| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.9 CrAccepted-AOC | ₹1.9 Cr | L1 | Accepted-AOC Responsive |
| 2 | L2₹1.9 Cr+₹3.7 L (1.92%)Rejected-Finance | ₹1.9 Cr+₹3.7 L (1.92%) | L2 | Rejected-Finance Not Responsive |
| 3 | L3₹2.0 Cr+₹7.6 L (3.99%)Rejected-Finance | ₹2.0 Cr+₹7.6 L (3.99%) | L3 | Rejected-Finance Not Responsive |
| 4 | Not Admitted-Fee/PreQual/Technical/Finance | - | - | Not Admitted-Fee/PreQual/Technical/Finance Others-Non Deposition Of original EMD |
Tender Value
Refer Docs
EMD Value
₹3.9 L
Closing Date
23 Mar 2022, 1:00 pmClosed
Executive Engineer
O/o Executive Engineer Naharlagun Division PWD, AP, Naharlagun
C/o. CC approach road to Galo Heritage Cum Mopin Ground at Tarajuli near Railway Station, Naharlagun.
2022_PWDAP_651_1
ND/ 2021- 22/14
Open Tender
Civil Works
Item Rate
90 days
Naharlagun
Please refer Tender documents.
3 documents required · 3 mandatory
₹0
₹3.9 L
Yes
Naharlagun
31 Mar 2022
18 Mar 2022
25 Mar 2022
18 Mar 2022
23 Mar 2022
18 Mar 2022
19 Mar 2022
Amount
CEMENT CONCRETE ROAD
Preparation of Sub Grade:) Preparation of sub grade (Preparation of sub grade by excavating earth to an average depth of 22.50 cm, dressing to camber and consolidating with road roller, making good the undulations etc. and disposal of surplus earth, lead upto 50 m.
Consolidation of sub-grade with road roller of 8 to 12 tonne capacity including making good the undulations etc. with earth or quarry spoils etc. and rerolling the sub grade
By Mix in Place Method (Construction of granular sub-base by providing close graded material, spreading in uniform layers with motor grader on prepared surface, mixing by mix in place method with rotavator at OMC, and compacting with vibratory roller to achieve the desired density, complete as per clause 401) a0 Grading I material
Dry Lean Cement Concrete Sub- base (Construction of dry lean cement concrete Sub- base over a prepared sub-grade with coarse and fine aggregate conforming to IS: 383, the size of coarse aggregate not exceeding 25 mm, aggregate cement ratio not to exceed 15:1, aggregate gradation after blending to be as per table 600-1, cement content not to be less than 150 kg/ cum, optimum moisture content to be determined during trial length construction, concrete strength not to be less than 10 Mpa at 7 days, mixed in a batching plant, transported to site, laid with a paver with electronic sensor, compacting with 8-10 tonnes vibratory roller, finishing and curing.)
Cement Concrete Pavement (Construction of un-reinforced, dowel jointed, plain cement concrete pavement over a prepared sub base with 43 grade cement @ 400 kg per cum, coarse and fine aggregate conforming to IS 383, maximum size of coarse aggregate not exceeding 25 mm, mixed in a batching and mixing plant as per approved mix design, transported to site, laid with a fixed form or slip form paver, spread, compacted and finished in a continuous operation including provision of contraction, expansion, construction and longitudinal joints, joint filler, separation membrane, sealant primer, joint sealant, debonding strip, dowel bar, tie rod, admixtures as approved, curing compound, finishing to lines and grades as per drawing )
Cable Duct Across the Road (Providing and laying of a reinforced cement concrete pipe duct, 300 mm dia, across the road (new construction), extending from drain to drain in cuts and toe of slope to toe of slope in fills, constructing head walls at both ends, providing a minimum fill of granular material over top and sides of RCC pipe as per IRC:98-1997, bedded on a 0.3 m thick layer of granular material free of rock pieces, outer to outer distance of pipe at least half dia of pipe subject to minimum 450 mm in case of double and triple row ducts, joints to be made leak proof, invert level of duct to be above higher than ground level to prevent entry of water and dirt, all as per IRC: 98 - 1997 and approved drawings.) i)Single Row for Single utility services
Anchor Beam :
Excavation for Structures (Earth work in excavation of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and backfilling with approved material.)
PCC 1:3:6 in Foundation (Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days.)
Plain/Reinforced cement concrete in open foundation complete as per drawing and technical specifications. PCC grade M20 using concrete mixer
Reinforcement of RCC work including bending, binding and placing in position complete.b) Cold twisted bars.
EMBANKMENT FILLING
Embankment Construction with Material Obtained from Borrow Pits Construction of embankment with approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading to required slope and compacting to meet requirement of table 300-2
CC Drain
Excavation for Structures (Earth work in excavation of foundation of structures as per drawing and technical specification, including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and bottom, backfilling the excavation earth to the extent required and utilising the remaining earth locally for road work.) I Ordinary soil A Manual Means (i) upto 3 m depth
PCC 1:3:6 in Foundation (Plain cement concrete 1:3:6 nominal mix in foundation with crushed stone aggregate 40 mm nominal size mechanically mixed, placed in foundation and compacted by vibration including curing for 14 days.)
Plain/Reinforced cement concrete in open foundation complete as per drawing and technical specificationsPCC Grade M20
M/s Raj Steel
M/s J J Construction
stage.html
html • 0.04 MB
tech_eval.pdf
fin_eval.pdf
aoc.pdf
finance_727.pdf
boq_comp_chart.xlsx
xlsx
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .