| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L-1₹30.1 LAccepted-AOC 101 KRISHNA VIHAR RAILWAY COLONY QUARSI RAMGHAT ROAD ALIGARH | L-1 | Accepted-AOC L-1 | |
| 2 | L-2₹32.2 L+₹2.1 L (6.97%)Rejected-Finance | L-2 | Rejected-Finance L-2 | |
| 3 | L-3₹34.5 L+₹4.4 L (14.6%)Rejected-Finance | L-3 | Rejected-Finance L-3 | |
| 4 | Rejected-Technical | - | Rejected-Technical document not complete |
Tender Value
₹38.4 L
EMD Value
₹76,720
Closing Date
19 Jan 2024, 5:00 pmClosed
S.E.DRAINAGE CIRCLE ALIGARH
S.E.DRAINAGE CIRCLE ALIGARH
Construction of New V.R.B. no Km.0.715, Km. 2.505 And Km. 14.100 and Repairs of V.R.B. on 4.610, Km. 5.380, Km. 5.720, Km. 13.650 and Km. 15.350 and Construction of Boundry Piller on Kulba Dy.
2024_UPIDC_877340_2
05/S.E/2023-24
Open Tender
Civil Works
Item Wise
180 days
E.E.ALIGARH DIVISION GANGGA CANAL ALIGARH
Please refer Tender documents.
2 documents required · 2 mandatory
₹1,354
₹76,720
12 Mar 2024
10 Jan 2024
20 Jan 2024
10 Jan 2024
19 Jan 2024
10 Jan 2024
Amount
Filling empty cement bags with earth sewing and placing in position upto 60m lead to Protect Bundhasa as directed by Engineer-in-charge.
Earth work in axcavation in foundation in all types of soil with all lead and lift i/c cost of labur and T and P.
Laying C.C In 1:4:8 in foundation(Cement coarse sand and stone grite 10-25mm size) includig all cost of material labour T and P etc.
Ist.Class brick work in 1:4 CM. with cement and coarse sand i/c all cost of material labour and T and P etc.
Centering and shuttering for RCC work including all cost of material,labour and T and P etc.
Providing R.C.C In 1:1.5:3(Cement:Coarse sand: cressed aggregated of required size) including cost of all material labour, T and P,etc.As per direction of Engineer-in-charge.
Providing and fixing steel Reinforcement for R.C.C work i/ccost of steel ,bending,binding and placing in position i/c all cost of material,labour and T and P etc. complete
Struck deep pointing in 1:3 on brick masonry, cement, fine sand including cost of all material, labour and T and P etc. complete
Providing and Fixing 75mm dia PVC. Pipe for weep holes including all cost of material labour T7P as per direction of Engineer-in-charge
Providing and fixing C.I Jali 100X100mm size including all cost of materiala labbour T and P as per direction of Engineer-in-charge
S/F of wheel gard size 750X200X200mm including all cost of materiaal labour T and P.
S/F of year mark marble plate size 300X300X25mm including all cost of material labour T and P.
Finishing walls(Two Coats) with water proofing cement paint of approved make such ass Superscem,Durocem,Robiance,Guttucem,Supercem quality and of required shade on undecorated wall surface over and including one coat white cement primer to give and even shade after thoroughly brushing the surface, including cost of all materials labours, T&P etc. complete required for proper completion of the work.
Finishing walls with Acrylic Smooth exterior paint(Apex) of required shade : New Work(Two or more coat applied 1.67 ltr/10 sqm over and including priming coat of exterior primer applied 2.20kg/10 sqm)
CA CONSTRUCTION WORK AND ENGINEERING SERVICE
SHUBHAM SHARMA
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .