.4 L | L1 | Accepted-AOC L1 |
| 2 | L2₹8.4 LRejected-Finance | ₹8.4 L | L2 | Rejected-Finance L2 |
| Sl No | Description | Qty | Unit | Veerasekar.P L2 | Elayaraja L1 |
|---|---|---|---|---|---|
| 1.01 | Clearing and scurb / light jungle by cutting, removing and disposing of all materials such as bushes, scrubs, stumps, roots, grass, weeds, top organic soil not exceeding 150mm in thickness rybbish including cutting of tress up to 300mm girth KM-0/681-0/980 | 322.92 | M2 | 5.9 ₹1,905.23 | 5 ₹1,614.60 |
| 1.02 | Earth work excavation and classes of soils except hard rock requiring blasting depositing on bank with initial lead of 10M and lift of 2M including all labour charges and incidental charges such as shoring, strutting, providing coffer dams, bailing out KM-0/681-0/980 | 121.1 | M3 | 131.25 ₹15,894.38 | 130 ₹15,743 |
| 1.03 | Provind US Gravel with a lead of KM including cost and conveyance and stacking at side to departmental gauge for taking pre measurements by departmental officers and including labour charges for spreading the gravel as per standard specification etc.KM-0/681-0/980 | 17.94 | M3 | 661.7 ₹11,870.90 | 660 ₹11,840.40 |
| 1.04 | Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) specification including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 250mm thick with pavers in SubBase/Base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete. KM-0/681-0/980 | 140.16 | M3 | 2,846.9 ₹4.0 L | 2,846 ₹4.0 L |
| 1.05 | Applying PRIMECOAT over WMB/ WMM surface at 7.00Kg of SS-1 bitumen Emulsion / 10 sq.m including labour for spraying, hire charges for bitumen sprayer etc, Comp KM-0/681-0/980 | 1,121.25 | M2 | 79.2 ₹88,803 | 79 ₹88,578.75 |
| 1.06 | Applying TACK COAT over WMB/ WMM surface at 7.00Kg of SS-1 bitumen Emulsion / 10 sq.m including labour for spraying, hire charges for bitumen sprayer etc, Comp KM-0/681-0/980 | 1,121.25 | M2 | 18.1 ₹20,294.63 | 18 ₹20,182.50 |
| 1.07 | BITUMINOUS CONCRETE 25 MM THICK USING cmp (Grade-II) Providing and laying Bituminious concrete to 40mm thick using 0.08cum of 13.20-11.20mm. 0.11cum of 6.70-2.36 and 0.16 cum 2.36 and below with 50.3kgs of VG30/VG40 heating the bitumen and aggregates to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, carrying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonnes vibratory/phenumatic roller to the required density etc., including labour for attending to paver to site etc.including hire charges and fuel charges foe 20-30t CMP with bitumen boiler, tipper trucks,paver finisher/9m paver finisher,vibratory/phenumatic roller and all other tools and plants required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clauses 507 of MORTH Part-5 KM-0/681-0/980 | 28.03 | M2 | 10,786.7 ₹3.0 L | 10,786 ₹3.0 L |
Updated dates
Tender Value
₹10 L
EMD Value
₹10,000
Closing Date
2 Dec 2025, 4:00 pmClosed
Block Development Officer (BP)
Block Development Officer (BP)
Strengthening BT Road From Erumanur to Thottikuppam Road 0/681 0/980 in Vridhachalam Block
2025_RDTN_627843_1
A6/0972/2025 General Fund 2025-26 Vridhachalam Block
Open Tender
Civil Works - Roads
90 days
Panchayat union, Vridhachalam
as per tender
4 documents required · 4 mandatory
₹0
₹10,000
Yes
7 Jan 2026
1 Dec 2025
2 Dec 2025
1 Dec 2025
2 Dec 2025
1 Dec 2025
Amount
Clearing and scurb / light jungle by cutting, removing and disposing of all materials such as bushes, scrubs, stumps, roots, grass, weeds, top organic soil not exceeding 150mm in thickness rybbish including cutting of tress up to 300mm girth KM-0/681-0/980
Earth work excavation and classes of soils except hard rock requiring blasting depositing on bank with initial lead of 10M and lift of 2M including all labour charges and incidental charges such as shoring, strutting, providing coffer dams, bailing out KM-0/681-0/980
Provind US Gravel with a lead of KM including cost and conveyance and stacking at side to departmental gauge for taking pre measurements by departmental officers and including labour charges for spreading the gravel as per standard specification etc.KM-0/681-0/980
Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam(WMM) specification including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 250mm thick with pavers in SubBase/Base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete. KM-0/681-0/980
Applying PRIMECOAT over WMB/ WMM surface at 7.00Kg of SS-1 bitumen Emulsion / 10 sq.m including labour for spraying, hire charges for bitumen sprayer etc, Comp KM-0/681-0/980
Applying TACK COAT over WMB/ WMM surface at 7.00Kg of SS-1 bitumen Emulsion / 10 sq.m including labour for spraying, hire charges for bitumen sprayer etc, Comp KM-0/681-0/980
BITUMINOUS CONCRETE 25 MM THICK USING cmp (Grade-II) Providing and laying Bituminious concrete to 40mm thick using 0.08cum of 13.20-11.20mm. 0.11cum of 6.70-2.36 and 0.16 cum 2.36 and below with 50.3kgs of VG30/VG40 heating the bitumen and aggregates to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, carrying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 40mm with mechanical paver to the specified grades and cross sections and consolidated by 8-10 tonnes vibratory/phenumatic roller to the required density etc., including labour for attending to paver to site etc.including hire charges and fuel charges foe 20-30t CMP with bitumen boiler, tipper trucks,paver finisher/9m paver finisher,vibratory/phenumatic roller and all other tools and plants required, including fuel and all other incidental charges etc., complete as per specification using CMP as per clauses 507 of MORTH Part-5 KM-0/681-0/980
Veerasekar.P (BID ID -1525148)
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 0.64 MB
erumanur.pdf
Tender Documents • 1.63 MB
BOQ_750599.xls
BOQ • 0.29 MB
Download all tender documents and submit your bid