CONSTRUCTION OF P.C.C ROAD AND DRAIN FROM PIYUSH KUMAR HOUSE TO KISAN BHAWAN UNDER NAGAR PANCHAYAT SHEKHOPURSARAI. (Group- 07)
127644
NIT 07/2025 - 26/ GR- 07
Open Tender
CIVIL
Jamui
• REGISTRATION
• PAN CARD
• GST
• ANY OTHER DOCUMENTS AS PER NIT
CIVIL
PERCENTAGE
L1
1
8 documents required · 8 mandatory
₹10,000
Processing Fee: 590
₹1.4 L
OFFICE AT NAGAR PANCHAYAT SHEIKHOPURSARAI
17 Mar 2026
17 Mar 2026
1 Apr 2026
17 Mar 2026
28 Mar 2026
17 Mar 2026
18 Mar 2026
ESTIMATE FOR CONSTRUCTION OF P.C.C ROAD AND DRAIN FROM PIYUSH KUMAR HOUSE TO KISAN BHAWAN UNDER NAGAR PANCHAYAT SHEKHOPURSARAI.
SL. NO ITEM QTY UNIT RATE AMOUNT
1 demolishing cement cocreate including disposal of material 396.72 M3 970.90 385175.00
2 Supplying and stacking at site 53mm to 22.4mm size stone 238.82 M3 883.70 211045.00
3 supplying andstacking at site moorum 238.82 M3 431.20 102979.00
4 Laying Spreading and compacting stone aggregate of specified size to WBM 238.82 M3 487.00 116305.00
5 Providing and laying in position cement concrete of specified grade exluding the cost of centring and shuttering-all work upto plinth level.1:1.5:3(1 Cement :1.5 coarse sand:3 graded stone aggregate 20 mm nominal size) 398.03 M3 5418.60 2156765.00
6 Centring and shuttering including strutting, propping etc. and removal of form for Walls (any thickness) including attached pilasters. Butteresses, plinth and string courses etc 217.50 M2 211.10 45914.00
7 Earth work in excavation in foundation trenches or drains(not exceeding 1.5 m in width or 10 sqm on plan) including dressing of sides and ramming of bottoms, lift upto 1.5 m . including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. 855.50 M3 383.70 328255.00
8 Supplying and Filling in plinth with local sand and under floors including, watering , ramming consolidating and dressing complete. 44.18 M3 287.30 12693.00
9 Providing designation 100 A one brick flat soling joints filled with local sand including cost of watering, taxes, royalty all complete as per building specification and direction of E/l, 567.31 M2 283.30 160719.00
10 Providing and laying in position cement concreate of specified grade excluuding the cost of centring and shuttering all work upto plinth level 1:2:4 47.58 M3 3998.10 190230.00
11 100A brick work(1:4) cement mortar 39.41 M3 5017.90 197755.00
12 Providing and laying in position specified grade of reinforced cement concrete excluding the cost of Centring ,shuttering, finishing and reinforcement-All work puto plinth level 1:1:5:3(1 cement: 1.5 coarse sand:3 graded stone aggregate 20 mm nominal size) 3.12 M3 4688.30 14627.00
13 Reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete Thermo-Mechanically Treated bars TMTC-500-10mm dia.
TOTAL WEIGHT OF 8mm dia: - 0.00 Kg 94.50 0.00
TOTAL WEIGHT OF 12mm dia: - 280.57 Kg 92.60 25981.00
14 Suppying and fixing C.I cover with frame for manholes : 560mm diameter (heavy duty)the weight of the cover to be not less than 58kg 29.00 Nos 6918.30 200631.00
15 providing and laying non pressure NP class 3 (medium duty) R.C.C pipes 435.00 M 2903.70 1263110.00
16 Filling available excavated earth (excluding rock) in treanches,plinth , sides of foundation etc in layer not exceeding 20 cm in depth 548.10 M 123.90 67910.00
17 CARRIAGE OF MATERIAL : -
(iii) COURSE SAND - 50 KM 223.54 M3 1286.33 287546.00
18 Difference cost of materials
19 Providing and fixing of information board 1.00 Each 3200.00 3200.00
Total Amount (Including 12% GST) : - 6448715.53
Providing Amount for rate escalation in GST (12% to 18%). Multiplying factor 0.05357 Total Rs:- 345457.69
Total Amount (Including 18% GST) : - 6794173.22
SIAGNIORANGE FEE 42767.00
TOTAL 6836940.22
20 Seigniorage fee @ 10% of Basic rate
(ii) LOCAL SAND - 52.24 M3 14.17 740.24
(iii) COURSE SAND - 223.54 M3 17.58 3929.83
(iv) STONE CHIPS - 493.71 M3 54.54 26926.94
Total seigniorage fee : - 50972.14
ESTIMATE FOR CONSTRUCTION OF P.C.C ROAD AND DRAIN FROM PIYUSH KUMAR HOUSE TO KISAN BHAWAN UNDER NAGAR PANCHAYAT SHEKHOPURSARAI.
SL. NO ITEM QTY UNIT RATE AMOUNT
1 demolishing cement cocreate including disposal of material 396.72 M3 970.90 385175.00
2 Supplying and stacking at site 53mm to 22.4mm size stone 238.82 M3 883.70 211045.00
3 supplying andstacking at site moorum 238.82 M3 431.20 102979.00
4 Laying Spreading and compacting stone aggregate of specified size to WBM 238.82 M3 487.00 116305.00
5 Providing and laying in position cement concrete of specified grade exluding the cost of centring and shuttering-all work upto plinth level.1:1.5:3(1 Cement :1.5 coarse sand:3 graded stone aggregate 20 mm nominal size) 398.03 M3 5418.60 2156765.00
6 Centring and shuttering including strutting, propping etc. and removal of form for Walls (any thickness) including attached pilasters. Butteresses, plinth and string courses etc 217.50 M2 211.10 45914.00
7 Earth work in excavation in foundation trenches or drains(not exceeding 1.5 m in width or 10 sqm on plan) including dressing of sides and ramming of bottoms, lift upto 1.5 m . including getting out the excavated soil and disposal of surplus excavated soil as directed, within a lead of 50 m. 855.50 M3 383.70 328255.00
8 Supplying and Filling in plinth with local sand and under floors including, watering , ramming consolidating and dressing complete. 44.18 M3 287.30 12693.00
9 Providing designation 100 A one brick flat soling joints filled with local sand including cost of watering, taxes, royalty all complete as per building specification and direction of E/l, 567.31 M2 283.30 160719.00
10 Providing and laying in position cement concreate of specified grade excluuding the cost of centring and shuttering all work upto plinth level 1:2:4 47.58 M3 3998.10 190230.00
11 100A brick work(1:4) cement mortar 39.41 M3 5017.90 197755.00
12 Providing and laying in position specified grade of reinforced cement concrete excluding the cost of Centring ,shuttering, finishing and reinforcement-All work puto plinth level 1:1:5:3(1 cement: 1.5 coarse sand:3 graded stone aggregate 20 mm nominal size) 3.12 M3 4688.30 14627.00
13 Reinforcement for R.C.C. work including straightening, cutting, bending, placing in position and binding all complete Thermo-Mechanically Treated bars TMTC-500-10mm dia.
TOTAL WEIGHT OF 8mm dia: - 0.00 Kg 94.50 0.00
TOTAL WEIGHT OF 12mm dia: - 280.57 Kg 92.60 25981.00
14 Suppying and fixing C.I cover with frame for manholes : 560mm diameter (heavy duty)the weight of the cover to be not less than 58kg 29.00 Nos 6918.30 200631.00
15 providing and laying non pressure NP class 3 (medium duty) R.C.C pipes 435.00 M 2903.70 1263110.00
16 Filling available excavated earth (excluding rock) in treanches,plinth , sides of foundation etc in layer not exceeding 20 cm in depth 548.10 M 123.90 67910.00
17 CARRIAGE OF MATERIAL : -
(iii) COURSE SAND - 50 KM 223.54 M3 1286.33 287546.00
18 Difference cost of materials
19 Providing and fixing of information board 1.00 Each 3200.00 3200.00
Total Amount (Including 12% GST) : - 6448715.53
Providing Amount for rate escalation in GST (12% to 18%). Multiplying factor 0.05357 Total Rs:- 345457.69
Total Amount (Including 18% GST) : - 6794173.22
SIAGNIORANGE FEE 42767.00
TOTAL 6836940.22
20 Seigniorage fee @ 10% of Basic rate
(ii) LOCAL SAND - 52.24 M3 14.17 740.24
(iii) COURSE SAND - 223.54 M3 17.58 3929.83
(iv) STONE CHIPS - 493.71 M3 54.54 26926.94
Total seigniorage fee : - 50972.14
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
NIT 07 2025-26.pdf
NIT • 5.41 MB
NIT 07 2025-26.pdf
NIT • 5.41 MB
Dainik Bhaskar paper cutting.jpg
NIT • 5.71 MB
Prabhat khabar paper cutting.jpg
NIT • 2.73 MB
GR 07.xlsx
NIT • 0.02 MB
GR 07.xlsx
NIT • 0.02 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .