Loading…
Loading…
| # | Company | Quoted % | Amount | Rank | Status |
|---|---|---|---|---|---|
| 1 | L1₹25.7 LAdmitted-Finance | L1 | Admitted-Finance | ||
| 2 | Not Admitted-Fee/PreQual/Technical | - | Not Admitted-Fee/PreQual/Technical No EMD or Fee received |
Tender Value
₹27.7 L
EMD Value
₹55,420
Closing Date
21 Sept 2026, 6:00 pmClosed
ADPC SMSA PALI
ADARSH NAGAR, PALI
(4) Remanining work of Strengthening of existing school at GSSS Malnu Block Bali
2026_RCSCE_597330_4
Nit 03 Civil 2026-27 District Level
Open Tender
Civil Works
Percentage
Pali
Please Refer Bid Document
7 documents required · 7 mandatory
₹1,000
Yes
ADPC SMSA PALI/ MD RISL PALI
₹55,420
Yes
3 Oct 2026
14 Sept 2026
22 Sept 2026
14 Sept 2026
21 Sept 2026
14 Sept 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | PART-A (Building Work) Based on BSR PWD - 2019, Pali
Earth work in excavation by mechanical means (Hydraulic Excavator)/ manual means in foundation trenches or drains (not exceeding 1.5 m in width or 10 sqm on plan) including dressing of sides and ramming of bottoms, lift upto 1.5 m, including taking out the excavated soil and depositing and refilling of jhiri with watering & ramming and disposal of surplus excavated soil as directed with in a lead of 50 meter.
All kinds of soils | 76.25 | cum | 138 | ₹10,522.5 |
| 2 | Providing and laying in position cement concrete including curing compaction etc. of specified grade excluding the cost of centering and shuttering =All up to plinth leve. 1:4:8 (1Cement :4 Course Sand :8 Graded stone aggregate 40 mm nominal size | 13.19 | cum | 2,522 | ₹33,265.18 |
| 3 | Providing and laying cement concrete including curing, compaction etc. complete in retaining walls, return walls (any thickness) including attached pilasters, coloumns, pillars, posts, struts, buttresses, string or lacing courses, parapets, coping, bed blocks, plain window sills, fillets etc up to floor three level excluding the const centering and shuttering.1:1.5:3 (1Cement :1.5 Course Sand :3 Graded stone aggregate 20 mm nominal size | 0.77 | Cum | 3,860 | ₹2,972.2 |
| 4 | Providing and laying in position specified grade of reinforced cement concrete including curing compaction finishing with rendering in cement sand mortar 1:3 (1-Cement:3-coarse sand) and making good the joints excluding the cost of centering, shuttering and reinforcement. All work up to plinth level : 1:1.5:3 (1-Cement:1.5 coarse sand:3-graded stone aggregate 20 mm nominal size) | 6.93 | cum | 3,984 | ₹27,609.12 |
| 5 | Reinforced cement concrete work in beams, suspended floors, roofs, girders having slopes up to 15o , landings, balconies, shelves, chajjas, lintels, bands, plain windows sills, staircases and spiral staircases, up to floor three level including curing, compaction, finishing with rendering in cement sand mortar 1:3 (1-Cement:3-coarse sand) and making good and joints excluding the cost of centering, shuttering and reinforcement: 1:1.5:3 (1-Cement:1.5 coarse sand:3-graded stone aggregate 20 mm nominal size). | 50.57 | cum | 4,347 | ₹2,19,827.79 |
| 6 | Reinforced cement concrete work in walls (any thickness) including attached pilasters, buttresses, plinth and string courses, fillets, columns, pillars, piers, abutments, posts and struts etc. up to floor three level including curing, compaction, finishing with rendering in cement sand mortar 1:3 (1-Cement:3-coarse sand) and making good the joints excluding cost of centering shuttering and reinforcement :1:1:2 (1-Cement:1-coarse sand:2-graded stone aggregate 20 mm nominal size). | 3.33 | cum | 4,778 | ₹15,910.74 |
| 7 | Centering and shuttering with plywood or steel sheets including strutting, propping, bracing both ways and removal of formwork for foundations in basements rafts, footings, strap beams, bases of columns , etc. up to plinth level. | 7.88 | sqm | 107 | ₹843.16 |
| 8 | Centering and shuttering with plywood or steel sheets including strutting, propping, bracing both ways with wooden members and removal of formwork for superstructure up to 4.5 mtr above plinth, for: Suspended floors, roofs, landings, staircases, balconies, girders, cantilevers, bands , coping, bed plates, anchor blocks, sills, chhajjas lintel, beam etc. | 390.93 | sqm | 231 | ₹90,304.83 |
| 9 | Centering and shuttering with plywood or steel sheets including strutting, propping, bracing both ways with wooden members and removal of formwork for superstructure up to 4.5 mtr above plinth, for: Columns, pillars, posts and struts etc. | 73.67 | sqm | 246 | ₹18,122.82 |
| 10 | Providing and fabricating reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding (including cost of binding wire) all complete up to floor five level.
('Original producers' who manufacture billet directly from iron ores and roll the bilets to produce steel conforming to IS:1786) Tremo Mechanically treated bars | 4,056.56 | kg | 70 | ₹2,83,959.2 |
stage.html
html • 0.03 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 4.97 MB
Tendernotice_2.pdf
PDF • 0.11 MB
Tendernotice_3.pdf
PDF • 0.53 MB
Tendernotice_4.pdf
PDF • 9.61 MB
BOQ_1059355.xls
BOQ • 0.39 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .