| # | Company | Amount | Status |
|---|---|---|---|
| 1 | ₹49.9 LAWARDED | ₹49.9 L | AWARDED |
Tender Value
₹1.1 Cr
EMD Value
₹1.1 L
Closing Date
3 Feb 2026, 9:30 pmClosed
Karnataka Power Corporation Limited
Procurement of worm gear and shaft of mill gear box of Unit 3 & 4 of RTPS
51168
KPCL/2025-26/IND2351
Open
KPCL Executive Engineer Purchase Office RTPS Raichur
7 documents required · 4 mandatory · 3 optional
a) For Manufacturers: The intending bidder shall have successfully supplied Worm Shaft and worm gear of Cleveland-USA or CMD-France make to any government sector/PSU/Major power plants/Reputed private sector major industries amounting to not less than Rs. 86.20 lakhs (Rs. 43.10 lakhs for Micro and small Enterprises) in any one year of the preceding three financial years i.e. 2022-23, 2023-24 & 2024-25 (2 year for Micro and small Enterprises i.e. 2023-24 & 2024-25) As a proof purchase order (PO) copies (Single/Multiple (max.3)) for any one of the said financial year during which supplies are made shall be uploaded. b) For Authorized importer/Authorized dealers etc: The intending bidder shall have successfully supplied Worm Shaft and worm gear of Cleveland-USA or CMD-France make to any government sector /PSU/Major power plants/Reputed private sector major industries amounting to not less than Rs. 32.32 lakhs in any one year of the preceding three financial years i.e. 2022-23, 2023-24 & 2024-25.
The intending bidder shall be Manufacturer/ authorized importer / authorized dealer of Worm Shaft and worm gear of Cleveland-USA or CMD-France make. As a proof bidder shall upload valid registration certificate/importer certificate/dealership certificate issued by the Competent Authority/ relevant documents in e-portal.
The annual financial turnover of the tenderer should be not less than Rs. 107 lakhs (Rs. 53.50 lakhs for Micro and small Enterprises) during the last 3 preceding financial years (last 2 preceding financial years respect to Micro and small Enterprises). As a proof the bidder shall upload the certified copy of the Annual turnover certificate/Profit & Loss statement duly certified by the Chartered Accountant.
₹500
₹1.1 L
20 Jan 2026
20 Jan 2026
4 Feb 2026
29 Jan 2026
27 Jan 2026
ANNEXURE Procurement of Worm gear and shaft of mill gear box of Unit 3&4 of RTPS
SL NO IIMS CODE ITEM NAME ITEM SPECIFICATIONS UNIT % of GST included in quoted rates HSN Code BRAND/ MAKE Bidder's Compliance/ Remarks
1 522420461R WORM GEAR & SHAFT HP-803 MGB Worm Gear (Wheel) and Worm Shaft in Matching Set along with Lock Nut & Keys for HP 803 Bowl Mills of Units 3 & 4, having 36" Center Distance. Make: M/s Cleaveland-USA OR CMD- FRANCE Only. BHEL Spare Code : HY611810493001. WORM GEAR : As per BHEL Drawing No 2-61-180-018 Rev 04, Outer Dia 1648 mm, Pitch Dia 1592.2 mm, Circular Pitch 63.32 mm(2.493"), 24 Holes Drull at Dia 32 mm 1.5x45' Chamf. Material : Z102-4 (AGMA-Grade) or GZ -CuSn12Ni2. No of Teeth : 79 RH, Gear Ratio : 79/7. WORM SHAFT : As per BHEL Drawing No 1-61-180-00511 Rev 03, Outer Dia 10.839", Pitch Dia 7.481", Circular Pitch 2.493", Material : 20MnCr5, AISE 4150 Forged Steel Worm Shaft with Flame Case Hardened to 56-60 RC on all Tooth Surface and ground. No of Starts : 07 RH. Along with Lock Nut, Keys, Test Certificate, Guarantee Certificate, Inspection Report, Interchangability Certificate and Import Certificate. SETS
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
pqr conditions.docx
Others - PQR • 0.02 MB
Annexure- Specifications.xlsx
Technical Information / Worksheet • 0.01 MB
special conditions.docx