| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹28.1 CrAccepted-AOC THOTTAPPALLY HOUSE EMILY KALPETTA P O KERALA 673121 | WAYANAD | KERALA | 673121 | L1 | Accepted-AOC BEING L1 | |
| 2 | L2₹31.1 Cr+₹3.0 Cr (10.6%)Rejected-AOC 4 195 38 PARAMESHWARA NILAYA MARAKADA KUNJATHBAIL DAKSHINA KANNADA KARNATAKA 575014 UDYAM KR 11 0021217 | DAKSHINA KANNADA | KARNATAKA | 575014 | L2 | Rejected-AOC NOT BEING L1 | |
| 3 | L3₹31.6 Cr+₹3.5 Cr (12.3%)Rejected-AOC NO 11 WEST CAR STREET RAMANATHAPURAM TAMILNADU 623501 | RAMANATHAPURAM | RAMANATHAPURAM | TAMILNADU | 623501 | L3 | Rejected-AOC NOT BEING L1 | |
| 4 | L4₹32.2 Cr+₹4.1 Cr (14.6%)Rejected-AOC K 99 LGF KALKAJI NEW DELHI 110 019 | NEW DELHI | NEW DELHI | DELHI | 110019 | L4 | Rejected-AOC NOT BEING L1 | |
| 5 | L5₹33.1 Cr+₹5.0 Cr (17.7%)Rejected-AOC H NO 12 2 823 A 45 FLAT NO 45 SANTHOSH NAGAR COLONY MEHIDIPATNAM HYDERABAD 500025 | HYDERABAD | HYDERABAD | TELANGANA | 500025 | L5 | Rejected-AOC NOT BEING L1 |
| Sl No | Description | Qty | Unit | SHAIJAL T M L1 | Jas & Co L8 | M/s Imperial Coastal Infra L5 | GOVARDHAN AND COMPANY L2 | C R R CONSTRUCTIONS L6 | SOOD ASSOCIATES PVT LTD L4 | UNITED TECHNO PROJECTS PVT LTD L7 | SRI RAMANA BUILDING CONSTRUCTIONS PRIVATE LIMITED L3 |
|---|---|---|---|---|---|---|---|---|---|---|---|
| .50BOQ Dated Sep 2025 | |||||||||||
| .75GENERAL SUMMARY NOTE: Schedule ‘A’ Part I to XII are prepriced by MES under Ser No. 1 to 12. Bidders shall insert their lumpsum amount in the Green coloured field under Col-6 only. | |||||||||||
| 1.00 | Lumpsum price worked out by the contractor for “Building or Works” as listed in Schedule ‘A’ Part–I | 1 | Lumpsum | 20,11,270 ₹20,11,270 Lowest | 30,30,300 ₹30,30,300 | 28,88,000 ₹28,88,000 | 29,25,635 ₹29,25,635 | 28,49,000 ₹28,49,000 | 21,49,700 ₹21,49,700 | 30,56,200 ₹30,56,200 | 28,49,000 ₹28,49,000 |
| 2.00 | Lumpsum price worked out by the contractor for “Internal Water Supply" as listed in Schedule ‘A’ Part–II | 1 | Lumpsum | 67,950 ₹67,950 | 73,500 ₹73,500 | 75,000 ₹75,000 | 63,740 ₹63,740 Lowest | 83,010 ₹83,010 | 1,04,949.35 ₹1,04,949.35 | 85,975.46 ₹85,975.46 | 65,000 ₹65,000 |
| 3.00 | Lumpsum price worked out by the contractor for “Internal Electric Supply" as listed in Schedule ‘A’ Part - III. | 1 | Lumpsum | 13,82,330 ₹13,82,330 | 17,10,000 ₹17,10,000 | 14,88,000 ₹14,88,000 | 14,75,000 ₹14,75,000 | 16,15,800 ₹16,15,800 | 12,19,248.48 ₹12,19,248.48 Lowest | 14,68,974.07 ₹14,68,974.07 | 16,00,000 ₹16,00,000 |
| 4.00 | Lumpsum price worked out by the contractor for "Site Clearance and Area Development" as listed in Schedule ‘A’ Part - IV . | 1 | Lumpsum | 1,25,60,930 ₹1,25,60,930 | 2,19,00,000 ₹2,19,00,000 | 2,68,58,788 ₹2,68,58,788 | 2,05,00,000 ₹2,05,00,000 | 2,20,94,900 ₹2,20,94,900 | 1,08,42,847.06 ₹1,08,42,847.06 Lowest | 2,04,58,202 ₹2,04,58,202 | 2,50,00,000 ₹2,50,00,000 |
| 5.00 | Lumpsum price worked out by the contractor for "Road / Hardstanding / Culvert" as listed in Schedule ‘A’ Part - V . | 1 | Lumpsum | 59,76,980 ₹59,76,980 Lowest | 98,65,000 ₹98,65,000 | 98,04,764 ₹98,04,764 | 78,93,407 ₹78,93,407 | 96,06,800 ₹96,06,800 | 82,20,353.13 ₹82,20,353.13 | 1,04,39,848.48 ₹1,04,39,848.48 | 86,42,000 ₹86,42,000 |
| 6.00 | Lumpsum price worked out by the contractor for "Area Drainage" as listed in Schedule ‘A’ Part - VI . | 1 | Lumpsum | 29,21,670 ₹29,21,670 Lowest | 44,27,000 ₹44,27,000 | 42,00,000 ₹42,00,000 | 34,67,805 ₹34,67,805 | 43,13,800 ₹43,13,800 | 40,49,009.42 ₹40,49,009.42 | 44,65,262.72 ₹44,65,262.72 | 39,62,500 ₹39,62,500 |
| 7.00 | Lumpsum price worked out by the contractor for "Sewage Disposal" as listed in Schedule ‘A’ Part - VII . | 1 | Lumpsum | 4,11,270 ₹4,11,270 | 2,46,000 ₹2,46,000 | 2,18,000 ₹2,18,000 Lowest | 2,35,000 ₹2,35,000 | 2,35,082 ₹2,35,082 | 3,29,536.15 ₹3,29,536.15 | 2,47,676.86 ₹2,47,676.86 | 2,20,000 ₹2,20,000 |
| 8.00 | Lumpsum price worked out by the contractor for "Retaining Wall" as listed in Schedule ‘A’ Part - VIII . | 1 | Lumpsum | 3,38,97,640 ₹3,38,97,640 Lowest | 5,34,89,000 ₹5,34,89,000 | 5,18,88,000 ₹5,18,88,000 | 4,50,97,131 ₹4,50,97,131 | 5,20,94,190 ₹5,20,94,190 | 5,44,19,824.11 ₹5,44,19,824.11 | 4,65,12,670.18 ₹4,65,12,670.18 | 5,50,00,000 ₹5,50,00,000 |
Tender Value
₹34.8 Cr
EMD Value
₹15 L
Closing Date
26 Sept 2025, 6:00 pmClosed
Eligibility, documents, scope and key termsEligibility, required documents, scope of work and key terms of this tender, in one click.
Chief Engineer AF Bangalore
Chief Engineer AF Bangalore No. 2 DC Area MES Road Yeshwantpur Post Bangalore 560022
CONSTRUCTION OF BASE OPERATION CONTROL CENTRE (BOCC) AT AF STN THANJAVUR
2025_MES_724617_1
801679/AF/E8
Open Tender
Civil Works
Lump-sum
660 days
GE(AF)THANJAVUR
AS PER NIT
8 documents required · 8 mandatory
₹3,000
GE(AF)THANJAVUR
₹15 L
Yes
28 Oct 2025
5 Aug 2025
3 Oct 2025
5 Aug 2025
26 Sept 2025
19 Sept 2025
6 Aug 2025 - 14 Aug 2025
| Sl No | Description | Qty | Unit | Est. Rate | Est. Amount |
|---|---|---|---|---|---|
| 0.5 | BOQ Dated JUL 2025 | - | - | - | - |
| 0.75 | GENERAL SUMMARY
NOTE: Schedule ‘A’ Part I to XII are prepriced by MES under Ser No. 1 to 12. Bidders shall insert their lumpsum amount in the Green coloured field under Col-6 only. | - | - | - | - |
| 1 | Lumpsum price worked out by the contractor for “Building or Works” as listed in Schedule ‘A’ Part–I | 1 | Lumpsum | 25,90,000 | ₹25,90,000 |
| 2 | Lumpsum price worked out by the contractor for “Internal Water Supply" as listed in Schedule ‘A’ Part–II | 1 | Lumpsum | 59,293.42 | ₹59,293.42 |
| 3 | Lumpsum price worked out by the contractor for “Internal Electric Supply" as listed in Schedule ‘A’ Part - III. | 1 | Lumpsum | 11,11,967.17 | ₹11,11,967.17 |
| 4 | Lumpsum price worked out by the contractor for "Site Clearance and Area Development" as listed in Schedule ‘A’ Part - IV . | 1 | Lumpsum | 2,04,58,202 | ₹2,04,58,202 |
| 5 | Lumpsum price worked out by the contractor for "Road / Hardstanding / Culvert" as listed in Schedule ‘A’ Part - V . | 1 | Lumpsum | 84,99,755.83 | ₹84,99,755.83 |
| 6 | Lumpsum price worked out by the contractor for "Area Drainage" as listed in Schedule ‘A’ Part - VI . | 1 | Lumpsum | 37,84,120.95 | ₹37,84,120.95 |
| 7 | Lumpsum price worked out by the contractor for "Sewage Disposal" as listed in Schedule ‘A’ Part - VII . | 1 | Lumpsum | 2,09,895.64 | ₹2,09,895.64 |
| 8 | Lumpsum price worked out by the contractor for "Retaining Wall" as listed in Schedule ‘A’ Part - VIII . | 1 | Lumpsum | 4,65,12,670.18 | ₹4,65,12,670.18 |
stage.html
html • 0.06 MB
tech_bid_open.pdf
tech_eval.pdf
fin_bid_open.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
BOQ_811083.xls
BOQ • 0.62 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .