| Sl No | Description | Qty | Unit | IMPLA GENERAL SUPPLIERS L1 |
|---|---|---|---|---|
| 1.00Work items identified; | ||||
| 1.01 | Supply,Installation ,testing and commisioning of 9mtr (410 SP-33) long Steel Tubular Poles complete with base plate(350x350x5mm) with 50 mm dia hole, top cap, Earthing Channel(75x40x6) including digging of pit positioning etc, complete in all respect as per Standards. | 15 | Nos. | 15,000 ₹2.3 L |
| 2.01 | Supply,Installation ,testing and commisioning of 8 mtr (410 SP-15) long Steel Tubular Poles complete with base plate (350x350x5mm) with 50 mm dia hole, top cap, Earthing Channel(75x40x6) positioning etc, complete in all respect as pe Standards. | 40 | Nos. | 10,800 ₹4.3 L |
| 3.01 | Supply,laying, stringing, tensioning, binding of 50 Sqmm ACSR Conductor complete in all respects as per standards. | 10.5 | Km. | 40,000 ₹4.2 L |
| 4.01 | Supply Carraige upto site, fixing of
GI V cross-arm with top Bracket including clamp duly fabricated as per site requirement including clamps(50x8 mm), GI Nuts & Bolts,washers etc complete in all respects as per standards. | 315 | Kg | 105 ₹33,075 |
| 5.01 | Supply,Carraige upto site,Installation,testing and Commissioning of 11 KV polymer composite Pin Insulators 12 kv, 5KN, Lighting impulse 75 Kv positive and 80 Kv negative, Creepage distance 320mm complete in all respects as per standards. | 45 | No. | 160 ₹7,200 |
| 6.01 | Supply,Carraige upto site,Installation,testing and Commissioning of 11kV Polymeric composite Disc Insulator 12kV,min failing load 45kN, Lighting Impulse 75kV Positive and 80kV Negative, creepage distance 320mm as per standards. | 10 | set | 100 ₹1,000 |
| 7.01 | Supply,Carraige upto site and installation of GI Mukhi Clamp for Shackle insulators. | 200 | Kg. | 115 ₹23,000 |
| 8.01 | Supply,Carraige upto site and installation of 45 KN Shackle insulators. | 80 | No. | 20 ₹1,600 |
| 9.01 | Cement bottoming 1:2:4 mix as per Standards 0.45cum /0.5 cum pole as per drawings | 55 | Job | 1,000 ₹55,000 |
Tender Value
₹13 L
EMD Value
₹26,000
Closing Date
20 Feb 2026, 6:00 pmClosed
Executive Engineer, ED Budgam, KPDCL
ED Budgam, KPDCL
Replacement of Worn-out conductor and Rotton Poles under the jurisdiction of ED Budgam.
2026_PDD_302641_1
EDB/120 of 2025-26
Open Tender
Electrical and Maintenance Works
30 days
ED Budgam, KPDCL
AS PER SBD
7 documents required · 7 mandatory
₹1,000
Executive Engineer, ED Budgam, KPDCL
₹26,000
24 Feb 2026
9 Feb 2026
21 Feb 2026
9 Feb 2026
20 Feb 2026
10 Feb 2026
9 Feb 2026 - 10 Feb 2026
Work items identified;
Supply,Installation ,testing and commisioning of 9mtr (410 SP-33) long Steel Tubular Poles complete with base plate(350x350x5mm) with 50 mm dia hole, top cap, Earthing Channel(75x40x6) including digging of pit positioning etc, complete in all respect as per Standards.
Supply,Installation ,testing and commisioning of 8 mtr (410 SP-15) long Steel Tubular Poles complete with base plate (350x350x5mm) with 50 mm dia hole, top cap, Earthing Channel(75x40x6) positioning etc, complete in all respect as pe Standards.
Supply,laying, stringing, tensioning, binding of 50 Sqmm ACSR Conductor complete in all respects as per standards.
Supply Carraige upto site, fixing of GI V cross-arm with top Bracket including clamp duly fabricated as per site requirement including clamps(50x8 mm), GI Nuts & Bolts,washers etc complete in all respects as per standards.
Supply,Carraige upto site,Installation,testing and Commissioning of 11 KV polymer composite Pin Insulators 12 kv, 5KN, Lighting impulse 75 Kv positive and 80 Kv negative, Creepage distance 320mm complete in all respects as per standards.
Supply,Carraige upto site,Installation,testing and Commissioning of 11kV Polymeric composite Disc Insulator 12kV,min failing load 45kN, Lighting Impulse 75kV Positive and 80kV Negative, creepage distance 320mm as per standards.
Supply,Carraige upto site and installation of GI Mukhi Clamp for Shackle insulators.
Supply,Carraige upto site and installation of 45 KN Shackle insulators.
Cement bottoming 1:2:4 mix as per Standards 0.45cum /0.5 cum pole as per drawings
Earthing of steel tubular poles complete by GI pipe 40mm or GI rod 20mm 3.0 mtr long through GI strip 25*3 mm.
Painting of Poles with one coat of Red Oxide and two or more coats of alimunium paint to obtain proper finish/uniformity as per standards.
SITC of GI Barbed wire anticlimbing device with clamps complete in all respects as per standards.
SITC of danger plates with clamps complete in all respects as per standars
NOTE: 1.The rates quoted by the bidder for all the items shall be inclusive of GST/freight/insurance/storage/installation/testing and any other charges FOR Replacement of Worn-out conductor and Rotton Poles under the jurisdiction of ED Budgam., KPDCL.
Please Enable Macros to View BoQ information
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Tendernotice_1.pdf
PDF • 0.62 MB
Tendernotice_2.pdf
PDF • 1.60 MB
BOQ_982330.xls
BOQ • 0.26 MB
Download all tender documents and submit your bid