| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹1.7 CrAccepted-AOC HARDAHA BALUWA VARANASI CHANDAULE | ₹1.7 Cr | L1 | Accepted-AOC L1 |
| 2 | L2₹1.8 Cr+₹5.5 L (3.18%)Rejected-AOC | ₹1.8 Cr+₹5.5 L (3.18%) | L2 | Rejected-AOC L2 |
| 3 | L3₹1.9 Cr+₹17.9 L (10.3%)Rejected-AOC | ₹1.9 Cr+₹17.9 L (10.3%) | L3 | Rejected-AOC L3 |
| 4 | L4₹1.9 Cr+₹20.8 L (12.0%)Rejected-AOC 00 KANDHARPUR NEAR JUNIOR HIGH SCHOOL KANDHARPUR BAREILLY UTTAR PRADESH 243004 UDYAM UP 15 0021222 | BAREILLY | UTTAR PRADESH | 243004 | ₹1.9 Cr+₹20.8 L (12.0%) | L4 | Rejected-AOC L4 |
| 5 | Rejected-Technical 0 BARAGOAN JANGIGANJ BHADOHI SANT RAVIDAS NAGAR UTTAR PRADESH 221310 | BHADOHI | UTTAR PRADESH | 221310 | - | - | Rejected-Technical Invalid Tender |
Tender Value
₹2.0 Cr
EMD Value
₹19.6 L
Closing Date
8 Jun 2026, 3:00 pmClosed
chief Engineer nagar nigam saharanpur
chief Engineer nagar nigam saharanpur
construction of RCC convert from dhamola nadi earlier break the small bridge for devendra nagar at ward no. 13
2026_NNSAH_1151476_1
2364 G
Open Tender
Civil Works
Percentage
60 days
saharanpur
Please refer Tender documents.
2 documents required · 2 mandatory
₹2,950
₹19.6 L
18 Sept 2026
23 May 2026
9 Jun 2026
23 May 2026
8 Jun 2026
23 May 2026
This is a percentage-rate BOQ. The schedule below shows estimated quantities and rates. Bidders quote a single percentage above or below the total estimated cost.
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 1 | Earthwork in Excavation in dry soil with manual labour ive disposal of earth, labour, T&P etc. for complettion of work | 1,184.99 | cum | 122.5 | ₹1,45,161.28 |
| 2 | Brick ballast M-15, 4.00 CM gauge all material, labour and T&P etc. | 90 | cum | 900 | ₹81,000 |
| 3 | C.C. 1:2:4 (M-15)with stone ballast 10 to 20 mm/ cum i/e all cost of material, labour. T&P ete for proper completion of work/cum | 370.71 | cum | 5,750 | ₹21,31,582.5 |
| 4 | R.C.C. 1:1:2 (M-25) i/e all cost of material, labour. T&P etc for proper completion of work | 720.44 | cum | 7,803.3 | ₹56,21,809.45 |
| 5 | Providing & laying Wearing Coat with 1:1.5:3 cement concrete i/c all cost of material, labour T&P etc complete. | 2.1 | cum | 7,803.3 | ₹16,386.93 |
| 6 | Supplying and filling brick bats | 79.2 | cum | 800 | ₹63,360 |
| 7 | Steel Reinforcement (TMT) i/e cost of material labour. T & P etc for proper completion of work | 621 | mt | 8,529 | ₹52,96,509 |
| 8 | Providing and fixing P.V.C. pipe 75mm dia & 6Kg./cm Sq. I.S.I. Mark including all cost of materials, T&P and labour etc. | 10 | No | 115 | ₹1,150 |
| 9 | Laying R.cc hume pipe 1200 mm dia including labour, T&P etc. complete. | 100 | rm | 12,460 | ₹12,46,000 |
| 10 | E/W for making diversion & ramp on both side of bridge by power transport | 4,987.18 | cum | 180 | ₹8,97,692.4 |
stage.html
html • 0.05 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.03 MB
Tendernotice_1.pdf
PDF • 3.40 MB
BOQ_2156809.xls
BOQ • 0.24 MB
corregendumnit33.pdf
PDF • 0.52 MB
corrigendum26.pdf
PDF • 0.37 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .