| # | Company | Amount | Rank | Status |
|---|---|---|---|---|
| 1 | L1₹2.1 CrAccepted-AOC | ₹2.1 Cr | L1 | Accepted-AOC L1 |
| 2 | L2₹2.1 Cr+₹10,180 (0.05%)Rejected-Finance | ₹2.1 Cr+₹10,180 (0.05%) | L2 | Rejected-Finance L2 |
Tender Value
₹2.1 Cr
EMD Value
₹2.1 L
Closing Date
29 Dec 2023, 3:00 pmClosed
Additional Collector, DRDA
DRDA, Collectorate Campus, Vengikkal, Tiruvannamalai
Construction of Bridge at Melragarambedu ADC to Navalpakkam Road at Km. 0/400 (R64) in Melnagarambedu Panchayat Cheyyar Block Package No.TVM/2023-24/17 of Tiruvannamalai District under NABARD RIDF XXIX 2023-24
2023_RDTN_397819_1
Roc.No.4845/2023/A11 Date.16.10.2023 17
Open Tender
Civil Works - Bridges
Item Wise
540 days
Cheyyar
Please refer Tender documents.
2 documents required · 2 mandatory
₹0
₹2.1 L
DRDA, Collectorate Campus, Vengikkal, Tiruvannamal
21 Jun 2024
9 Dec 2023
29 Dec 2023
9 Dec 2023
29 Dec 2023
9 Dec 2023
15 Dec 2023
Amount
Bridge
Earth work excavation in all classes of soil except hard rock requiring blasting and depositing on bank as per SS20B with all leads and lifts and all other incidental charges such as bailing out water shoring strutting, walling and forming protective bunds whereever necessary etc., complete as per relevent standard specification for DRESSING THE BED UPTO SILL LEVEL.
Earthwork excavation in all classes of soil except hardrock requiring blasting and depositing on bank with all leads and lifts as per SS20B, including cost of all labour, equipments and all incidental charges such as Bailing out water, providing and maintaining necessary coffferdams, sheeting, shoring, bracing and their subsequent removal, removal of all logs, stumps, grubs and other deleterious matter and obstructions, trimming bottom of excavation backfilling, and clearing the site and disposal of all surplus materials etc., complete as per relevant standard specifications for FOUNDATION (OPEN FOUNDATION, RAFT FOUNDATION, CUT OFF WALL,FLEXIBLE &RIGID APRON)UNDER ABUTMENTS & PIERS BELOW SILL LEVEL.
Vibrated Cement Concrete of grade M 15 (Nominal Mix 1:2:4) using 20mm ISS size HBG metal including cost and conveyance of all materials to site including cost of cement at site including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete, working at depths, tools and plants and maintaining of protective bunds, cofferdams, shoring, strutting etc., complete as per relevant standard specifications for foundation concrete (below footing, below raft foundation, below retaining wall)
Vibrated Plain Cement Concrete of grade M 20 (Design Mix 1:1.5:3) using ISS size HBG metal including cost and conveyance of all materials to site including cost of cement at site including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete, working at depths, tools and plants and maintaining of protective bunds, cofferdams, shoring, strutting etc., complete as per relevant standard specifications for cut off wall concrete
Vibrated Plain Cement Concrete of grade M 20 (Design Mix 1:1.5:3) using ISS size HBG metal including cost and conveyance of all materials to site including cost of cement at site including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete, working at depths, tools and plants and maintaining of protective bunds, cofferdams, shoring, strutting etc., complete as per relevant standard specifications for Rigid apron
Vibrated Cement Concrete of grade M20 design Mix, using 20mm & 12mm ISS size HBG graded metal including cost and conveyance of all materials to site including cost of cement at site including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete , working at depths , tools and plants and maintaining of protective bunds, cofferdams, shoring, strutting etc., complete as per relevant standard specifications, for FOOTINGS OF ABUTMENT, PIERS AND WINGS BELOW SILL LEVEL.
Vibrated Cement Concrete of grade M20 Nominal Mix using 20mm & 12mm ISS size HBG metal including cost and conveyance of all materials to site including cost of cement at site including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete , working at depths , tools and plants and including all other incidental charges etc; complete as per relevant standard specifications, for SUBSTRUCTURE OF ABUTMENTS, WINGS, AND PIERS ABOVE SILL LEVEL.
Vibrated Reinforced Cement Concrete of grade M30 design mix using ISS 20 & 12mmsize HBG graded metal including cost and conveyance of all materials to site including cost of cement at site including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete , working at depths , tools and plants including all other incidental charges etc; complete as per relevant standard specifications, for DIRT WALL CUM BED BLOCK OVER ABUTMENTS AND BED BLOCK OVER PIERS, -
Providing and fixing seepage pipes of 100mm dia. PVC pipes of required lengths for abutments and wings including cost and conveyance of all materials to work site, cost and labour for 900mm dia. semi-spherical back fill arrangements with 100mm size broken granite chips at the periphery and labour charges for fixing, etc., to drain of the backfill IN THE ABUTMENTS AND WINGS, -
Providing and fixing KRAFT PAPER for full width of seating of deck slab and including cost and conveyance to work site, labour charges for fixing the same in the correct position and all other incidental charges etc., complete.
Vibrated Reinforced Cement Concrete of grade M30 design mix using ISS 20 & 12mmsize HBG graded metal including cost and conveyance of all materials to site including cost ofcement at site including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete , working at depths , tools and plants including all other incidental charges etc; complete as per relevant standard specifications, for DECK SLAB.
Providing filter media behind the abutments and wings with clean III graded material 53mm to 5.6mm to 600mm thick and well compacted in layers with smaller sized towards the soil and bigger size towards the wall including cost and conveyance to work site including all labours and other incidental charges including hire charges for tools and plants employed etc., for filter media as per MOST's (Roads Wing) specifications for Roads and Bridges " Fourth Revision Cl. 309-3-2-13 and 305 -4 4 etc., complete.
Filling behind Abutments and wings with clean gritty gravel including cost and conveyance of gravel to worksite,laying,handling charges and filling in layers,tamping under optimum moisture content to get the maximum density including watering,with all leads for water and all other incidental charges etc,complete for filling behind the abutment and wings.
Providing and fixing PVC EXPANSION JOINT in between deck slabs over abutment and pier as shown in the drawing including cost and conveyence of expansion joints including shalimar pad and joint sealent etc, complete.
Supply and fabrication of Fe-500 steel required for all RCC items of works involved in the schedule cost of steel at site fabrication,labour charges for cleaning the rods straightening, cutting, bending, tying grills, including overlapping to the required length whenever necessary and placing the reinforcement in position as specified in the drawings,including cost of binding wire, provision of spacer bars, cover blocks and all other incidental charges etc,complete,Fe-500 grade MT
Vibrated Cement Concrete of grade M 15 (Nominal Mix 1:2:4) using 20mm ISS size HBG metal including cost and conveyance of all materials to site including cost of cement at site including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete, working at depths, tools and plants and maintaining of protective bunds, cofferdams, shoring, strutting etc., complete as per relevant standard specifications for BASECOURSE BELOW APPROACH SLAB
Vibrated reinforced cement concrete M30 design mix using ISS graded hard granite broken metal including cost and conveyance of all materials to site including cement at site including labour charges for mixing, laying, curing concrete, working at heights, hire charges for tools and plants, including all other incidental changes etc., complete for APPROACH SLAB.
Vibrated Cement Concrete M20grade Design Mix using 20mm & 12mm ISS size hard granite broken metal including cost and conveyance of all materials to site and cement at sitel including labour charges for mixing,transporting, laying, and curing concrete,working at heights for parapet wall over wings
Vibrated cement Concrete M30 design mix using ISS size HBG graded metal including cost and conveyance of all materials to worksite and cement at site including all labour charges for fixing concrete, laying, vibrating, hire charges for tools and plants, compacting, curing with all leads for soft water, including all other incidental charges,formwork,cost of premoulded expansion joints and fixing the same in position etc., complete for wearing cost of 75mm uniform thickness over deck slab and approach slab.
Vibrated Reinforced Cement Concrete M25 grade, Design Mix Mix, using 20mm & 12mm ISS size hard granite broken graded metal including cost and conveyance of all materials to site and cement at site including labour charges for mixing, transporting, laying, and curing concrete, working at heights, hire charges for tools and plants, including all other incidental charges,etc.,complete as per standard specification for Hand Rail
Providing and fixing of G.I Drainage Spouts 100mm dia as per GOI drawing SD/205 with grating arrangements at top as shown in the drawing and 100mm dia drainage spout projecting atleast 300 mm beyond the bottom of deck slab as shown in the drawing including cost and conveyance of Galvanised iron pipes and flats and fixing them in position etc,complete as per cl 2705 of MORT & H specification. (V Revision)
Whitewashing for Abutment and Pier Substructure using two coats of freshly burnt Shell lime
Enamel painting for Crashbarrier and handrail using two coat of enamel paint
Providing and making Gabion structure with Mechanically Woven Double Twisted Hexagonal Shaped Wire Mesh Gabion Boxes as per IS 16O14 -2O12, MORTH Clause 2500, of requjred size, Mesh Type 10 x 12 (D=100mm with toterance of + 2%) Zinc Coated, Mesh Wire diameter 3.0 mm, mechanically edged / selvedged with partitions at every 1m interval and shall have minimum 10 numbers of openings per meter of mesh perpendicular to twist, tying with lacing wire of diameter 2.2mm, supplied @3% by weight of Gabion boxes, filled with boulders with least dimension of 200 mm, as per drawing, all complete as per direction of Engineer-in-Charge
Diversion road
Excavation including removal and satisfactory disposal of all materials necessary for the construction of road way and side drains in accordance with specifications and the lines , grades and cross sections shown in the drawings or as indicated by the Engineer using Carted Eath with a lead of 2km for formation of Approach Road.
Providing and Laying Granular Sub base as per table No 400-1/400-2 and Grading III of MORTH Revision IV with and any other Granular material or a combination those of for 150 mm thick to give a CBR of 20 on prepared sub grade in accordance with the requirements of the specifications For Sand, Gravel & 6 mm Aggregate Mix
Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam (WMM) specification including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 250mm thick with pavers in SubBase/Base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete.
Supply and fixing of NP 3 class RCC 900 mm dia. pipes supplied by the Contractor at his own cost specified below confirming to IS 458 / 1989 cost of pipe as a finished work including all other incidental charges, testing charges including loading and unloading transport and delivery in good condition at work site as directed by the departmental officers etc., complete for culvert.
Approach road
Excavation including removal and satisfactory disposal of all materials necessary for the construction of road way and side drains in accordance with specifications and the lines , grades and cross sections shown in the drawings or as indicated by the Engineer using the carted earth with a lead of 2km for formation of Approach Road.
98% COMPACTION
100% CO0MPACTION
Providing and Laying Granular Sub base as per table No 400-1/400-2 and Grading III of MORTH Revision IV with and any other Granular material or a combination those of for 150 mm thick to give a CBR of 20 on prepared sub grade in accordance with the requirements of the specifications For Sand, Gravel & 6 mm Aggregate Mix
Providing and laying spreading and compacting graded stone aggregate to Wet Mix Macadam (WMM) specification including premixing the material with water at OMC in machanical mix plant carriage of mixed material by tipper to site laying in uniform layers 250mm thick with pavers in SubBase/Base course on well prepared surface and compacting with vibratory roller to achieve the desired density including cost of material,labour charges, rentals for machinery, fuel and all other incidental charges etc., complete.
Providing and laying Prime coat over the WMM surface using 7.00 Kg of bituminous emulsion) for 10 sqm. Including cost of bituminous emulsion( SS-1) including labour charges for preparing the surface for laying tack coat and for applying required quantity of bituminous emulsion by mechanical sprayer including hire and fuel charges for all tools and plants employed etc., complete as per clause 503 of MOST specification.
Providing and laying Tack coat over the Prime WMM surface using 2.50 Kg of bituminous emulsion) for 10 sqm. Including cost of bituminous emulsion( RS-1) including labour charges for preparing the surface for laying tack coat and for applying required quantity of bituminous emulsion by mechanical sprayer including hire and fuel charges for all tools and plants employed etc., complete as per clause 503 of MOST specification.
Providing and laying Premix Carpet with Seal Coat Type -A to 20 mm thick using 0.18cum of 13.2mm, 0.09 cum of 11.20mm and .09cum of 6.70mm with 23.232 Kgs of VG 30 Bitumen for premixing per 10sqm including cost and conveyance of all materials to CMP site, heating the bitumen and aggregate to required temperature and mixing them in required temperature in Central Hot Mix Plant 20-30T capacity, conveying the mix by tipper trucks to paver site, spreading the mix to uniform thickness of 20mm with mechanical paver to the specified grades and cross section and consolidated by 8-10T vibratory/pneumatic roller to the required density etc., including labour for attending to paver to site, hire & fuel charges for 20-30T CMP with bitumen boiler, tipper trucks, paver finisher, vibratory/pneumatic roller and all other tools and plants required, including fuel and other incidental charges etc., complete .- (Using Plastic Waste)
Retaining Wall
Earthwork excavation in all classes of soil except hard rock requiring blasting and depositing on bank with all leads and lifts as per SS20B, including cost of all labour, equipments and all incidental charges such as baling out water, providing and maintaining necessary cofffer dams, sheeting, shoring, bracing and their subsequent removal, removal of all logs, stumps, grubs and other deleterious matter and obstructions, trimming bottom of excavation, backfilling, and clearing the site and disposal of all surplus materials etc., complete as per relevant standard specifications for FOUNDATION UNDER RETAING WALL.
Filling inside the Foundation with clean coarse sand including cost and conveyance of gravel to worksite, laying, handling charges and filling in layers, tamping under optimum moisture content to get the maximum density including watering with all leads for water and all other incidental charges etc., complete for filling inside the Foundation.
Vibrated Cement Concrete of Grade M 15 Nominal Mix using 20 mm size HBG metal including cost and conveyance of all materials to site including cost of cement at site including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete, working at depths, tools and plants and maintaining of protective bunds, cofferdams, shoring, strutting etc., complete as per relevant standard specifications for FOUNDATION BELOW.
Vibrated Cement Concrete Grade M 20 Design Mix using 20 & 12 mm ISS size HBG graded metal including cost and conveyance of all materials to site and cement at site but excluding cost and fabrication of steel but including form work and centering soft water labour charges for mixing, transporting, placing in position, vibrating and compacting finishing and curing concrete working at heights, hire charges for tools and plants, including all other incidental charges etc., complete as per standard specifications for RETAINING WALL FOUNDATION.
Vibrated Cement Concrete of Grade M 20 Design Mix using 20 mm & 12 mm ISS size HBG metal including cost and conveyance of all materials to site including cost of cement at site including cost of formwork, soft water, labour charges for mixing, transporting, laying and curing concrete , working at depths , tools and plants and including all other incidental charges etc; complete as per relevant standard specifications, for SUBSTRUCTURE OF RETAINING WALL ABOVE SILL LEVEL -
Providing and fixing seepage pipes of 100 mm dia. PVC pipes of required lengths for Retaining Wall including cost and conveyance of all materials to work site and labour charges for fixing, complete
Dismantling of Existing Structure
Dismantling the existing Plain Cement Concrete in the existing causeway and clearing away from the work site and carefully stacking the useful materials for reuse on the road side as directed by the departmental officers including all labour and incidental charges etc., complete.
Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts and lead of 1000 m - Substructure.
Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of masonry, cement concrete, wood work, steel work, including T&P and scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts and lead of 1000 m as - Superstructure.
GST Amount for providing Service to Government Contract Works for the above Construction & Maintenance Works. { GST Amount is the Total GST Amount for overall quoted amount (Both Construction and Maintenance) above this row in column "BB" for all works in this package}
KMV Constructions
stage.html
html • 0.04 MB
tech_bid_open.pdf
tech_eval.pdf
boq_comp_chart.xlsx
xlsx
fin_eval.pdf
aoc.pdf
Tap a document below to read it instantly. You can also download everything as a ZIP if you prefer.
details.html
html • 0.04 MB
Download all tender documents and submit your bid
Disclaimer: TenderKart has made every reasonable effort to ensure that the information on this page is accurate and authentic, however it cannot be held liable for any third-party claims or losses or any damages. TenderKart makes no warranty, expressed or implied, as to the results obtained from the use of this information. If you notice any error or omission, please let us know at .